| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Jan 16, 2026 | 62P93 | CookDistrict 1 | ADA Improvements: curb ramps for sidewalks (ADA) including combination curb and gutter removal and replacement, sidewalk removal and replacement, installation of detectable warning surfaces, drainage structure adjustments, minor traffic signal improvements (accessible pedestrian signals), thermoplastic pavement markings work. Location: Various Routes, Various Locations within Norwood Park and Leyden Townships (Villages of Norridge, Park Ridge, River Grove and Elmwood Park). | — | Executed | Triggi Construction, Inc. $2,633,662 · | ||
| Jan 16, 2026 | 62R76 | WillDistrict 1 | Reconstruction of the expansion joints with strip seals, hydro scarification (3/4-), deck and approach slab re (290-Ft) Bridge Deck Overlay, (SN 099-0210) over I-55. The project consists of reconstruction of the expansion joints with strip seals, hydro scarification (3/4-), deck and approach slab repairs, latex concrete overlay (2¼-) with diamond grinding and longitudinal grooving, application of a protective coat, and substructure concrete repair. Roadway improvements include HMA on each side of the bridge. I-55 at Caton Farm Road (3 miles north of US 52) in the Village of Plainfield. | — | Executed | D. Construction, Inc. $647,187 · | ||
| Jan 16, 2026 | 62U12 | CookDistrict 1 | (520-Ft) Bridge Superstructure replacement, approach slab replacement, lighting ADA improvement and traffic signal modernization. The project is located at Structure No. 016-2114 on Loomis Street over I-290 in the City of Chicago in Cook County. | — | Executed | F. H. Paschen, S.N. Nielsen & Associates LLC $11,102,837 · | ||
| Jan 16, 2026 | 62V42 | CookDistrict 1 | Resurfacing the existing HMA pavement with HMA surface course, HMA Binder course, thermoplastic pavement marki (4,061-Ft) Standard Overlay and ADA improvements consists of resurfacing the existing HMA pavement with HMA surface course, HMA Binder course, thermoplastic pavement markings, ADA Improvements for curb ramps. This project is in the villages of Niles and Morton Grove in Cook County. | — | Rejected | |||
| Jan 16, 2026 | 62W33 | CookDistrict 1 | (2,652-Ft) Drainage improvements, installation of new trunk storm sewer includes pavement restoration, designed overlay, curb ramps for sidewalks (ADA) improvements and lane re-allocation via pavement markings. Location of Work: FAU 2843: Dixie Hwy, from Harwood Avenue to north of Sycamore Drive, within the Village of Homewood in Cook County. | — | Executed | Iroquois Paving Corporation $7,521,180 · | ||
| Jan 16, 2026 | 62W47 | CookDistrict 1 | (2,231-Ft) Intersection Improvements, Traffic Signal Modernization, ADA compliant curb ramps at pedestrian crossings, driveway improvements, pavement markings, landscaping, roadway lighting locations at IL 7 (Southwest Hwy) and IL 43 (Harlem Ave) in the Villages of Worth and Chicago Ridge in Cook County. | — | Executed | D. Construction, Inc. $3,827,864 · | ||
| Jan 16, 2026 | 62Y05 | McHenryDistrict 1 | Replacing the expansion joints at both abutments, updating the guardrail, removing tree debris from the channe (1050-Ft) Bridge Deck Overlay (SN 056-0037) consists of replacing the expansion joints at both abutments, updating the guardrail, removing tree debris from the channel. Located on FAP Route 336, IL 31 (Richmond Road) over Nippersink Creek in The City of Richmond in McHenry County, IL. | — | Executed | Martam Construction Incorporated $740,984 · | ||
| Jan 16, 2026 | 62Y09 | WillDistrict 1 | This is an advance procurement of selective mechanical, electrical, and structural components for the existing rolling movable bridges at Jackson Street and Jefferson Street over the Des Plaines River, Structure Number 099- 0239 and 099-0166 in Will County. | — | Executed | GRANITE CONSTRUCTION COMPANY $2,400,000 · | ||
