| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Nov 18, 2022 | 78372 | JacksonWilliamsonDistrict 9 | Intersection improvements, pavement widening, HMA resurfacing and a multi-use path on IL 13 from the Williamson County line to east of Spillway Road. | — | Executed | E. T. Simonds Construction Company $6,023,216 · | ||
| Nov 18, 2022 | 78719 | PopeDistrict 9 | Bridge replacement project on IL 145, approximately 2.3 miles south of the IL 145 / IL 146 intersection. (SN 076-0024) | — | Executed | E. T. Simonds Construction Company $4,417,453 · | ||
| Nov 18, 2022 | 78893 | FranklinDistrict 9 | Replacement of 5 box culverts on IL 34 between Benton and Thompsonville. | — | Executed | Sierra Bravo Contractors, LLC $1,395,537 · | ||
| Nov 18, 2022 | 78930 | FranklinDistrict 9 | Joint reconstruction, hydro-scarification with microsilica concrete overlay, bearing replacement and approach Proposed improvements consist of joint reconstruction, hydro-scarification with microsilica concrete overlay, bearing replacement and approach slab repair on SN 028-0063, W. Webster St. over 1-57 in Franklin County. | — | Executed | E. T. Simonds Construction Company $453,453 · | ||
| Nov 18, 2022 | 78957 | WilliamsonDistrict 9 | This project involves the construction of a mid-block crosswalk with ADA ramps, median refuge island, rectangular rapid flashing beacons, highway lighting and appropriate pavement markings on IL 13 at Ray Fosse Park in Marion IL. | — | Executed | Samron Midwest Contracting, Inc. $246,246 · | ||
| Nov 18, 2022 | 78958 | FranklinDistrict 9 | Replacement of the pumps, piping, back-up and electrical controls of the pump station along I-57 at the West Frankfort interchange. | — | Active | Haier Plumbing and Heating, Inc. $3,343,253 · | ||
| Nov 18, 2022 | 78962 | FranklinDistrict 9 | Replacement of the sanitary sewer lift station and grinder, electrical service, alarm system, driveway pavement and water service at northbound I-57 Rend Lake Rest Area, 2.4 miles north of the IL 14 / Benton interchange. | — | Active | Lake Contracting, Inc. $434,024 · | ||
| Nov 18, 2022 | 85728 | Rock IslandDistrict 2 | Removal of existing steel pile retaining walk and construction of a 330' drilled shaft foundation retaining wall supporting concrete columns and web walls with HMA pavement removal and replacement, aggregate shoulders, reshaping of ditches, and grading along county highway 11 in Rock Island County . | — | Executed | General Constructors Inc. of the Quad Cities $988,253 · | ||
| Nov 18, 2022 | 87768 | GrundyDistrict 3 | Replace superstructure carrying Brisbin Road over Collins Run Creek, 1.4 miles south of Minooka. | — | Executed | D. Construction, Inc. $787,230 · | ||
| Nov 18, 2022 | 87810 | LaSalleDistrict 3 | Construction of a soldier pile wall and slope stabilization along North 2550th Road from North 2551st Road to a point approximently 0.25 mile east along 2550th Road in the Peru Road District. | — | Executed | D. Construction, Inc. $1,662,869 · | ||
| Nov 18, 2022 | 89796 | FultonDistrict 4 | Replace the bridge carrying CH 2 over Otter Creek, 4 miles north of Astoria. | — | Executed | Stark Excavating, Inc. $2,199,397 · | ||
| Nov 18, 2022 | 93796 | ScottDistrict 6 | Replace the bridge carrying CH 12 over Mauvaise Terre Creek, 1.5 miles east of Exeter. | — | Executed | County Contractors, Inc. $2,196,562 · | ||
