| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Jun 14, 2024 | 87832 | DeKalbDistrict 3 | Construction of single lane roundabout at the intersection of Lucinda Avenue an d Normal Road in the City of Dekalb. Work includes aggregate subgrade improveme nt, HMA pavement, driveways, sewer construction, pavement markings, traffic sig nal removal, lighting, and other necessary work. | — | Executed | Elliott and Wood, Inc. $1,820,000 · | ||
| Jun 14, 2024 | 87835 | KankakeeDistrict 3 | Construct a three-span PPC deck beam bridge with HMA approaches and guardrail to carry CH 17 over Exline Slough, 5.9 miles northeast of Manteno. | — | Executed | Tobey's Construction & Cartage, Inc. $910,990 · | ||
| Jun 14, 2024 | 87838 | LaSalleDistrict 3 | Reconstruction of Plank Road to provide a 3 lane roadway with bi-directional tu rn lane from Ed Urban Drive to Midtown Road in the City of Peru. | — | Executed | Advanced Asphalt Company $2,875,373 · | ||
| Jun 14, 2024 | 87839 | DeKalbDistrict 3 | Resurface Sycamore Street from the CN Railroad to Walnut Street, and resurface West Hill Street from Emmett Street to Sycamore Street in Genoa. | — | Executed | Peter Baker & Son Co. $253,877 · | ||
| Jun 14, 2024 | 87849 | GrundyDistrict 3 | Remove and replace two precast channel beam superstructures on Gardner Road over Johnny Run and West Fork of Mazon River. Includes the salvage and reinstallation of S1 bridge rail and HMA approach pavment. | — | Executed | D. Construction, Inc. $1,144,745 · | ||
| Jun 14, 2024 | 87867 | GrundyDistrict 3 | HMA resurfacing, curb and gutter, sidewalks and pavement markings on Carbon Hill Road from IL 113 to Spring Road in Coal City. | — | Executed | P. T. Ferro Construction Co. $438,984 · | ||
| Aug 2, 2024 | 66K82 | BureauLaSalleDistrict 3 | Milling and resurfacing (designed overlay), structure repairs, patching, pavement marking, and raised reflective markers on FAI 80 (I-80) from 1 mile west of IL 89 to 0.7 mile west of IL 251. | — | Executed | Advanced Asphalt Company $21,687,508 · | ||
| Aug 2, 2024 | 66P43 | LivingstonDistrict 3 | HMA milling and resurfacing, pavement marking, and raised reflective markers on FAP 786 (IL 170) from south of IL 17 to the intersection of IL 23, including the northbound right turn lane of IL 23. | — | Executed | Kankakee Valley Construction Company, Inc. $3,524,732 · | ||
| Aug 2, 2024 | 66P59 | VariousDistrict 3 | Vegetation management control along various routes in various counties in District 3. | — | Executed | Semper Fi Yard Service, Inc. d/b/a Semper Fi Land Service, Inc. $314,620 · | ||
| Aug 2, 2024 | 87848 | DeKalbDistrict 3 | Construct a two-cell concrete box culvert with aggregate roadway surface and grading on Anderland Road over North Branch of Kishwaukee River. | — | Executed | McCarthy Improvement Company $397,900 · | ||
| Aug 2, 2024 | 87865 | LaSalleDistrict 3 | Resurfacing 8th Street from Crosat St. to Sterling St. and Richard Hallett Road from US 6 to the south city limits of LaSalle. | — | Executed | Advanced Asphalt Company $535,616 · | ||
| Sep 20, 2024 | 66E54 | LivingstonDistrict 3 | About 2.32 miles of milling and resurfacing designed overlay of IL 116 and OR 66 with intersection improvements, drainage and ADA improvements. Along IL-116 from the west leg of Ewing Drive to Old Rt. 66 and along Old Rt. 66 from IL-116 to the south approach slab of the bridge over the Vermilion River in Pontiac. | — | Executed | Kankakee Valley Construction Company, Inc. $7,271,812 · | ||
| Sep 20, 2024 | 66P11 | KendallLaSalleDistrict 3 | 5.62 miles of milling and resurfacing on US 52 from east of the IL-71 intersection to the north leg of Townhouse Road. | — | Executed | D. Construction, Inc. $2,515,676 · | ||
| Sep 20, 2024 | 66P19 | FordDistrict 3 | 11.01 miles of milling and resurfacing on IL 115 from south of E 1600N RD to IL 9 in Roberts City. | — | Executed | Iroquois Paving Corporation $7,755,834 · | ||
| Sep 20, 2024 | 66P42 | LaSalleLivingstonDistrict 3 | 16.21 miles of HMA milling and resurfacing on IL 170 from 0.2 mile south of River Road in Seneca to the intersection with IL 17. | — | Executed | D. Construction, Inc. $6,376,242 · | ||