| Jan 16, 2026 | 62Y14 | CookDistrict 1 | I-beam repair, joint sealing, HMA surface removal, butt joints, HMA surface course, guardrail removal, traffic (296-Ft) Bridge joint repair and replacement, and bridge deck latex overlay project (SN 016-2545) consist of I-beam repair, joint sealing, HMA surface removal, butt joints, HMA surface course, guardrail removal, traffic barrier terminal installation, pavement markings, temporary concrete barrier, maintenance of traffic with temporary pavement markings, temporary traffic signals. This project is in the City of Chicago Heights, in Cook County, IL. | — | Executed | D. Construction, Inc. $742,733 · | ||
| Jan 16, 2026 | 64L27 | StephensonDistrict 2 | Reconstruction of the intersection of US Route 20 and Illinois Route 73 including grade changes, replacing across road culverts, adding turn lanes, and installing traffic signals. The project includes Jointed PCC Pavement and Tied-Shoulders, 9", Hot-Mix Asphalt (HMA) surface removal and replacement 2-3/4", HMA Shoulders, 8", PCC and HMA Driveway Pavement, Pipe and Box Culverts pavement markings, tree removal, pavement removal, temporary pavement, intersection lighting, highway signage, earthwork | — | Executed | Martin & Company Excavating $11,833,444 · | ||
| Jan 16, 2026 | 64L71 | HenryDistrict 2 | Culvert replacement on IL 82 Over a Drainage Ditch 0.3 mile north of roadway 1700N. | — | Executed | Phoenix Corporation of the Quad Cities $811,655 · | ||
| Jan 16, 2026 | 64T05 | OgleDistrict 2 | Bridge repairs and joint replacement on SN 071-0082, carrying IL 64 over Elkhorn Creek Tributary, 0.4 mile east of US 52. | — | Executed | Martin & Company Excavating $460,374 · | ||
| Jan 16, 2026 | 64T96 | LeeDistrict 2 | Bridge repairs and joint replacement on SN 052-0068, carrying IL 251 over Bureau Creek, 0.80 miles north of Lee County line. | — | Executed | Martin & Company Excavating $369,059 · | ||
| Jan 16, 2026 | 64U16 | HenryDistrict 2 | 12.4 miles of patching, milling, and resurfacing on Osco Rd from IL 81 to US 6. | — | Executed | Advanced Asphalt Company $6,016,335 · | ||
| Jan 16, 2026 | 64U18 | HenryWhitesideDistrict 2 | 11.4 miles of patching, cold milling, and standard overlay on IL 78 from 0.2 mile north of IL 92 in Henry County to north of west 8th St in Prophetstown, Whiteside County; and IL 92 from IL 78 to Bureau County Line in Henry County. | — | Executed | Advanced Asphalt Company $5,878,533 · | ||
| Jan 16, 2026 | 64U20 | WhitesideDistrict 2 | Designed overlay, milling, and patching from Emerson Rd to Galt Rd and US 30 Connector._Approximately 4.29 miles. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $5,204,514 · | ||
| Jan 16, 2026 | 64U21 | LeeDistrict 2 | 8 Miles Cold-In Place Eldena Road to US 30. | — | Executed | Martin & Company Excavating $4,655,130 · | ||
| Jan 16, 2026 | 64U81 | Rock IslandDistrict 2 | Class B patches along IL 5 at 16th St. in Moline with Approx. 560' of resurfacing. | — | Executed | G. M. Sipes Construction, Inc. $779,622 · | ||
| Jan 16, 2026 | 64U83 | Rock IslandDistrict 2 | 1.5 miles of pavement patching from 1st St. to Archer Rd. HMA skip patching frontage roads in Rock Island County. | — | Executed | G. M. Sipes Construction, Inc. $685,514 · | ||
| Jan 16, 2026 | 64U84 | BooneDistrict 2 | 650 ft of standard overlay at US BUS 20 and Logan Ave. South to 2nd St. | — | Executed | Rock Road Companies, Inc. $233,841 · | ||
| Jan 16, 2026 | 64U94 | VariousDistrict 2 | Restoration of turf right-of-way as a result of motorist caused damage. This involves tilling, fertilizing, seeding, and installing soil retention blanket on Disturbed areas throughout District 2. | — | Executed | O'Brien Civil Works, Inc. $83,680 · | ||