| Nov 18, 2022 | 97781 | MarionDistrict 8 | HMA surface course and bind course on a processed modified soil cement base, also culvert and storm replacement on Heinzmann Road from IL 161 extension to Kell Road. | — | Executed | Guinzy Construction,Inc. $1,647,597 · | ||
| Nov 18, 2022 | 97792 | MadisonDistrict 8 | .52 miles of pavement patching, HMA removal and resurfacing, drainage repairs, and ADA curb ramps on State Street from Rozier Street to Logan Street in Alton. | — | Executed | Charles E. Mahoney Co. $672,894 · | ||
| Nov 18, 2022 | 99671 | FranklinDistrict 9 | .55 miles of PCC and HMA pavement road reconstruction, concrete curb and gutter, and storm sewer construction on Wastena Street from IL 37 to South McLeansboro Street in Benton. | — | Executed | Samron Midwest Contracting, Inc. $1,598,362 · | ||
| Nov 18, 2022 | 99696 | MassacDistrict 9 | Resurfacing CH 5 from CH 4 to the east city limits of Joppa. | — | Executed | Southern Illinois Asphalt Co., Inc. $640,826 · | ||
| Jan 20, 2023 | 61H91 | DuPageDistrict 1 | HMA surface removal and replacement along North York Street from Crestview Avenue to Grand Avenue, with widening and traffic signal modernization at the Belden Avenue/Idustrial Drive intersection. Work includes raised medians, ADA improvements, Curb and Gutter removal and reconstruction, storm sewers, landscaping, and pavement markings all in the city of Elmhurst. | — | Executed | Builders Paving, LLC $3,125,808 · | ||
| Jan 20, 2023 | 61H95 | KaneDistrict 1 | Widening, reconstruction, and extending Dauberman Road on new alignment south of US 30, construction of bridges for BNSF Railway and over US 30, reconstruction of US 30, roadway improvements to Granart Road, Construction of a connector road for the Dauberman/US 30 interchange, new traffic signals, and a bike trail from US 30 to Granart Road. | — | Executed | Curran Contracting Company $21,981,771 · | ||
| Jan 20, 2023 | 61H99 | WillDistrict 1 | Reconstruction of Crete Road from Richton Road to Exchange Street in Crete. | — | Executed | Iroquois Paving Corporation $2,196,658 · | ||
| Jan 20, 2023 | 61J04 | CookDistrict 1 | Pavement reconstruction on National Parkway from Golf Road (IL58) to 0.1 mile south of American Lane, and the construction of a roundabout at American Lane, in schaumburg. | — | Executed | Plote Construction, Inc. $8,749,122 · | ||
| Jan 20, 2023 | 61J10 | CookDistrict 1 | Replace the Clearmont pedestrian bridge over Salt Creek in Elk Grove Village. | — | Executed | Lorig Construction Company $2,797,341 · | ||
| Jan 20, 2023 | 61J11 | DuPageDistrict 1 | Resurface Montgomery Road from Frontenac Street to IL 59 in Aurora | — | Executed | K-Five Construction Corporation $831,305 · | ||
| Jan 20, 2023 | 61J12 | DuPageDistrict 1 | Widening and resurfacing the intersection of Devon Avenue and Park Boulevard and the intersection of Park Boulevard and Pierce Road in Itasca. | — | Executed | A Lamp Concrete Contractors, Inc. $1,996,347 · | ||
| Jan 20, 2023 | 61J13 | DuPageDistrict 1 | Resurfacing Liberty Street from Commons Drive to IL 59 in Aurora. | — | Executed | K-Five Construction Corporation $977,658 · | ||
| Jan 20, 2023 | 61J17 | CookDistrict 1 | HMA removal and replacement with patching, minor utility structure repairs, curb and gutter, sidewalk, ADA improvements and striping along Wilmetter Ave. from Ridge Road to Green Bay Road in Willmette. | — | Executed | J. A. Johnson Paving Company $1,139,610 · | ||
