20-00130-15-BR
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stark Excavating, Inc. Low bidder | $2,199,397 | ||
| 2 | Laverdiere Construction, Inc. | $2,201,355 | +0.1% | |
| 3 | Otto Baum Company, Inc. | $2,372,700 | +7.9% | |
| 4 | Freesen, a div of UCM, Inc. | $2,455,389 | +11.6% | |
| 5 | White Construction LLC | $2,627,996 | +19.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stark Excavatin… | #2 Laverdiere Cons… | #3 Otto Baum Compa… | #4 Freesen, a div … | #5 White Construct… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.9 | ACRE | $5,250.00 | $14,400.00 | $13,357.20 | $5,281.50 | $5,030.00 | |
| 2 | X6310088 | TRAF BAR TERM T6A SPL | 1 | EACH | $4,700.00 | $5,412.00 | $5,020.08 | $4,735.50 | $4,510.00 | |
| 3 | X6330725 | SPBGR (SHORT RADIUS) | 50 | FOOT | $68.00 | $77.76 | $72.13 | $68.04 | $64.80 | |
| 4 | X7011006 | TR CONT-PROT TEMP DET | 1 | EACH | $15,000.00 | $25,170.00 | $23,347.26 | $22,023.75 | $20,975.00 | |
| 5 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $13,500.00 | $39,600.00 | $32,000.00 | $25,869.87 | $40,000.00 | |
| 6 | 20100500 | TREE REMOV ACRES | 0.2 | ACRE | $75,000.00 | $24,250.00 | $67,030.95 | $56,958.40 | $42,000.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 745 | CU YD | $39.00 | $25.77 | $75.00 | $17.35 | $16.00 | |
| 8 | 20300100 | CHANNEL EXCAVATION | 1,490 | CU YD | $22.00 | $17.95 | $30.00 | $27.88 | $16.00 | |
| 9 | 20400800 | FURNISHED EXCAVATION | 2,295 | CU YD | $44.25 | $29.15 | $55.00 | $67.30 | $72.00 | |
| 10 | 25100630 | EROSION CONTR BLANKET | 4,026 | SQ YD | $1.30 | $4.98 | $4.62 | $1.31 | $1.25 | |
| 11 | 28000250 | TEMP EROS CONTR SEED | 82 | POUND | $3.25 | $7.20 | $6.68 | $6.56 | $5.00 | |
| 12 | 28000400 | PERIMETER EROS BAR | 1,296 | FOOT | $4.25 | $4.80 | $4.45 | $8.95 | $9.15 | |
| 13 | 28100209 | STONE RIPRAP CL A5 | 1,500 | TON | $99.00 | $106.45 | $84.37 | $117.67 | $72.00 | |
| 14 | 28200200 | FILTER FABRIC | 1,430 | SQ YD | $5.00 | $2.12 | $5.85 | $4.38 | $3.25 | |
| 15 | 28300400 | AGGREGATE DITCH | 61 | TON | $110.00 | $122.52 | $105.60 | $75.80 | $90.00 | |
| 16 | 35100100 | AGG BASE CSE A | 939 | TON | $58.00 | $42.57 | $61.57 | $59.72 | $56.00 | |
| 17 | 40200100 | AGG SURF CSE A | 104 | TON | $87.00 | $45.47 | $92.09 | $93.36 | $85.00 | |
| 18 | 40600275 | BIT MATLS PR CT | 2,834 | POUND | $1.00 | $2.18 | $1.05 | $1.82 | $1.82 | |
| 19 | 40600290 | BIT MATLS TACK CT | 907 | POUND | $1.25 | $3.19 | $1.30 | $2.66 | $2.66 | |
| 20 | 40603080 | HMA BC IL-19.0 N50 | 176 | TON | $250.00 | $273.46 | $240.00 | $227.88 | $227.88 | |
| 21 | 40604050 | HMA SC IL-9.5 C N50 | 106 | TON | $315.00 | $366.07 | $310.00 | $305.06 | $305.06 | |
| 22 | 42000070 | PVT CON HMA BR APP SL | 93 | SQ YD | $250.00 | $394.27 | $220.00 | $328.56 | $328.56 | |
| 23 | 48101200 | AGGREGATE SHLDS B | 261 | TON | $79.00 | $46.50 | $61.83 | $85.84 | $73.00 | |
| 24 | 50100100 | REM EXIST STRUCT | 1 | EACH | $88,500.00 | $49,728.00 | $48,671.79 | $104,590.84 | $200,000.00 | |
| 25 | 50200100 | STRUCTURE EXCAVATION | 185 | CU YD | $28.00 | $26.35 | $79.08 | $40.74 | $53.00 | |
| 26 | 50200300 | COFFERDAM EXCAVATION | 218 | CU YD | $38.00 | $43.86 | $69.56 | $53.98 | $53.00 | |
| 27 | 50201121 | COFFERDAM TYP 2 LOC 1 | 1 | EACH | $50,000.00 | $70,600.00 | $31,029.18 | $73,464.06 | $97,000.00 | |