| Jan 16, 2026 | 64V02 | VariousDistrict 2 | Concrete sealer applied to bridge decks at various locations in Henry, Rock Island and Whiteside Counties. | — | Executed | M & M Concrete, Inc. $44,239 · | ||
| Jan 16, 2026 | 64V03 | WinnebagoDistrict 2 | Concrete sealer applied to bridge decks at various locations in Winnebago County. | — | Executed | M & M Concrete, Inc. $79,732 · | ||
| Jan 16, 2026 | 64V04 | VariousDistrict 2 | Concrete sealer applied to bridge decks at various locations in Carroll, Jo Daviess, Lee and Ogle Counties. | — | Executed | M & M Concrete, Inc. $27,283 · | ||
| Jan 16, 2026 | 64V08 | VariousDistrict 2 | Bridge washing of 6 structures over the Rock River in various Counties. | — | Executed | Pressure Washing Unlimited Inc. $41,570 · | ||
| Jan 16, 2026 | 64V09 | HenryRock IslandDistrict 2 | Bridge washing of 5 structures over the Rock River in Henry and Rock Island Counties. | — | Executed | Pressure Washing Unlimited Inc. $53,315 · | ||
| Jan 16, 2026 | 64V10 | VariousDistrict 2 | Bridge washing of 8 structures over the Rock River in various Counties. | — | Executed | All States Painting, Inc. $66,330 · | ||
| Jan 16, 2026 | 64V22 | HenryDistrict 2 | Tree Removal, 0.1 mi W of Union St to 0.3 mi W of ILL 78 in Kewanee. | — | Executed | Homer Tree Service, Inc. $353,310 · | ||
| Jan 16, 2026 | 66D52 | LivingstonDistrict 3 | 8.78 miles gross of HMA designed overlay and installation of four foot HMA safety shoulders along with edge line rumble strips on IL 17 in Livingston County. | — | Executed | Kankakee Valley Construction Company, Inc. $7,195,925 · | ||
| Jan 16, 2026 | 66N78 | BureauDistrict 3 | 5.8 miles of milling and resurfacing 3 3/4" (designed overlay) for IL 29/26 and milling 3 1/2", resurfacing 3 3/4" (designed overlay) for SBI 29; additional work includes ditch cleaning, pipe culvert replacement, guardrail as applicable, pavement marking, and raised reflective pavement markers. This is located on FAS 318 (IL 29), SBI 29 A (IL 29), FAS 2245 (IL 29/26), starting at the Putnam County line and_ending south of Kansas St. in Bureau Junction, and on SBI 29 (OR 29), from IL 29 to dead e | — | Executed | Advanced Asphalt Company $4,503,804 · | ||
| Jan 16, 2026 | 66R21 | LaSalleDistrict 3 | Bridge deck wearing surface removal and replacement, deck patching, expansion joint replacement, bearing replacement, concrete repairs, HMA shoulder repairs, pavement striping, and other related construction work at two structures: SN's 050-0077 and 050-0078 carrying IL Route 251 over I-80 in LaSalle County. | — | Executed | D. Construction, Inc. $1,801,296 · | ||
| Jan 16, 2026 | 66R58 | LivingstonDistrict 3 | Removing existing dual CMP culverts at three locations and replacement with a precast concrete box culvert, ditch cleaning, pavement removal and replacement, landscaping and other related construction work on IL Route 116 beginning approximately 138 feet west of N. 1450 Rd and ending approximately 170 feet east of 1304 W. Reynolds St. in Pontiac. | — | Executed | Phoenix Corporation of the Quad Cities $686,220 · | ||
| Jan 16, 2026 | 66R74 | VariousDistrict 3 | Application of growth regulator and broadleaf herbicide chemicals to vegetation within the "Safety Zone" along_shoulders of District 3 Interstate Routes and ramps, including I-80, I-180, I-55, I-39, and I-57 within the counties of Bureau, LaSalle, Grundy, Livingston, Kankakee, Iroquois, and Ford. | — | Executed | ALLEN CHASE ENTERPRISES INC. $147,145 · | ||
| Jan 16, 2026 | 66R77 | VariousDistrict 3 | Bridge Deck Concrete Sealing with the parapets/curbs on various routes at various locations throughout Dekalb, Grundy, Kendall and Lasalle Counties. | — | Executed | M & M Concrete, Inc. $195,933 · | ||