| Jan 20, 2023 | 61J18 | CookDistrict 1 | Construct Des Plaines River Trail from north of Touhy Avenue to Devon Avenue in Park Ridge. | — | Executed | Martam Construction Incorporated $1,154,616 · | ||
| Jan 20, 2023 | 61J19 | CookDistrict 1 | HMA resurfacing and contruction of HMA shared-use path with pavement narrowing and widening, sidewalks, concrete curb and gutter, landscaping, retaining wall, and traffic signal enhancements along Oakton Street in Des Plaines. | — | Executed | Dunnet Bay Construction Company $2,137,222 · | ||
| Jan 20, 2023 | 61J20 | CookDistrict 1 | HMA removal and resurfacing with pavement patching, curb and gutter, sidewalks, and landscaping on Harrison Street from Bellwood Avenue to 25th Street in Bellwood. | — | Executed | J. A. Johnson Paving Company $856,000 · | ||
| Jan 20, 2023 | 61J21 | CookDistrict 1 | HMA resurfacing, curb and gutter, sidewalk repair, drainage structure adjustments, parkway restoration along Shabbona Drive from Sauk Trail to Indianwood Boulevard, in Park Forest. | — | Executed | Iroquois Paving Corporation $2,392,849 · | ||
| Jan 20, 2023 | 61J23 | CookDistrict 1 | HMA removal and replacement with Curb and gutter, sidewalks, structure adjustments, pipe culvert replacement, and landscaping on Oak Park Avenue in Chicago Ridge. | — | Executed | Lindahl Brothers, Inc. $497,710 · | ||
| Jan 20, 2023 | 61J24 | CookDistrict 1 | HMA resurfacing with Class D Patches, driveway removal and replacement, curb and gutter, sidewalk, drainage and utility structure reconstruction, and detector loop replacement on state street from US 6 to Sibley Boulevard in South Holland. | — | Executed | Gallagher Asphalt Corporation $1,866,271 · | ||
| Jan 20, 2023 | 62A53 | LakeDistrict 1 | Dry Land Bridge reconstruction, roadway widening, resurfacing and ADA improvement for IL 132 (Grand Avenue) at (2,811-Ft) The proposed improvement consists of Dry Land Bridge reconstruction, roadway widening, resurfacing and ADA improvement for IL 132 (Grand Avenue) at East of Cedar Lake Road located in the Village of Lake Villa in Lake County. | — | Executed | Dunnet Bay Construction Company $8,715,212 · | ||
| Jan 20, 2023 | 62G26 | LakeDistrict 1 | (5.35-Mile) Design, Standard and Smart overlay resurfacing on IL Rte. 173 (Rosecrans Rd.) from Brown Ave. to Hunt Club Rd. in the Village of Antioch, Lake County. | — | Executed | Payne & Dolan, Inc. $3,296,603 · | ||
| Jan 20, 2023 | 62H02 | KaneDistrict 1 | (300-Ft) Culvert replacement, retaining wall construction, railroad track re-alignment, roadway resurfacing, pavement marking and ADA ramp reconstruction for IL 31 Culvert over Ditch located in the Village of South Elgin in Kane Co. | — | Executed | Martam Construction Incorporated $1,536,744 · | ||
| Jan 20, 2023 | 62K74 | CookDistrict 1 | This is a Bridge Deck overlay, bridge joint repair, pavement patching, overhead sign replacement, ITS loop detectors and lighting project along the inbound and inversible lanes on I-90 (Kennedy Expy from I-94 (Edens Expy) to Hubbard Street in the City of Chicago for a total of 40,320 Ft (7.63-Miles). | — | Executed | Dunnet Bay Construction Company & Martam Construction JV $69,946,701 · | ||
