(19X-15D)RS-3
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | P. H. Broughton & Sons, Inc. Low bidder | $1,115,449 | ||
| 2 | Truman L. Flatt & Sons Co., Inc. | $1,162,413 | +4.2% | |
| 3 | Illinois Valley Paving, a div of UCM, Inc. | $1,308,315 | +17.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 P. H. Broughton… | #2 Truman L. Flatt… | #3 Illinois Valley… |
|---|---|---|---|---|---|---|---|---|
| 1 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $5,768.59 | $6,725.00 | $6,581.66 | |
| 2 | Z0076600 | TRAINEES | 1,500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 3 | Z0076604 | TRAINEES TPG | 1,500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 4 | 20200100 | EARTH EXCAVATION | 54 | CU YD | $15.96 | $99.86 | $89.16 | |
| 5 | 40200800 | AGG SURF COURSE TY B | 4 | TON | $230.74 | $261.37 | $62.59 | |
| 6 | 40600290 | BIT MATLS TACK CT | 26,298 | POUND | $0.5900 | $0.6700 | $1.10 | |
| 7 | 40600370 | LONG JOINT SEALANT | 14,109 | FOOT | $3.01 | $2.96 | $2.90 | |
| 8 | 40600405 | MATL TRANSFER DEVICE | 3,074 | TON | $3.63 | $3.15 | $3.08 | |
| 9 | 40600982 | HMA SURF REM BUTT JT | 329 | SQ YD | $49.00 | $35.92 | $8.53 | |
| 10 | 40600985 | PCC SURF REM BUTT JT | 34 | SQ YD | $49.44 | $31.41 | $8.53 | |
| 11 | 40600990 | TEMPORARY RAMP | 94 | SQ YD | $18.41 | $18.97 | $13.38 | |
| 12 | 40602965 | HMA BC IL-9.5FG N50 | 2,562 | TON | $102.48 | $104.35 | $123.11 | |
| 13 | 40604050 | HMA SC IL-9.5 C N50 | 3,074 | TON | $102.24 | $101.54 | $118.25 | |
| 14 | 40800029 | BIT MATLS TACK CT | 268 | POUND | $0.5800 | $0.6700 | $1.07 | |
| 15 | 40800050 | INCIDENTAL HMA SURF | 163 | TON | $174.94 | $341.44 | $269.79 | |
| 16 | 44000155 | HMA SURF REM 1 1/2 | 21,142 | SQ YD | $1.27 | $2.06 | $3.23 | |
| 17 | 44000160 | HMA SURF REM 2 3/4 | 17,737 | SQ YD | $1.35 | $3.69 | $3.23 | |
| 18 | 44000200 | DRIVE PAVEMENT REM | 200 | SQ YD | $6.75 | $21.56 | $56.67 | |
| 19 | 44201389 | CL C PATCH T2 13 | 59 | SQ YD | $526.54 | $341.25 | $341.25 | |
| 20 | 44201394 | CL C PATCH T3 13 | 40 | SQ YD | $526.54 | $339.15 | $339.15 | |
| 21 | 44201396 | CL C PATCH T4 13 | 134 | SQ YD | $526.54 | $336.00 | $336.00 | |
| 22 | 48102100 | AGG WEDGE SHLD TYPE B | 351 | TON | $41.81 | $57.14 | $50.53 | |
| 23 | 48203100 | HMA SHOULDERS | 366 | TON | $128.06 | $101.19 | $133.82 | |
| 24 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $3,691.90 | $2,605.76 | $3,525.89 | |
| 25 | 67100100 | MOBILIZATION | 1 | L SUM | $24,404.75 | $25,331.25 | $25,974.52 | |
| 26 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $12,764.61 | $28,875.00 | $28,875.00 | |
| 27 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $797.79 | $12,690.21 | $12,827.26 | |
| 28 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $6,063.19 | $0.0100 | $0.0100 | |
| 29 | 70300100 | SHORT TERM PAVT MKING | 4,233 | FOOT | $1.60 | $0.3800 | $1.68 | |
| 30 | 70300150 | SHRT TRM PAVT MK REM | 471 | SQ FT | $3.25 | $3.11 | $5.07 | |
| 31 | 78004600 | PREF PL PM TD STD LTR/SYM | 123 | SQ FT | $45.74 | $45.15 | $47.25 | |
| 32 | 78004720 | PREF PL PM TD STD L24 | 66 | FOOT | $26.25 | $25.91 | $41.27 | |
| 33 | 78009005 | MOD URETH PM LINE 5 | 42,112 | FOOT | $0.9300 | $0.9100 | $0.8500 | |
| 34 | 78011000 | GRV RCSD PM LTR & SYM | 123 | SQ FT | $6.91 | $6.83 | $47.44 | |
| 35 | 78011125 | GRV RCSD PVT MRKG 25 | 66 | FOOT | $6.38 | $6.30 | $23.40 | |
| 36 | 78100100 | RAISED REFL PAVT MKR | 179 | EACH | $40.11 | $39.60 | $54.34 | |
| 37 | 78300200 | RAISED REF PVT MK REM | 179 | EACH | $11.32 | $12.32 | $15.96 |