| Jan 16, 2026 | 66R83 | LaSalleDistrict 3 | Milling and resurfacing, patching, pavement striping, pavment markers, and other related construction work on FAU_Route 6081 north of I-80 in Peru beginning at Il Route 251 and ending at Airport Rd; also on Charles St adjacent to east 3rd Rd in Lasalle County. | — | Executed | Advanced Asphalt Company $836,744 · | ||
| Jan 16, 2026 | 66R85 | LaSalleDistrict 3 | Filling existing shoulder inlets, paved shoulder removal and replacement with PCC shoulders and concrete curbs, pipe drain removal, riprap installation Class A Patching (Special) and other related construction work on FAI 39 north and south of SNs 050-0167 and 050-0168 over the Chicago and Northwestern Railroad. | — | Executed | D. Construction, Inc. $333,979 · | ||
| Jan 16, 2026 | 66R89 | KendallDistrict 3 | Cleaning and painting steel bridge, pavement striping, and traffic control at SN 047-0052 carrying US Route 52 over Roods Creek in Kendall County. | — | Executed | ERA-Valdivia Contractors, Inc. $118,285 · | ||
| Jan 16, 2026 | 66R90 | DeKalbDistrict 3 | Cleaning and painting steel bridge, pavement striping, and traffic control at SN 019-0012 carrying IL Route 64 over S. Branch Kishwaukee River in Dekalb County. | — | Executed | ERA-Valdivia Contractors, Inc. $132,665 · | ||
| Jan 16, 2026 | 66R91 | BureauDistrict 3 | Cleaning and painting all structural steel, pavement striping, and traffic control of SN 019-0012 carrying IL Route 92 over a branch of Masters Creek in Bureau County. | — | Executed | ERA-Valdivia Contractors, Inc. $118,396 · | ||
| Jan 16, 2026 | 66T16 | GrundyDistrict 3 | 0.60 miles of seeding, Minooka Rd to Aux Sable Creek. | — | Executed | Central Landscaping, LP $117,275 · | ||
| Jan 16, 2026 | 68F50 | FultonDistrict 4 | Bridge painting and repair on SN 063-0002, the Scott W. Lucas Memorial Bridge over the Illinois River, in Fulton County. | — | Executed | Civil Coatings and Construction Inc. $14,341,242 · | ||
| Jan 16, 2026 | 68F92 | TazewellDistrict 4 | 3.22 miles patching, resurfacing and traffic signals; from west of Grosenbach Road to east of Cummings Lane in Peoria County. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $11,508,683 · | ||
| Jan 16, 2026 | 68J43 | TazewellDistrict 4 | Bridge joint replacement, structural steel repairs, floor drain extension, and deck sealer on East Washington Street over Farm Creek in East Peoria. | — | Executed | Stark Excavating, Inc. $498,351 · | ||
| Jan 16, 2026 | 68K52 | PeoriaDistrict 4 | 1.38 miles of landscaping maintenance and installation along I-74 from Ellis St to the Illinois River. | — | Executed | JIMAX Landscape LLC $271,496 · | ||
| Jan 16, 2026 | 68K60 | VariousDistrict 4 | Districtwide tree removal on an on call basis. | — | Executed | JIMAX Landscape LLC $137,673 · | ||
| Jan 16, 2026 | 68K61 | VariousDistrict 4 | Weed spraying throughout District 4. Aproximately 2142 acres. | — | Executed | The Daltons Inc. $155,821 · | ||
| Jan 16, 2026 | 70E65 | PiattDistrict 5 | Bridge deck overlay IL-32 over the Sangamon River 4.3 miles south of Cisco (SN 074-3171). | — | Executed | Sangamo Construction Company $1,304,781 · | ||
| Jan 16, 2026 | 70F93 | McLeanDistrict 5 | Bridge deck overlay at Mackinaw River 2 miles southwest of Lexington and at Turkey Creek 1.5 miles southwest of Lexington on I-55. | — | Executed | Stark Excavating, Inc. $6,136,985 · | ||
| Jan 16, 2026 | 70H59 | ChampaignDistrict 5 | Bridge Painting of 7 Structures on FAI 74 / (I-74) in Champaign County. | — | Executed | ERA-Valdivia Contractors, Inc. $2,340,051 · | ||
| Jan 16, 2026 | 70H79 | McLeanDistrict 5 | 88.7 miles of Litter removal along interstate right-of-ways in McLean County. | — | Executed | Thor General Contracting LLC $70,676 · | ||