| Jan 20, 2023 | 62K77 | DuPageDistrict 1 | (1,254-Ft) Deck replacement, replacement of exterior beams, structural repairs to existing beams and substructure, guardrail replacement, and resurfacing from Woodland Ave. and Meadow Lane. The project includes a flush 5 ft sidewalk on both sides and traffic signal interconnect fiber will be replaced from St Charles Road to IL 64 (North Ave.) | — | Executed | Herlihy Mid-Continent Company $3,360,385 · | ||
| Jan 20, 2023 | 62M43 | DuPageWillDistrict 1 | (4,199-Ft) Designed Overlay, New Shoulders on Joliet Rd from I-55 to Sherman Road. The project also includes Diamond Grooving on I-55 NB off ramp to I-355. This Project is in the Villages of Romeoville, Bollingbrook and Woodridge. | — | Executed | P. T. Ferro Construction Co. $2,288,051 · | ||
| Jan 20, 2023 | 62N69 | LakeDistrict 1 | (5.59-Mile) Smart overlay and ADA improvements, on IL 120 (0.2 Mile East of IL 60 0.1 Mile East of Alleghany Road) in the villages of Volo, Round Lake, Round Lake Park, Hainseville, Grayslake, and Mundelein in the townships of Avon, Grant, Wauconda, and Freemont in Lake County. | — | Executed | Peter Baker & Son Co. $2,492,285 · | ||
| Jan 20, 2023 | 62N79 | CookDistrict 1 | (4.03 mi); Smart Overlay and ADA Improvements on Roosevelt Rd from Des Plaines Av to Belt Railway. This project is located in the Village of Forest Park, Village of Oak Park, City of Berwyn, Town of Cicero and the City of Chicago in Cook Co. | — | Executed | MAT Construction Leasing, Inc. $3,816,869 · | ||
| Jan 20, 2023 | 62R80 | CookDistrict 1 | (1.04-Mile) Standard Overlay project on Des Plaines Ave from Madison St to Roosevelt Road located in the Village of Forest Park in Cook County. | — | Executed | Arrow Road Construction Co. $1,473,887 · | ||
| Jan 20, 2023 | 62T54 | CookDistrict 1 | Installation of new fiber optic cable, network switches, PTZ cameras, at 82 signalized intersections located along Barrington Rd from IL-72 to US-20, US-20 from Bartlett Rd to Springfield Dr, IL-19 from Bartlett Rd to Wright Blvd, IL-62 from Penny Rd to East of New Wilke Rd, and Meacham Rd from IL-62 to IL-72 | — | Executed | H & H Electric Co. $3,452,216 · | ||
| Jan 20, 2023 | 62T89 | VariousDistrict 1 | Dead tree removal located within the right-of-way limits of state-maintained routes located in District One (counties of Cook, DuPage, Kane, Lake, McHenry, and Will). | — | Executed | Homer Tree Service, Inc. $550,775 · | ||
| Jan 20, 2023 | 62T92 | VariousDistrict 1 | The proposed improvement is located along various expressways and arterial routes at various locations in District One. | — | Executed | MYS, Incorporated $524,210 · | ||
| Jan 20, 2023 | 62T96 | DuPageDistrict 1 | Bridge deck patching and bridge joint reconstruction on FAI 290 (WB) ramp to SB 1-355 located in the Village o (2546-Ft) Improvement consists of Bridge deck patching and bridge joint reconstruction on FAI 290 (WB) ramp to SB 1-355 located in the Village of Addison and Medinah in DuPage County. | — | Executed | Alliance Contractors, Inc. $915,316 · | ||
| Jan 20, 2023 | 62U02 | VariousDistrict 1 | Installing signs at new locations and repairing existing damaged signs on a work order basis throughout Distri The work to be completed under this contract consists of installing signs at new locations and repairing existing damaged signs on a work order basis throughout District 1. | — | Executed | ROADSAFE TRAFFIC SYSTEMS, INC. $374,700 · | ||
| Jan 20, 2023 | 62U04 | CookDistrict 1 | (2100-Ft) SMART overlay project on IL Route 43 from Sanitary and Ship Canal to Hanover Street, located in Village of Summit, Village of Forest View, and City of Chicago in Cook County. | — | Executed | MAT Construction Leasing, Inc. $1,284,283 · | ||
