(116)CR-5309
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Herlihy Mid-Continent Company Low bidder | $431,778 | ||
| 2 | Sjostrom & Sons, Inc. | $443,908 | +2.8% | |
| 3 | Riber Construction, Inc. | $586,597 | +35.9% | |
| 4 | Alliance Contractors, Inc. | $624,472 | +44.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Herlihy Mid-Con… | #2 Sjostrom & Sons… | #3 Riber Construct… | #4 Alliance Contra… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0900064 | MEMBR WTRPR SYS B STR | 157 | SQ YD | $69.48 | $35.00 | $35.00 | $45.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $4,075.00 | $5,000.00 | $15,000.00 | $4,075.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,000.00 | $3,700.00 | $7,900.00 | $3,330.00 | |
| 4 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $30.00 | $33.00 | $16.00 | $30.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 115 | CU YD | $32.00 | $70.00 | $80.00 | $40.00 | |
| 6 | 20700220 | POROUS GRAN EMBANK | 54.7 | CU YD | $59.00 | $70.00 | $200.00 | $40.00 | |
| 7 | 25000200 | SEEDING CL 2 | 0.25 | ACRE | $4,500.00 | $7,800.00 | $10,500.00 | $10,500.00 | |
| 8 | 25000400 | NITROGEN FERT NUTR | 11 | POUND | $10.00 | $11.00 | $5.00 | $5.00 | |
| 9 | 25000500 | PHOSPHORUS FERT NUTR | 11 | POUND | $10.00 | $11.00 | $5.00 | $5.00 | |
| 10 | 25000600 | POTASSIUM FERT NUTR | 11 | POUND | $10.00 | $11.00 | $5.00 | $5.00 | |
| 11 | 25100115 | MULCH METHOD 2 | 0.25 | ACRE | $2,500.00 | $7,800.00 | $8,500.00 | $8,500.00 | |
| 12 | 25100635 | HD EROS CONTR BLANKET | 48 | SQ YD | $10.00 | $2.70 | $20.00 | $20.00 | |
| 13 | 28000250 | TEMP EROS CONTR SEED | 36 | POUND | $10.00 | $13.00 | $1.00 | $1.00 | |
| 14 | 28000400 | PERIMETER EROS BAR | 280 | FOOT | $10.00 | $4.00 | $10.00 | $10.00 | |
| 15 | 28100107 | STONE RIPRAP CL A4 | 135 | SQ YD | $115.00 | $68.00 | $60.00 | $100.00 | |
| 16 | 28200200 | FILTER FABRIC | 135 | SQ YD | $6.80 | $5.00 | $2.50 | $1.00 | |
| 17 | 40200800 | AGG SURF CSE B | 254 | TON | $33.00 | $28.00 | $50.00 | $75.00 | |
| 18 | 44000100 | PAVEMENT REM | 121 | SQ YD | $10.00 | $17.00 | $40.00 | $40.00 | |
| 19 | 48101200 | AGGREGATE SHLDS B | 102 | TON | $68.24 | $52.00 | $50.00 | $75.00 | |
| 20 | 48203037 | HMA SHOULDERS 10 | 111 | SQ YD | $139.90 | $156.00 | $139.90 | $140.00 | |
| 21 | 50100100 | REM EXIST STRUCT | 1 | EACH | $62,839.03 | $26,000.00 | $30,000.00 | $175,500.00 | |
| 22 | 50800205 | REINF BARS, EPOXY CTD | 27,580 | POUND | $1.60 | $2.00 | $1.90 | $1.85 | |
| 23 | 51500100 | NAME PLATES | 1 | EACH | $470.00 | $850.00 | $550.00 | $750.00 | |
| 24 | 52200010 | TEMP SHT PILING | 3,307 | SQ FT | $0.1000 | $20.00 | $37.00 | $1.00 | |
| 25 | 54003000 | CONC BOX CUL | 156.4 | CU YD | $1,150.00 | $1,010.00 | $1,350.00 | $1,370.00 | |
| 26 | 59100100 | GEOCOMPOSITE WALL DR | 157 | SQ YD | $15.00 | $30.00 | $18.00 | $30.00 | |
| 27 | 63000001 | SPBGR TY A 6FT POSTS | 125 | FOOT | $33.00 | $36.00 | $42.14 | $50.20 | |
| 28 | 63000030 | SPGR ATT TO CULVERT | 50 | FOOT | $225.00 | $250.00 | $194.96 | $195.00 | |
| 29 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $3,860.00 | $4,300.00 | $3,610.00 | $3,610.00 | |
| 30 | 63200310 | GUARDRAIL REMOV | 100 | FOOT | $10.00 | $10.00 | $7.00 | $17.40 | |
| 31 | 67100100 | MOBILIZATION | 1 | L SUM | $25,906.00 | $26,000.00 | $35,000.00 | $46,890.00 | |
| 32 | 70400100 | TEMP CONC BARRIER | 62.5 | FOOT | $30.00 | $50.00 | $52.00 | $150.00 | |
| 33 | 70400125 | PIN TEMP CONC BARRIER | 18 | EACH | $48.00 | $25.00 | $0.0100 | $5.00 | |
| 34 | 72501000 | TERMINAL MARKER - DA | 2 | EACH | $30.00 | $33.00 | $35.00 | $35.00 | |
| 35 | 78001110 | PAINT PVT MK LINE 4 | 50 | FOOT | $30.00 | $33.00 | $30.00 | $30.00 | |
| 36 | 78200005 | GRDRAIL REF TYPE A | 4 | EACH | $25.00 | $27.00 | $10.00 | $15.00 |