| Jan 16, 2026 | 70H80 | ChampaignDistrict 5 | 75.3 miles of Litter removal along interstate right-of-ways in Champaign County. | — | Executed | Thor General Contracting LLC $60,155 · | ||
| Jan 16, 2026 | 70H84 | VariousDistrict 5 | 567.5 miles of weed spraying; approximately 2,004 acres on state ROW along US 51 and interstate routes including interchanges in Champaign, Dewitt, McLean, Piatt, and Vermilion Counties. | — | Executed | ALLEN CHASE ENTERPRISES INC. $149,012 · | ||
| Jan 16, 2026 | 72047 | VariousDistrict 6 | Bridge washing at eight major river crossings within District 6. | — | Executed | All States Painting, Inc. $151,644 · | ||
| Jan 16, 2026 | 72307 | PikeDistrict 6 | 9.2 miles of partial depth pavement patching, resurfacing, HMA shoulders, concrete gutter replacement and guardrail updates on IL 107 from the Brown County line to north of Franklin Street in Griggsville. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $7,106,857 · | ||
| Jan 16, 2026 | 72383 | LoganDistrict 6 | 5 miles of Cape seal on the mainline and fog seal on the shoulders of IL 121 from west of IL 54, south of Mt Pulaski, to 0.2 miles west of CH 6 (2200th Avenue), west of Latham. | — | Executed | A. C. Pavement Striping Co. $639,547 · | ||
| Jan 16, 2026 | 72415 | ChristianDistrict 6 | 2.6 miles of milling, resurfacing and HMA shoulders on US 51 from IL 16 to 540 N. Road. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $1,716,492 · | ||
| Jan 16, 2026 | 72419 | MacoupinDistrict 6 | 6 miles of resurfacing on IL 111 from south of Albany Road, 1.8 miles south of Chesterfield, to IL 267 in Medora. | — | Executed | Charles E. Mahoney Co. $4,595,378 · | ||
| Jan 16, 2026 | 72420 | MacoupinDistrict 6 | 4.43 miles of cape sealing the existing mainline pavement of IL 4, and fog sealing the HMA shoulders. | — | Executed | A. C. Pavement Striping Co. $527,386 · | ||
| Jan 16, 2026 | 72433 | SangamonDistrict 6 | 2.7 miles of resurfacing on Andrew Road from 0.1 miles east of IL 29 to west of IL 124, west of Sherman. | — | Executed | P. H. Broughton & Sons, Inc. $1,115,449 · | ||
| Jan 16, 2026 | 72464 | ScottDistrict 6 | 3.9 miles of resurfacing on IL 106 from west of Hillview Blacktop to Old US 36 and on Old US 36 from IL 106 to north of Commercial Street in Winchester. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $2,868,473 · | ||
| Jan 16, 2026 | 72653 | LoganDistrict 6 | Painting three bridges on I-55 in northern Logan County. (SN 054-060, 054-0061, and 054-0062) | — | Executed | Three Star Painting, Inc. $1,463,000 · | ||
| Jan 16, 2026 | 72715 | SangamonDistrict 6 | Substructure repairs on SN 084-0073 and SN 084-0178 carrying Dirksen Parkway over NS Railroad and IC Railroad in Springfield. | — | Executed | William Charles Construction Company, LLC $329,894 · | ||
| Jan 16, 2026 | 72729 | SangamonDistrict 6 | Bridge painting on SN 084-0127 and SN 084-0127 carrying I-72 over the NS Railroad, 1.2 miles east of Wabash Avenue in Springfield. | — | Executed | Three Star Painting, Inc. $409,200 · | ||
| Jan 16, 2026 | 72732 | MorganDistrict 6 | Bridge deck patching on four bridges carrying US 67 over IL 104 ramps and NS Railroad northwest of Jacksonville. (SN 069-0073, 0074, 0075, 0076) | — | Executed | Freesen, a div of UCM, Inc. $485,061 · | ||
| Jan 16, 2026 | 72777 | VariousDistrict 6 | 26.3 miles of crack and joint sealing on various routes in District 6. | — | Executed | SKC Construction, Inc. $148,228 · | ||
| Jan 16, 2026 | 72913 | MorganDistrict 6 | Riprap installation for erosion control at SN 069-0019 carrying IL 104 over NS Railroad, 0.5 miles south of IL 78 in Jacksonville. | — | Executed | Earth Worx Solutions LLC $25,450 · | ||