| Jan 20, 2023 | 62U15 | CookDistrict 1 | A full bridge painting of 1-57 at the 1-80 Interchange in the City of Calumet City in Cook County This improvement consists of a full bridge painting of 1-57 at the 1-80 Interchange in the City of Calumet City in Cook County. | — | Executed | Capital Industrial Services $1,383,300 · | ||
| Jan 20, 2023 | 62U16 | CookDistrict 1 | Cleaning and painting existing steel on the structures No The improvement consists of cleaning and painting existing steel on the structures No. 1: IL-394 under Glenwood Dyer Road; No. 2: IL-394 under Glenwood Lansing Road, in Villages of Glenwood and Lynwood, in Cook County. | — | Executed | Capital Industrial Services $1,013,300 · | ||
| Jan 20, 2023 | 62U24 | CookDistrict 1 | 3 locations along the eastbound direction of the Kennedy Expressway (I-90/94 EB) at the structures 2,112-Ft) Bridge Painting and Lighting Replacement. This improvement consists of 3 locations along the eastbound direction of the Kennedy Expressway (I-90/94 EB) at the structures; Grand Ave - (SN 016-2048), Green St.- (SN 016-0136), Hubbard St.- (SN 016-2050) and Metra Railroad, Kinzie St and Wayman St (SN 016-2020). All are located within Chicago, Cook County, Illinois. | — | Executed | Capital Industrial Services $17,773,330 · | ||
| Jan 20, 2023 | 62U50 | VariousDistrict 1 | Removal and replacement of impact attenuators and sand module replacement on a work order various State mainta The work to be completed under this contract consists of removal and replacement of impact attenuators and sand module replacement on a work order various State maintained expressway and arterial routes within the counties of Cook, DuPage, Will, Lake, McHenry, and Kane. | — | Executed | ROADSAFE TRAFFIC SYSTEMS, INC. $2,554,255 · | ||
| Jan 20, 2023 | 62U54 | WillDistrict 1 | The pickup, removal and disposal of debris/litter on a work order basis located on 1) FAI 94: I-94 from I-90/9 Project consists of the pickup, removal and disposal of debris/litter on a work order basis located on 1) FAI 94: I-94 from I-90/94 (Dan Ryan Expwy) to I-80; 2) FAP 341: Stony Island from I-94 to US 12 (95th St); 3) FAU 1574: 103rd St from Cottage Groove to Stony Island in Cook County. | — | Executed | The Final Connection, Inc. $198,656 · | ||
| Jan 20, 2023 | 64N68 | Rock IslandDistrict 2 | Replace highway lighting at the interchange of 1-280 with IL 92. | — | Executed | Tri-City Electric Company of Iowa $288,884 · | ||
| Jan 20, 2023 | 64N69 | Rock IslandDistrict 2 | Replace highway lighting at the interchange of IL 92/IL 5 with IL 84, near Carbon Cliff. | — | Executed | Tri-City Electric Company of Iowa $229,250 · | ||
| Jan 20, 2023 | 64P43 | Rock IslandDistrict 2 | Pavement patching, cold milling, HMA resurfacing on IL 5 and expansion joint replacement, deck patching, HMA wearing surface with waterproofing membrane system and misc. other bridge repairs on: SN 081-0095 and 081-0096 carrying IL 5 over 27th Street, and SN 081-0097 and 081-0098 carrying IL 5 over I-74. | — | Executed | Valley Construction Co. $7,037,577 · | ||
| Jan 20, 2023 | 64R48 | CarrollDistrict 2 | Deck repair, and installation of deck concrete wearing surface including approaches on SN 008-0042 carrying IL 78 over East Plum River, 3.4 miles South of JoDaviess County line. | — | Executed | Sjostrom & Sons, Inc. $606,592 · | ||