| 28 | 50300225 | CONC STRUCT | 73.3 | CU YD | $1,025.00 | $1,414.48 | $1,828.20 | $1,188.58 | $1,630.00 | |
| 29 | 50300255 | CONC SUP-STR | 151.7 | CU YD | $1,350.00 | $1,769.02 | $1,630.39 | $1,936.35 | $1,450.00 | |
| 30 | 50300260 | BR DECK GROOVING | 644 | SQ YD | $11.00 | $14.81 | $19.12 | $12.99 | $10.00 | |
| 31 | 50300265 | SEAL COAT CONC | 30 | CU YD | $380.00 | $1.00 | $656.68 | $274.26 | $850.00 | |
| 32 | 50300280 | CONCRETE ENCASEMENT | 9.9 | CU YD | $2,300.00 | $945.08 | $770.64 | $2,613.29 | $2,800.00 | |
| 33 | 50300300 | PROTECTIVE COAT | 777 | SQ YD | $3.75 | $4.16 | $4.01 | $3.89 | $2.50 | |
| 34 | 50301350 | CONC SUPSTR APP SLAB | 85.3 | CU YD | $500.00 | $519.64 | $592.16 | $601.37 | $615.00 | |
| 35 | 50500105 | F & E STRUCT STEEL | 1 | L SUM | $550,000.00 | $570,120.00 | $552,870.38 | $588,635.43 | $663,200.00 | |
| 36 | 50500505 | STUD SHEAR CONNECTORS | 3,260 | EACH | $3.75 | $5.40 | $5.01 | $4.73 | $5.00 | |
| 37 | 50800205 | REINF BARS, EPOXY CTD | 81,800 | POUND | $2.15 | $1.87 | $1.91 | $2.11 | $2.00 | |
| 38 | 50901050 | STEEL RAILING TY SM | 354 | FOOT | $250.00 | $286.50 | $265.75 | $250.69 | $255.00 | |
| 39 | 51201700 | FUR STL PILE HP12X74 | 760 | FOOT | $100.00 | $131.65 | $107.40 | $107.90 | $95.00 | |
| 40 | 51202305 | DRIVING PILES | 760 | FOOT | $0.0100 | $1.00 | $0.0100 | $0.0100 | $0.1000 | |
| 41 | 51203700 | TEST PILE ST HP12X74 | 2 | EACH | $12,000.00 | $8,855.18 | $18,000.00 | $19,139.17 | $12,000.00 | |
| 42 | 51500100 | NAME PLATES | 1 | EACH | $675.00 | $600.00 | $752.72 | $782.83 | $925.00 | |
| 43 | 52100520 | ANCHOR BOLTS 1 | 30 | EACH | $115.00 | $170.40 | $158.79 | $163.60 | $175.00 | |
| 44 | 58600101 | GRANULAR BACKFILL STR | 50 | CU YD | $145.00 | $131.13 | $133.36 | $189.88 | $300.00 | |
| 45 | 59100100 | GEOCOMPOSITE WALL DR | 60 | SQ YD | $37.00 | $66.00 | $37.91 | $56.04 | $55.00 | |
| 46 | 60100060 | CONC HDWL FOR P DRAIN | 3 | EACH | $500.00 | $187.50 | $945.93 | $322.80 | $400.00 | |
| 47 | 60108104 | PIPE UNDERDR T 1 4 | 105 | FOOT | $30.00 | $11.90 | $17.55 | $27.35 | $50.00 | |
| 48 | 60146304 | P UNDR FOR STRUCT 4 | 110 | FOOT | $40.00 | $9.09 | $18.97 | $38.09 | $46.00 | |
| 49 | 63000001 | SPBGR TY A 6FT POSTS | 13 | FOOT | $120.00 | $135.30 | $125.50 | $118.39 | $112.75 | |
| 50 | 63100045 | TRAF BAR TERM T2 | 1 | EACH | $2,000.00 | $2,352.00 | $2,181.67 | $2,058.00 | $1,960.00 | |
| 51 | 63100087 | TRAF BAR TERM T6A | 1 | EACH | $4,800.00 | $5,424.00 | $5,031.21 | $4,746.00 | $4,520.00 | |
| 52 | 63100167 | TR BAR TRM T1 SPL TAN | 1 | EACH | $3,900.00 | $4,404.00 | $4,085.07 | $3,853.50 | $3,670.00 | |
| 53 | 67100100 | MOBILIZATION | 1 | L SUM | $131,500.00 | $30,708.00 | $140,000.00 | $62,540.18 | $158,000.00 | |
| 54 | 70300100 | SHORT TERM PAVT MKING | 1,500 | FOOT | $0.0100 | $2.56 | $2.37 | $1.65 | $2.13 | |
| 55 | 70300150 | SHRT TRM PAVT MK REM | 68 | SQ FT | $0.0100 | $24.00 | $22.26 | $1.72 | $40.00 | |
| 56 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $50.00 | $57.00 | $52.87 | $49.88 | $47.50 | |
| 57 | 78001110 | PAINT PVT MK LINE 4 | 2,788 | FOOT | $2.00 | $2.40 | $2.23 | $2.10 | $2.00 | |
| 58 | 78200005 | GRDRAIL REF TYPE A | 7 | EACH | $10.00 | $11.40 | $10.57 | $9.98 | $9.50 |