| Jan 16, 2026 | 72978 | SangamonDistrict 6 | Bridge deck overlay on SN 084-0192 carrying IL 104 over Sugar Creek, 1.2 miles east of Auburn. | — | Executed | Sangamo Construction Company $674,724 · | ||
| Jan 16, 2026 | 72979 | SangamonDistrict 6 | Bridge deck patching and substructure repairs on SN 084-0102 carrying Ridgely Road over I-55, 0.5 miles south of Sangamon Avenue in Springfield. | — | Executed | Path Construction Company, Inc. $398,054 · | ||
| Jan 16, 2026 | 72A25 | PikeScottDistrict 6 | Painting portions of four bridges on I-72. (SN 075-0083, 075-0112, 086-0037 and 086-0038) | — | Executed | Three Star Painting, Inc. $559,150 · | ||
| Jan 16, 2026 | 72B36 | LoganDistrict 6 | 8.7 miles of resurfacing and ADA improvements on IL 54 from the DeWitt County line to north of IL 121 and on McDonald Street from IL 54 to IL 121 in Mt. Pulaski. | — | Executed | P. H. Broughton & Sons, Inc. $4,118,757 · | ||
| Jan 16, 2026 | 72C57 | ChristianDistrict 6 | 6.5 miles of resurfacing on Mount Auburn Road from CH 21 (2100 Road) to north of the Taylorville City limits. Also includes bridge repairs on SN 011-0029 located at Paper Mill Branch, 3.2 miles north of IL 29. | — | Executed | Truman L. Flatt & Sons Co., Inc. $2,539,344 · | ||
| Jan 16, 2026 | 72D12 | PikeScottDistrict 6 | 1.4 miles of tree removal for the new Illinois River Bridge in Florence. | — | Rejected | |||
| Jan 16, 2026 | 72F57 | MenardDistrict 6 | Expansion joint removal and deck/approach patching on SN 065-0018 carrying IL 123 over Indian Creek, 2.5 miles east of IL 97. | — | Executed | Otto Baum Company, Inc. $361,800 · | ||
| Jan 16, 2026 | 72G53 | SangamonDistrict 6 | Patching on I-55 from the Montgomery County line to the Logan County line, I-72 from the Morgan County line to the Macon County line and IL 29 from Dirksen Parkway in Springfield to 0.2 miles east of Cardinal Hill in Rochester. | — | Executed | Kinney Contractors, Inc. $1,797,824 · | ||
| Jan 16, 2026 | 72G63 | MacoupinDistrict 6 | 5.3 miles of resurfacing on IL 111 from south of Sherman Street in Palmyra to south of Cheshire Lane, north of Hettick. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $3,535,196 · | ||
| Jan 16, 2026 | 72G90 | ChristianDistrict 6 | 1.8 miles of resurfacing, patching, ADA curb ramps, storm sewer, pipe culverts and lighting on IL 29 in Pana. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $10,566,462 · | ||
| Jan 16, 2026 | 72H11 | LoganDistrict 6 | Patching on I-55 from the Sangamon County line to the Mclean County line. | — | Executed | Kinney Contractors, Inc. $340,896 · | ||
| Jan 16, 2026 | 72K24 | LoganSangamonDistrict 6 | Bridge deck sealing at various locations in Logan and Sangamon Counties. | — | Executed | All States Painting, Inc. $306,990 · | ||
| Jan 16, 2026 | 72K80 | SangamonDistrict 6 | Painting bridges on I-72 at Curran Road and Cantrell Road. (SN 084-0146 and SN 084-0161) | — | Executed | Civil Coatings and Construction Inc. $382,075 · | ||
| Jan 16, 2026 | 74168 | MaconDistrict 7 | Bridge replacement on IL 105 over Long Creek, 0.5 miles east of Oakley Road. (SN 058-0044) | — | Executed | Sangamo Construction Company $2,324,074 · | ||
| Jan 16, 2026 | 74498 | EffinghamDistrict 7 | 3.1 miles of resurfacing on IL 32 from the Shelby County line to IL 33. | — | Executed | Howell Paving, Inc. $2,835,837 · | ||
| Jan 16, 2026 | 74893 | EffinghamDistrict 7 | 1.2 miles of reconstruction, bridge replacement and bridge repairs on I-70 from Altamont to 0.8 miles east of the Altamont interchanges. | — | Executed | William Charles Construction Company, LLC $32,709,958 · | ||
| Jan 16, 2026 | 74B50 | MaconDistrict 7 | 7.9 miles of longitudinal joint repair on I-72 from US 36 to US 51. | — | Executed | Illinois Valley Paving, a div of UCM, Inc. $919,562 · | ||