| Jan 20, 2023 | 64R49 | BooneDistrict 2 | Deck repair, slope wall repair and microsilica overlay on SN 004-0016 carrying IL 76 over Beaver Creek, 2.5 mi South of IL 173. | — | Executed | Sjostrom & Sons, Inc. $586,034 · | ||
| Jan 20, 2023 | 64R54 | LeeDistrict 2 | Expansion joint replacement, miscellaneous repairs and deck concrete wearing surface on SN 052-0031 carrying US 30 over UP RR, 0.9 miles East of Whiteside County line. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $699,832 · | ||
| Jan 20, 2023 | 64R78 | VariousDistrict 2 | Guardrail and fence repairs along State maintained route in District 2. | — | Executed | |||
| Jan 20, 2023 | 64R79 | VariousDistrict 2 | Roadside restoration of Right-of-Way turf damage caused by motorists along State maintained routes within District 2. | — | Executed | O'Brien Civil Works, Inc. $68,120 · | ||
| Jan 20, 2023 | 64S17 | BooneCarrollDistrict 2 | Bridge deck sealing of 3 structures in Boone County and 11 structures in Carroll County. | — | Executed | M & M Concrete, Inc. $14,531 · | ||
| Jan 20, 2023 | 64S18 | HenryDistrict 2 | Bridge deck sealing of 30 structures in Henry County. | — | Executed | All States Painting, Inc. $34,199 · | ||
| Jan 20, 2023 | 64S19 | VariousDistrict 2 | Bridge deck sealing of 10 structures in Lee County, 5 structures in Ogle County and 4 structures in Winnebago County. | — | Executed | All States Painting, Inc. $28,999 · | ||
| Jan 20, 2023 | 66824 | DeKalbDistrict 3 | This project is located in Clinton Township, approximately 40 feet north of the intersection with US 30 (2.0 mile east of Waterman) in DeKalb County. | — | Executed | Herlihy Mid-Continent Company $431,778 · | ||
| Jan 20, 2023 | 66M66 | LaSallePutnamDistrict 3 | This project consists on performing Bridge Decks Concrete Sealing with the parapets/curbs on various routes at various location throughout LaSalle and Putnam Counties. | — | Executed | All States Painting, Inc. $169,800 · | ||
| Jan 20, 2023 | 66M73 | LaSalleDistrict 3 | Crack routing and filling as well as pavement marking This project is located on FAP 68 (IL 23) and FAP 623 (US 6). It consists of crack routing and filling as well as pavement marking. | — | Executed | Freehill Asphalt, Inc. $136,066 · | ||
| Jan 20, 2023 | 66N02 | IroquoisDistrict 3 | Bridge Painting at SN 038-0082, 2.62 miles South of IL 54 (Onarga). | — | Executed | Three Star Painting, Inc. $261,241 · | ||
| Jan 20, 2023 | 66N03 | IroquoisDistrict 3 | Bridge Painting at SN 038-0032, 2.1 mi. East of US 45 and SN 038-0033, 3.1 mi. East of US 45. | — | Executed | ERA-Valdivia Contractors, Inc. $248,590 · | ||
| Jan 20, 2023 | 68E42 | TazewellDistrict 4 | 0.47 miles, Bridge Replacement on I-155 over Indian Creek near Hopedale. | — | Executed | Stark Excavating, Inc. $8,247,342 · | ||
| Jan 20, 2023 | 68G91 | KnoxDistrict 4 | Bridge Preservation on S.N. 048-0080 over Spoon River, S .N. 048-0085 and S.N. 048-0086 over Cadwell Creek (2 locations) and S .N. 048-0089 over Branch of Brandywine creek. | — | Executed | Path Construction Company, Inc. $1,898,891 · | ||
| Jan 20, 2023 | 68H37 | VariousDistrict 4 | Tree removal at various locations within District 4. | — | Executed | Mosley Construction 1, LLC $93,770 · | ||