| Sep 20, 2024 | 66P50 | LaSalleDistrict 3 | 35.55 miles gross of On-Call Class A pavement patching, pavement striping, and other related items to complete the work as described herein on I-39 from the Marshall County Line to the Lee County Line including interchange ramps. | — | Executed | G. M. Sipes Construction, Inc. $2,186,049 · | ||
| Sep 20, 2024 | 66P58 | LaSalleDistrict 3 | Removal of HMA shoulders and replacing with PCC shoulders, striping, and traffic control at SN 050-0195 carrying US Route 6 over I-39 and SN 050-0181 carrying CH 19 over I-39. | — | Executed | G. M. Sipes Construction, Inc. $1,146,789 · | ||
| Sep 20, 2024 | 66P72 | VariousDistrict 3 | Tree removal in Bureau, Ford, Iroquois, Kankakee, Kendall, LaSalle, and Grundy Counties. | — | Executed | Thor General Contracting LLC $266,375 · | ||
| Sep 20, 2024 | 66P80 | LaSalleDistrict 3 | 2,596 gross ft of intermittent milling and resurfacing the mainline, merge lanes, and gore areas as show on plan details on F.A.I. Route 80 (I-80) from 0.5 miles west of the I-80/I-39 Interchange (just east of SN 050-0093) to west of SN 050-0178 in LaSalle County. | — | Executed | Advanced Asphalt Company $148,365 · | ||
| Nov 8, 2024 | 66L79 | LivingstonDistrict 3 | Bridge replacement of SN 053-0062 on IL 116 over Scattering Point Creek east of Flanagan. 600' | — | Executed | Riber Construction, Inc. $1,865,719 · | ||
| Nov 8, 2024 | 66P32 | IroquoisDistrict 3 | Bridge repairs to SN 038-0187 carrying US 24 over a tributary of Prairie Creek 3.74 miles west of I-57. | — | Executed | Iroquois Paving Corporation $354,306 · | ||
| Nov 8, 2024 | 66P35 | DeKalbDistrict 3 | Slope wall removal and replacement, erosion repairs to SN 019-0005 carrying IL 23 over Chicago, Central and Pacific Railroad. | — | Executed | Phoenix Corporation of the Quad Cities $137,674 · | ||
| Nov 8, 2024 | 66P61 | BureauDistrict 3 | Removing deteriorated wingwalls and partial barrel removal, clearing and grubbing adjacent slopes and installation of gabion baskets and slope mattress at SN 006-2543_carrying IL 29 over a stream 0.8 miles west of the US 6 and IL 89 intersection. | — | Executed | D. Construction, Inc. $238,332 · | ||
| Nov 8, 2024 | 87868 | KendallDistrict 3 | Replace the bridge carrying Minkler Road over Morgan Creek, 1.7 miles south of IL 71 in Oswego. | — | Executed | D. Construction, Inc. $2,509,615 · | ||
| Nov 8, 2024 | 87869 | KendallDistrict 3 | HMA Resurfacing, pavement patching, PCC sidewalk, curb and gutter, drainage improvements, pavement markings, and signage on East Van Emmon Street from IL 47 to the Yorkville City Limit. | — | Executed | D. Construction, Inc. $382,160 · | ||
| Nov 8, 2024 | 87870 | GrundyDistrict 3 | Sidewalk improvements along Mitchell, Main, and Railroad Streets in Braceville. | — | Executed | Gallagher Asphalt Corporation $248,978 · | ||
| Nov 8, 2024 | 87872 | GrundyDistrict 3 | Resurface Ashton Road from US 6 to north of Locust Road in the City of Morris. | — | Executed | D. Construction, Inc. $199,524 · | ||
| Jan 17, 2025 | 46655 | VariousDistrict 3 | Repairing various widths of pavement marking including lines, letters, numbers, and symbols on various routes throughout District 3. | — | Executed | Varsity Striping & Construction Co. $1,718,445 · | ||
| Jan 17, 2025 | 66K94 | IroquoisDistrict 3 | 0.2 mile bridge replacement at Little Beaver Creek. 1.2 miles north of Papineau Road. | — | Executed | Iroquois Paving Corporation $2,649,190 · | ||
| Jan 17, 2025 | 66P33 | BureauDistrict 3 | Deck patching, approach pavement resurfacing, parapet repairs, expansion joint replacement, substructure repairs, and slope wall repairs at SN 006-0056. | — | Executed | D. Construction, Inc. $439,369 · | ||
| Jan 17, 2025 | 66P34 | BureauDistrict 3 | bridge repairs including deck patching, expansion joint replacement, approach slab replacement, pavement and shoulder replacement at SN 006-0101 carrying IL 92 over the branch of Masters Creek 0.7 miles west of Van Orin. | — | Executed | D. Construction, Inc. $466,071 · | ||
| Jan 17, 2025 | 66P36 | LaSalleDistrict 3 | Shoulder replacement, seeding, storm sewers, drainage repairs, bridge repairs including expansion joint replacement, PPC I-beam repairs structural repair of concrete, bridge washing and other related construction work at SN 050-0175 carrying CH 33 over I-39 3.0 miles north of the I-39 and I-80 interchange. | — | Executed | D. Construction, Inc. $425,002 · | ||