| Jan 16, 2026 | 74B61 | EffinghamDistrict 7 | 0.5 miles of resurfacing and patching on IL 32/33 in Effingham from west of Ford Avenue to 0.1 miles west of Evergreen Avenue. | — | Executed | Howell Paving, Inc. $1,434,601 · | ||
| Jan 16, 2026 | 74C61 | ClayEffinghamDistrict 7 | 8 miles of resurfacing on I-57 northbound lanes from the Fayette County line to the Little Wabash River. | — | Executed | Howell Paving, Inc. $6,207,309 · | ||
| Jan 16, 2026 | 74D34 | ShelbyDistrict 7 | 0.5 miles of parking and ADA improvements on IL 128 from 0.1 miles north of Elm Street to Christy Street in Cowden. | — | Executed | A & R Mechanical Service, Inc. $499,150 · | ||
| Jan 16, 2026 | 74D36 | LawrenceDistrict 7 | Parking lot improvements at the Lawrenceville Maintenance Yard. | — | Executed | Samron Midwest Contracting, Inc. $198,545 · | ||
| Jan 16, 2026 | 74D37 | EffinghamDistrict 7 | Removal and replacement of lighting at exit 105 on I-70 in Montrose. | — | Executed | Capitol Construction Group, LLC d/b/a Egizii Electric $331,606 · | ||
| Jan 16, 2026 | 74D50 | FayetteDistrict 7 | Fencing at the Vandalia maintenance yard. | — | Executed | Lake Contracting, Inc. $115,664 · | ||
| Jan 16, 2026 | 76A46 | MadisonDistrict 8 | Intersection improvements with signals and bridge replacement on IL 162/IL 157 in Glen Carbon. | — | Executed | Keller Construction, Inc. $17,570,642 · | ||
| Jan 16, 2026 | 76E84 | MadisonSt. ClairDistrict 8 | 6.4 miles of resurfacing and bridge repairs along I-55/I-70 from the I-64 (Tri-Level) interchange to 0.5 miles west of Black Lane. Includes lighting work from east of I-64 (Tri-Level) in East St. Louis to east of IL 203 in Fairmont City. | — | Executed | The Kilian Corporation & Christ Brothers Asphalt & Keeley & Sons, Inc. tri-venture $99,865,324 · | ||
| Jan 16, 2026 | 76N65 | MadisonDistrict 8 | Bridge superstructure replacement on IL 3 (Cedar Street) over the rail yard, south of Niedringhaus Avenue in Granite City. (SN 060-0202) | — | Executed | Plocher Construction Company, Inc. $17,564,000 · | ||
| Jan 16, 2026 | 76U46 | St. ClairDistrict 8 | Bridge deck sealing at various locations in St. Clair County. | — | Executed | All States Painting, Inc. $519,048 · | ||
| Jan 16, 2026 | 76U72 | St. ClairDistrict 8 | 1.8 miles of chip seal on Water Street from IL 3 in Cahokia Heights to Old IL 3 in Dupo. | — | Executed | Evergreen Roadworks, LLC $186,914 · | ||
| Jan 16, 2026 | 76U88 | MadisonSt. ClairDistrict 8 | Well treatment at various locations in District 8. | — | Executed | Layne Christensen Company $853,559 · | ||
| Jan 16, 2026 | 76U89 | VariousDistrict 8 | Repair and maintenance of electrical equipment at various pump stations at various locations in District 8. | — | Executed | Electrico, Inc. $243,879 · | ||
| Jan 16, 2026 | 76U95 | St. ClairDistrict 8 | 0.88 miles of resurfacing on IL 159 from 0.1 miles north of Fountains Parkway to north of Lincoln Trail in Fairview Heights. | — | Executed | The Kilian Corporation $3,475,296 · | ||
| Jan 16, 2026 | 78937 | JacksonDistrict 9 | Replacement of SN 039-0052 carrying US 51 over CN, IC Railroad, approximately 2.6 miles north of Desoto. | — | Executed | E. T. Simonds Construction Company $4,810,447 · | ||
| Jan 16, 2026 | 78969 | GallatinDistrict 9 | Bridge replacement on IL 13 over North Fork Saline River east of Equality. (SN 030-0015) | — | Executed | Samron Midwest Contracting, Inc. $5,635,125 · | ||
| Jan 16, 2026 | 78A09 | FranklinDistrict 9 | Drainage culvert removal and replacement on IL 148 south of 9th Street in the City of Christopher. | — | Executed | Samron Midwest Contracting, Inc. $957,763 · |
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.