| Jan 20, 2023 | 70B79 | ChampaignDistrict 5 | Bridge deck overlay, Saline Branch 1 mile West of St. Joseph. | — | Executed | Stark Excavating, Inc. $514,629 · | ||
| Jan 20, 2023 | 70G33 | VariousDistrict 5 | 567.5 miles of spraying, approximately 2004 acres on state right-of-way along US 51 and interstate routes including interchanges in Champaign, Dewitt, Mclean, Piatt and Vermilion Counties. | — | Executed | The Daltons Inc. $133,427 · | ||
| Jan 20, 2023 | 72043 | VariousDistrict 6 | Bridge washing at various major river crossings on various routes in District 6. | — | Executed | All States Painting, Inc. $158,000 · | ||
| Jan 20, 2023 | 72063 | SangamonDistrict 6 | Painting SN 084-0142 carrying County Highway 10 over I-72 at the New Berlin overhead. | — | Executed | Eagle Painting & Maintenance Company, Inc. $336,500 · | ||
| Jan 20, 2023 | 72067 | LoganDistrict 6 | Painting SN 054-0072 carrying Township Road 79 over I-155, 1.9 miles north of I-55. | — | Executed | All States Painting, Inc. $222,900 · | ||
| Jan 20, 2023 | 72069 | SangamonDistrict 6 | Patching on I-55 from the Montgomery County line to the Logan County line and on I-72 from the Morgan County line to the Macon County line. | — | Executed | G. M. Sipes Construction, Inc. $671,886 · | ||
| Jan 20, 2023 | 72071 | BrownDistrict 6 | 6.8 miles of crack and joint sealing on IL 99 from 1.1 miles south of IL 107, south of Mount Sterling, to just south of Versailles northern city limits. | — | Executed | Complete Asphalt Service Co. $25,519 · | ||
| Jan 20, 2023 | 72073 | VariousDistrict 6 | Crack and joint sealing on various routes at various locations throughout District 6. | — | Executed | Complete Asphalt Service Co. $159,923 · | ||
| Jan 20, 2023 | 72120 | SangamonDistrict 6 | 0.8 miles of tree removal on IL 54 from TR 51 (Cass Road) to Sherman Road (along the southeast side). | — | Rejected | |||
| Jan 20, 2023 | 72550 | PikeDistrict 6 | 2.5 miles of standard overlay, drainage improvements, patching and guardrail replacement on IL 106 from 1.1 miles east of East Branch Kiser Creek to US 54 west of Pittsfield. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $1,944,538 · | ||
| Jan 20, 2023 | 72881 | HancockDistrict 6 | Expansion joint replacement on SN 034-0054 carrying IL 96 over Tyson Creek, 1.7 miles south of IL 9 in Niota. | — | Executed | County Contractors, Inc. $126,805 · | ||
| Jan 20, 2023 | 72G17 | LoganDistrict 6 | Pavement patching, HMA surface removal, HMA resurfacing, fog sealing and shoulder work on I-55 from the Sangamon County line to 0.5 miles south of County Highway 10. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $3,806,737 · | ||
| Jan 20, 2023 | 72G54 | MontgomeryDistrict 6 | 5.45 miles of milling/resurfacing and deck replacements from 1.3 miles south of Waggoner to Macoupin Creek, 0.4 mile south of CH 17 at Farmersville. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $24,784,111 · | ||
| Jan 20, 2023 | 72H24 | MasonDistrict 6 | 4.4 miles of standard overlay and bridge overlay on IL 97 from 0.3 miles north of East County Road 800 to the Menard County line and at Pecan Creek, 0.8 miles north of the Menard County line. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $3,156,393 · | ||
| Jan 20, 2023 | 72K64 | LoganDistrict 6 | 4.3 miles of milling, resurfacing and new deck on I-55 from 0.5 miles south to 1.7 miles north of County Highway 10 at the Elkhart Interchange. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $14,154,782 · | ||
