10RS-3
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | P. H. Broughton & Sons, Inc. Low bidder | $4,118,757 | ||
| 2 | Illinois Valley Paving, a div of UCM, Inc. | $4,133,496 | +0.4% | |
| 3 | Truman L. Flatt & Sons Co., Inc. | $4,302,811 | +4.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 P. H. Broughton… | #2 Illinois Valley… | #3 Truman L. Flatt… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0325714 | FL BEACON P MTD SP IN | 1 | EACH | $4,350.00 | $2,730.00 | $2,615.60 | |
| 2 | X4240420 | PC CONC SIDEWALK 4 SP | 250 | SQ FT | $35.00 | $21.11 | $23.41 | |
| 3 | Z0076600 | TRAINEES | 2,500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 4 | Z0076604 | TRAINEES TPG | 2,500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 3 | CU YD | $300.00 | $305.09 | $63.12 | |
| 6 | 21400100 | GRADING & SHAP DITCH | 4,260 | FOOT | $5.97 | $8.08 | $15.03 | |
| 7 | 25000200 | SEEDING CL 2 | 1.5 | ACRE | $2,752.13 | $2,693.25 | $2,616.30 | |
| 8 | 25000400 | NITROGEN FERT NUTR | 132 | POUND | $5.36 | $5.25 | $5.10 | |
| 9 | 25000500 | PHOSPHORUS FERT NUTR | 132 | POUND | $5.36 | $5.25 | $5.10 | |
| 10 | 25000600 | POTASSIUM FERT NUTR | 132 | POUND | $5.36 | $5.25 | $5.10 | |
| 11 | 25000700 | AGR GROUND LIMESTONE | 3 | TON | $85.84 | $84.00 | $81.60 | |
| 12 | 25100115 | MULCH METHOD 2 | 1.5 | ACRE | $2,752.13 | $2,693.25 | $2,616.30 | |
| 13 | 28000250 | TEMP EROS CONTR SEED | 147 | POUND | $7.51 | $7.84 | $2.29 | |
| 14 | 28000305 | TEMP DITCH CHECKS | 10 | FOOT | $13.95 | $20.61 | $19.84 | |
| 15 | 28000500 | INLET & PIPE PROTECT | 5 | EACH | $209.23 | $240.64 | $213.72 | |
| 16 | 40600290 | BIT MATLS TACK CT | 91,725 | POUND | $0.6100 | $0.6000 | $0.6800 | |
| 17 | 40600370 | LONG JOINT SEALANT | 46,532 | FOOT | $2.70 | $2.62 | $2.54 | |
| 18 | 40600405 | MATL TRANSFER DEVICE | 11,304 | TON | $3.63 | $2.87 | $3.17 | |
| 19 | 40600982 | HMA SURF REM BUTT JT | 2,600 | SQ YD | $26.03 | $4.72 | $17.82 | |
| 20 | 40600985 | PCC SURF REM BUTT JT | 75 | SQ YD | $32.31 | $13.56 | $21.34 | |
| 21 | 40600990 | TEMPORARY RAMP | 40 | SQ YD | $10.29 | $11.55 | $18.56 | |
| 22 | 40603080 | HMA BC IL-19.0 N50 | 16,280 | TON | $100.29 | $103.23 | $99.88 | |
| 23 | 40604050 | HMA SC IL-9.5 C N50 | 11,304 | TON | $105.81 | $117.80 | $112.30 | |
| 24 | 40800029 | BIT MATLS TACK CT | 1,112 | POUND | $0.6100 | $0.8500 | $0.6800 | |
| 25 | 40800050 | INCIDENTAL HMA SURF | 395 | TON | $214.75 | $230.19 | $247.18 | |
| 26 | 42400800 | DETECTABLE WARNINGS | 16 | SQ FT | $100.00 | $52.42 | $22.87 | |
| 27 | 44000100 | PAVEMENT REM | 59 | SQ YD | $42.00 | $49.41 | $22.07 | |
| 28 | 44000155 | HMA SURF REM 1 1/2 | 136,037 | SQ YD | $1.42 | $2.08 | $2.92 | |
| 29 | 44000600 | SIDEWALK REM | 250 | SQ FT | $7.00 | $14.64 | $4.20 | |
| 30 | 44003100 | MEDIAN REMOVAL | 95 | SQ FT | $23.00 | $17.37 | $16.00 | |
