$22.39Avg low bid / CU FT
$26.47Avg of all bids
—Avg engineer's estimate
15Jobs · 142,525.8 CU FT
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 7 | 25,285 | $26.32 | $33.51 |
| 2025 | 8 | 117,240.8 | $21.54 | $24.93 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 12, 2026 | 64L94 | HenryDistrict 2 | 4,932 CU FT | $9.00 | Valley Construction Co. |
| Jun 12, 2026 | 62L30 | CookDistrict 1 | 618 CU FT | $47.00 | D. Construction, Inc. |
| Apr 24, 2026 | 62K33 | CookDistrict 1 | 1,151 CU FT | $55.00 | Plote Construction, Inc. |
| Apr 24, 2026 | 61M41 | LakeDistrict 1 | 4,985 CU FT | $10.00 | Alliance Contractors, Inc. |
| Feb 27, 2026 | 62P01 | WillDistrict 1 | 4,235 CU FT | $28.00 | Austin Tyler Construction, Inc. |
| Jan 16, 2026 | 62F94 | WillDistrict 1 | 8,853 CU FT | $38.00 | D. Construction, Inc. |
| Jan 16, 2026 | 61M01 | WillDistrict 1 | 511 CU FT | $47.00 | Austin Tyler Construction, Inc. |
| Nov 7, 2025 | 85785 | Rock IslandDistrict 2 | 14,643 CU FT | $12.00 | Gensini Excavating, Inc. |
| Sep 19, 2025 | 62R22 | WillDistrict 1 | 23,302 CU FT | $45.00 | D. Construction, Inc. |
| Jun 13, 2025 | 60R76 | WillDistrict 1 | 6,794 CU FT | $50.00 | D. Construction, Inc. |
| Apr 25, 2025 | 62R62 | CookDistrict 1 | 2,592 CU FT | $20.30 | Areatha Construction Co., Inc. |
| Apr 25, 2025 | 61G79 | DupageDistrict 1 | 36,705 CU FT | $1.00 | OHLA Central, Inc. |
| Mar 7, 2025 | 62N91 | CookDistrict 1 | 5,349 CU FT | $30.50 | Dunnet Bay Construction Company & K-Five Construction Corporation |
| Mar 7, 2025 | 68E50 | KnoxDistrict 4 | 4,122 CU FT | $61.60 | Gunther Construction, a div of UCM, Inc. |
| Jan 17, 2025 | 93773 | SangamonDistrict 6 | 23,733.8 CU FT | $19.15 | Freesen, a div of UCM, Inc. |