43RS-10,SR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Illinois Valley Paving, a div of UCM, Inc. Low bidder | $1,716,492 | ||
| 2 | Truman L. Flatt & Sons Co., Inc. | $1,733,675 | +1.0% | |
| 3 | P. H. Broughton & Sons, Inc. | $1,895,521 | +10.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Illinois Valley… | #2 Truman L. Flatt… | #3 P. H. Broughton… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2020060 | EXC & GR EX SHLD SPL | 267 | UNIT | $340.06 | $321.74 | $464.07 | |
| 2 | X4021000 | TEMP ACCESS- PRIV ENT | 5 | EACH | $0.0100 | $475.87 | $125.00 | |
| 3 | X4022000 | TEMP ACCESS- COM ENT | 3 | EACH | $0.0100 | $1,081.93 | $125.00 | |
| 4 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $6,231.12 | $5,000.00 | $5,821.78 | |
| 5 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 6 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 49 | CU YD | $99.56 | $66.46 | $53.72 | |
| 8 | 35800100 | PREPARATION OF BASE | 176 | SQ YD | $3.90 | $7.58 | $9.13 | |
| 9 | 35800200 | AGG BASE REPAIR | 59 | TON | $0.0100 | $58.38 | $125.00 | |
| 10 | 40200800 | AGG SURF COURSE TY B | 16 | TON | $77.28 | $65.35 | $60.03 | |
| 11 | 40600290 | BIT MATLS TACK CT | 25,438 | POUND | $0.9600 | $0.6800 | $0.6200 | |
| 12 | 40600370 | LONG JOINT SEALANT | 13,694 | FOOT | $2.76 | $3.04 | $3.17 | |
| 13 | 40600982 | HMA SURF REM BUTT JT | 638 | SQ YD | $19.02 | $13.64 | $32.09 | |
| 14 | 40600990 | TEMPORARY RAMP | 83 | SQ YD | $13.85 | $17.36 | $15.55 | |
| 15 | 40602965 | HMA BC IL-9.5FG N50 | 2,355 | TON | $122.37 | $117.71 | $126.97 | |
| 16 | 40604150 | P HMA SC IL-9.5 C N50 | 2,826 | TON | $129.86 | $120.97 | $130.10 | |
| 17 | 40800029 | BIT MATLS TACK CT | 345 | POUND | $0.8900 | $1.06 | $2.50 | |
| 18 | 40800050 | INCIDENTAL HMA SURF | 188 | TON | $236.34 | $325.74 | $218.95 | |
| 19 | 44000155 | HMA SURF REM 1 1/2 | 33,641 | SQ YD | $1.95 | $2.50 | $1.15 | |
| 20 | 44000200 | DRIVE PAVEMENT REM | 228 | SQ YD | $21.40 | $20.11 | $15.65 | |
| 21 | 48102100 | AGG WEDGE SHLD TYPE B | 800 | TON | $39.43 | $51.56 | $60.03 | |
| 22 | 48203023 | HMA SHOULDERS 6 1/2 | 11,904 | SQ YD | $40.38 | $41.16 | $48.83 | |
| 23 | 48203100 | HMA SHOULDERS | 1,019 | TON | $109.88 | $119.88 | $127.96 | |
| 24 | 64200108 | SHOULDER RUM STRIP 8 | 26,729 | FOOT | $0.1800 | $0.3200 | $0.1900 | |
| 25 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,685.83 | $2,492.45 | $4,075.25 | |
| 26 | 67100100 | MOBILIZATION | 1 | L SUM | $21,121.65 | $13,563.09 | $21,620.44 | |
| 27 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $0.0100 | $0.0100 | $805.77 | |
| 28 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $13,435.34 | $7,528.53 | $11,415.04 | |
| 29 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $0.0100 | $1,065.19 | $805.77 | |
| 30 | 70107025 | CHANGEABLE MESSAGE SN | 15 | CAL DA | $176.31 | $100.01 | $214.87 | |
| 31 | 70300100 | SHORT TERM PAVT MKING | 4,112 | FOOT | $1.41 | $0.4800 | $1.61 | |
| 32 | 70300150 | SHRT TRM PAVT MK REM | 1,371 | SQ FT | $0.0100 | $2.99 | $2.25 | |
| 33 | 78009000 | MOD URETH PM LTR-SYM | 122 | SQ FT | $4.00 | $4.20 | $4.30 | |
| 34 | 78009005 | MOD URETH PM LINE 5 | 40,877 | FOOT | $0.9200 | $0.9700 | $0.9900 | |
| 35 | 78009024 | MOD URETH PM LINE 24 | 94 | FOOT | $4.40 | $4.62 | $4.73 | |
| 36 | 78011000 | GRV RCSD PM LTR & SYM | 122 | SQ FT | $5.00 | $5.25 | $5.37 | |
| 37 | 78011030 | GRV RCSD PVT MRKG 6 | 40,877 | FOOT | $0.3700 | $0.3900 | $0.4000 | |
| 38 | 78011125 | GRV RCSD PVT MRKG 25 | 94 | FOOT | $4.50 | $4.73 | $4.83 | |
| 39 | 78100100 | RAISED REFL PAVT MKR | 169 | EACH | $41.52 | $43.60 | $39.69 | |
| 40 | 78300200 | RAISED REF PVT MK REM | 169 | EACH | $6.87 | $13.18 | $12.53 |