| 31 | 44201421 | CL C PATCH T4 15 | 58 | SQ YD | $650.00 | $439.51 | $587.47 | |
| 32 | 48102100 | AGG WEDGE SHLD TYPE B | 3,822 | TON | $53.34 | $20.62 | $45.43 | |
| 33 | 48203100 | HMA SHOULDERS | 562 | TON | $126.19 | $106.07 | $121.21 | |
| 34 | 60608600 | COMB CC&G TM6.06 | 11 | FOOT | $178.00 | $138.44 | $121.77 | |
| 35 | 60609200 | COMB CC&G TM6.12 | 34 | FOOT | $178.00 | $146.28 | $119.76 | |
| 36 | 60618300 | CONC MEDIAN SURF 4 | 90 | SQ FT | $48.00 | $38.55 | $26.62 | |
| 37 | 60920024 | PIPE CULV CLEANED 24 | 40 | FOOT | $144.85 | $92.39 | $88.88 | |
| 38 | 60920030 | PIPE CULV CLEANED 30 | 20 | FOOT | $144.85 | $184.78 | $99.08 | |
| 39 | 66900200 | NON SPL WASTE DISPOSL | 5 | CU YD | $60.30 | $377.41 | $57.32 | |
| 40 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,555.78 | $1,522.50 | $1,479.00 | |
| 41 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,360.50 | $2,310.00 | $2,244.00 | |
| 42 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,360.50 | $2,310.00 | $2,244.00 | |
| 43 | 66901006 | REG SUB MON | 2 | CAL DA | $1,072.96 | $1,050.00 | $1,020.00 | |
| 44 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $3,721.45 | $2,685.72 | $2,523.97 | |
| 45 | 67100100 | MOBILIZATION | 1 | L SUM | $30,962.20 | $47,719.88 | $47,465.61 | |
| 46 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $107.30 | $0.0100 | $1,802.53 | |
| 47 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $9,441.99 | $23,416.87 | $12,594.32 | |
| 48 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1,545.05 | $756.18 | $401.64 | |
| 49 | 70107025 | CHANGEABLE MESSAGE SN | 30 | CAL DA | $118.03 | $120.38 | $102.00 | |
| 50 | 70300100 | SHORT TERM PAVT MKING | 18,701 | FOOT | $1.61 | $0.0100 | $0.4100 | |
| 51 | 70300150 | SHRT TRM PAVT MK REM | 1,559 | SQ FT | $1.98 | $1.06 | $2.83 | |
| 52 | 72000100 | SIGN PANEL T1 | 6.25 | SQ FT | $21.46 | $21.00 | $36.92 | |
| 53 | 73000100 | WOOD SIN SUPPORT | 12 | FOOT | $150.21 | $148.05 | $29.08 | |
| 54 | 78009000 | MOD URETH PM LTR-SYM | 32 | SQ FT | $4.29 | $21.00 | $20.40 | |
| 55 | 78009005 | MOD URETH PM LINE 5 | 106,769 | FOOT | $1.07 | $0.6900 | $0.6700 | |
| 56 | 78009006 | MOD URETH PM LINE 6 | 122 | FOOT | $1.07 | $8.40 | $8.16 | |
| 57 | 78009008 | MOD URETH PM LINE 8 | 102 | FOOT | $1.61 | $10.50 | $10.20 | |
| 58 | 78009012 | MOD URETH PM LINE 12 | 94 | FOOT | $2.15 | $13.65 | $13.26 | |
| 59 | 78009024 | MOD URETH PM LINE 24 | 30 | FOOT | $4.29 | $21.00 | $20.40 | |
| 60 | 78100100 | RAISED REFL PAVT MKR | 587 | EACH | $45.44 | $44.47 | $43.54 | |
| 61 | 78200020 | CURB REFLECTORS | 11 | EACH | $5.36 | $5.25 | $25.00 | |
| 62 | 78300200 | RAISED REF PVT MK REM | 587 | EACH | $13.92 | $12.49 | $18.47 | |
| 63 | 89502400 | REM EX FB INSTAL COMP | 1 | EACH | $751.07 | $3,726.82 | $0.0100 |