| Jan 20, 2023 | 72L78 | ScottDistrict 6 | Slope stabilization on IL 106 east of Hillview Blacktop. | — | Executed | White Construction LLC $2,476,190 · | ||
| Jan 20, 2023 | 72N14 | MorganDistrict 6 | 2.4 miles of cold milling and standard overlay on IL 104 from 0.4 miles west of IL 78 to 0.1 miles north of Morton Avenue in Jacksonville. | — | Executed | K. E. Vas Company $1,882,061 · | ||
| Jan 20, 2023 | 72N23 | VariousDistrict 6 | On call repair of guardrail and impact attenuators throughout District 6 as needed. | — | Executed | COLLINS & HERMANN, INC. $276,322 · | ||
| Jan 20, 2023 | 72N32 | MontgomeryDistrict 6 | 8.7 miles of milling and cape seal IL 185 from east of Chapman T Trail in Coffeen to the Fayette County line. | — | Executed | Beniach Construction Co., Inc. $1,215,973 · | ||
| Jan 20, 2023 | 74813 | MaconDistrict 7 | 9.9 miles of designed overlay, culvert replacement and ADA improvements on IL 48 from Bowman Road to the Christian County line. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $8,098,703 · | ||
| Jan 20, 2023 | 74961 | RichlandDistrict 7 | 11.7 miles of patching, milling, resurfacing, pavement replacement, median replacement and aggregate wedge shoulders on US 50 from 1.6 miles east of the Clay County line to 0.6 miles west of Ste. Marie Road. | — | Executed | Howell Paving, Inc. $12,894,108 · | ||
| Jan 20, 2023 | 74987 | WayneDistrict 7 | 12.8 miles of standard overlay, resurfacing and ramp repair on I-64 from the Jefferson County line to 7 miles west of US 45. | — | Executed | E. T. Simonds Construction Company $19,311,593 · | ||
| Jan 20, 2023 | 74A91 | FayetteDistrict 7 | Abutment modification, bridge deck scarification, full depth deck patching, curb repair, bridge deck overlay, deck drain replacement, new approach slab and pavement connectors on SN 026-0036 carrying US 51 over Old Hickory Creek, 2.5 miles south of US 40. | — | Executed | Stutz Excavating, Inc. $742,000 · | ||
| Jan 20, 2023 | 74B69 | CumberlandDistrict 7 | Removal of dead trees along I-70 and US 40 in Cumberland County. | — | Rejected | Mosley Construction 1, LLC $304,000 · | ||
| Jan 20, 2023 | 74B70 | MaconShelbyDistrict 7 | 42 miles of weed control on US 51 from the Christian County line and on I-72 from US 51 to the Piatt County line. | — | Executed | The Daltons Inc. $72,932 · | ||
| Jan 20, 2023 | 74B83 | VariousDistrict 7 | 47.3 miles of weed control on I-57 from the Marion County line to the Shelby County line and on I-70 from the Fayette County line to the Cumberland County line. | — | Executed | The Daltons Inc. $86,756 · | ||
| Jan 20, 2023 | 76M87 | MadisonDistrict 8 | 5.7 miles of resurfacing and ADA upgrades on IL 159 / Troy Road from Center Grove Road to West Country Lane. | — | Executed | Christ Bros. Asphalt, Inc. $12,374,453 · | ||
| Jan 20, 2023 | 76P70 | MadisonDistrict 8 | Painting of SN 060-0185 carrying Meridian Road over I-270 in Glen Carbon. | — | Executed | Venus Painting Co. $490,150 · | ||
| Jan 20, 2023 | 76P99 | MadisonSt. ClairDistrict 8 | Chemical treatment of deep wells at various locations in East St. Louis and Venice. | — | Rejected | Layne Christensen Company $792,818 · | ||
| Jan 20, 2023 | 76R66 | St. ClairDistrict 8 | Pavement patching on IL 157 at Lake Drive / Foley Drive. | — | Executed | Keeley & Sons, Inc. $592,843 · |
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.