(21)SLP
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | White Construction LLC Low bidder | $2,476,190 | ||
| 2 | Freesen, a div of UCM, Inc. | $2,994,139 | +20.9% | |
| 3 | Sangamo Construction Company | $4,323,721 | +74.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 White Construct… | #2 Freesen, a div … | #3 Sangamo Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $3,600.00 | $17,066.84 | $11,585.38 | |
| 2 | Z0016702 | DETOUR SIGNING | 1 | L SUM | $19,075.00 | $20,982.50 | $41,785.83 | |
| 3 | Z0054500 | ROCK FILL | 911 | TON | $68.00 | $53.65 | $72.81 | |
| 4 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 5 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 6 | 20200100 | EARTH EXCAVATION | 428 | CU YD | $24.00 | $53.55 | $84.20 | |
| 7 | 20400800 | FURNISHED EXCAVATION | 682 | CU YD | $120.00 | $109.03 | $128.90 | |
| 8 | 20700110 | POROUS GRAN EMBANK | 112 | TON | $85.00 | $105.67 | $90.64 | |
| 9 | 25000200 | SEEDING CL 2 | 0.5 | ACRE | $5,335.00 | $5,868.50 | $5,651.96 | |
| 10 | 25000400 | NITROGEN FERT NUTR | 45 | POUND | $5.00 | $5.50 | $5.30 | |
| 11 | 25000500 | PHOSPHORUS FERT NUTR | 45 | POUND | $5.00 | $5.50 | $5.30 | |
| 12 | 25000600 | POTASSIUM FERT NUTR | 45 | POUND | $5.00 | $5.50 | $5.30 | |
| 13 | 25100115 | MULCH METHOD 2 | 0.5 | ACRE | $5,335.00 | $5,868.50 | $5,651.96 | |
| 14 | 28100105 | STONE RIPRAP CL A3 | 36 | SQ YD | $65.00 | $127.31 | $93.51 | |
| 15 | 28200200 | FILTER FABRIC | 36 | SQ YD | $22.00 | $17.28 | $7.69 | |
| 16 | 40600290 | BIT MATLS TACK CT | 702 | POUND | $3.04 | $2.88 | $3.22 | |
| 17 | 40604050 | HMA SC IL-9.5 C N50 | 132 | TON | $195.62 | $184.64 | $207.24 | |
| 18 | 44000155 | HMA SURF REM 1 1/2 | 1,560 | SQ YD | $7.50 | $7.08 | $7.95 | |
| 19 | 44000400 | GUTTER REM | 450 | FOOT | $16.00 | $24.15 | $12.56 | |
| 20 | 50200100 | STRUCTURE EXCAVATION | 54 | CU YD | $52.00 | $120.79 | $80.86 | |
| 21 | 50800105 | REINFORCEMENT BARS | 370,170 | POUND | $2.10 | $3.04 | $3.54 | |
| 22 | 51603000 | DRILLED SHAFT IN SOIL | 582 | CU YD | $275.00 | $935.34 | $1,440.64 | |
| 23 | 51604000 | DRILLED SHAFT IN ROCK | 387 | CU YD | $1,850.00 | $1,104.94 | $2,954.01 | |
| 24 | 52200100 | FUR SOLDIER PILES HP | 857 | FOOT | $310.00 | $104.32 | $281.68 | |
| 25 | 52200200 | DRILL SET SLD PI SOIL | 195 | CU FT | $128.00 | $92.64 | $1.00 | |
| 26 | 52200205 | DRILL SET SLD PI ROCK | 3,199 | CU FT | $0.1000 | $58.57 | $1.00 | |
| 27 | 52200255 | TREATED TIMBER LAG | 1,704 | SQ FT | $28.00 | $34.96 | $78.24 | |
| 28 | 59100100 | GEOCOMPOSITE WALL DR | 190 | SQ YD | $36.00 | $47.53 | $53.62 | |
| 29 | 60100060 | CONC HDWL FOR P DRAIN | 2 | EACH | $400.00 | $291.72 | $437.16 | |
| 30 | 60146304 | P UNDR FOR STRUCT 4 | 240 | FOOT | $54.00 | $32.57 | $32.69 | |
| 31 | 60602800 | CONC GUTTER TB | 450 | FOOT | $58.00 | $72.14 | $44.33 | |
| 32 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $2,400.00 | $2,983.54 | $2,464.80 | |
| 33 | 67100100 | MOBILIZATION | 1 | L SUM | $148,000.00 | $178,877.04 | $255,099.54 | |
| 34 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $1,200.00 | $110.00 | $1.00 | |
| 35 | 70107025 | CHANGEABLE MESSAGE SN | 14 | CAL DA | $190.00 | $209.00 | $84.75 | |
| 36 | 78001120 | PAINT PVT MK LINE 5 | 2,200 | FOOT | $1.75 | $1.93 | $2.31 |