D6 PATCHING 2023
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | G. M. Sipes Construction, Inc. Low bidder | $671,886 | ||
| 2 | Kinney Contractors, Inc. | $702,694 | +4.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 G. M. Sipes Con… | #2 Kinney Contract… |
|---|---|---|---|---|---|---|---|
| 1 | 44200050 | WELDED WIRE REINF | 23 | SQ YD | $25.00 | $21.00 | |
| 2 | 44200577 | CL A PATCH T2 12 | 8 | SQ YD | $375.00 | $385.00 | |
| 3 | 44200610 | CL A PATCH T2 13 | 599 | SQ YD | $375.00 | $385.00 | |
| 4 | 44200612 | CL A PATCH T3 13 | 55 | SQ YD | $375.00 | $383.00 | |
| 5 | 44200614 | CL A PATCH T4 13 | 140 | SQ YD | $375.00 | $380.00 | |
| 6 | 44200645 | CL A PATCH T2 16 | 8 | SQ YD | $425.00 | $500.00 | |
| 7 | 44201043 | CL B PATCH T2 16 | 135 | SQ YD | $400.00 | $375.00 | |
| 8 | 44201047 | CL B PATCH T3 16 | 23 | SQ YD | $400.00 | $370.00 | |
| 9 | 44201299 | DOWEL BARS 1 1/2 | 290 | EACH | $35.00 | $30.00 | |
| 10 | 44213000 | PATCH REINFORCEMENT | 810 | SQ YD | $95.00 | $70.00 | |
| 11 | 44213200 | SAW CUTS | 5,986 | FOOT | $0.0100 | $6.00 | |
| 12 | 44213204 | TIE BARS 3/4 | 90 | EACH | $20.00 | $20.00 | |
| 13 | 67100100 | MOBILIZATION | 1 | L SUM | $33,000.00 | $42,000.00 | |
| 14 | 70100420 | TRAF CONT-PROT 701411 | 10 | EACH | $0.0100 | $1,400.00 | |
| 15 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $130,000.00 | $55,000.00 | |
| 16 | 70100815 | TRAF CONT-PROT 701446 | 1 | L SUM | $35,000.00 | $85,000.00 | |
| 17 | 70107025 | CHANGEABLE MESSAGE SN | 60 | CAL DA | $0.0100 | $150.00 | |
| 18 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $17,000.00 | $23,000.00 |