| Jan 17, 2025 | 66P60 | KendallDistrict 3 | Approximately 6.1 miles of centerline joint repair, pavement marking improvements and intermediate resurfacing of approximately 22,000 sq yds on IL 126 from 80 ft east of Wing Street to 500 ft west of County Line Road in Kendall County. | — | Executed | Austin Tyler Construction, Inc. $776,365 · | ||
| Jan 17, 2025 | 66P81 | LivingstonDistrict 3 | Cleaning and painting structural steel on SN's 053-0116 and 053-0019. | — | Executed | ERA-Valdivia Contractors, Inc. $658,785 · | ||
| Jan 17, 2025 | 66P82 | DeKalbDistrict 3 | Cleaning and painting all structural steel of SN's 019-0038 and 019-0040. | — | Executed | ERA-Valdivia Contractors, Inc. $167,056 · | ||
| Jan 17, 2025 | 66P90 | BureauLivingstonDistrict 3 | Bridge deck sealing with the parapets/curbs on various routes at various locations throughout Bureau and Livingston Counties. | — | Executed | M & M Concrete, Inc. $159,932 · | ||
| Jan 17, 2025 | 66P96 | GrundyDistrict 3 | Repair and maintain traffic signals, flashing beacons, roadway lighting, speed display signs, and other electrical services within Grundy County. | — | Active | Meade Inc. $341,893 · | ||
| Jan 17, 2025 | 66P97 | VariousDistrict 3 | Repair and maintain traffic signals, flashing beacons, roadway lighting, speed display signs, and other electrical services along various routes in Bureau, LaSalle, DeKalb, and Kendall Counties. | — | Executed | Laser Electric, Inc. $2,232,605 · | ||
| Jan 17, 2025 | 66P98 | VariousDistrict 3 | Repair and maintain traffic signals, flashing beacons, roadway lighting, speed display signs, and other electrical services along various routes in Ford, Iroquois, and Livingston Counties. | — | Executed | Leo P. Kelly Electric, Incorporated $384,646 · | ||
| Jan 17, 2025 | 66P99 | KankakeeDistrict 3 | Repair and maintain traffic signals, flashing beacons, roadway lighting, speed display signs, and other electrical services within Kankakee County. | — | Active | Outsen Electric, Incorporated $193,820 · | ||
| Jan 17, 2025 | 87805 | KankakeeDistrict 3 | Reconstruction of Manteno-Deslem Road to provide a 3-lane roadway with bi-directional turn lane from US 45/52 to Spuce Street in Manteno. | — | Executed | Kankakee Valley Construction Company, Inc. $9,569,046 · | ||
| Jan 17, 2025 | 87840 | GrundyDistrict 3 | Construction of a HMA multi-use path and pedestrian bridge with segmental block wall, utility adjustments, and culverts along McEvilly Road in Minooka. | — | Executed | D. Construction, Inc. $1,708,477 · | ||
| Jan 17, 2025 | 87852 | LaSalleDistrict 3 | Rehabiliate the bridge carrying Walnut Street over the IC Railroad, 0.9 miles east of IL 71. | — | Rejected | D. Construction, Inc. $946,209 · | ||
| Jan 17, 2025 | 87873 | KendallDistrict 3 | HMA rsurfacing and reconstruct portions of Hale Street from E. Dearborn St. to Larson Street in Plano. Reconstruciton includes cross slope and crown correction, curb and gutter, ADA ramps and a shared-use path. | — | Executed | Geneva Construction Company $1,060,850 · | ||
| Mar 7, 2025 | 66K70 | BureauDistrict 3 | 350 ft of Bridge Repairs (SN 006-0097) over Green River, 1.4 MI W OF IL 40. | — | Executed | Martin & Company Excavating $650,504 · | ||
| Mar 7, 2025 | 66M57 | DeKalbDistrict 3 | HMA milling and resurfacing (designed overlay), culvert replacement, pavement marking, ditch cleaning and raised reflective markers on IL 72 beginning at IL-23 (N) and ends at Kane County Line; HMA milling and resurfacing (standard overlay), pavement marking, and raised reflective markers on IL 23 beginning at IL 72 and ends at the McHenry County line. 7.183 miles gross length. | — | Executed | Curran Contracting Company $2,734,986 · | ||
| Mar 7, 2025 | 66N41 | PutnamDistrict 3 | Washing the entire structural steel superstructure, washing and sealing the concrete (deck surface, inside face of parapets, top surface of the abutments and piers) at Structure No. 078-0047 carrying IL Route 89 over the Illinois River approximately 0.91 mile south of US Route 6. | — | Executed | All States Painting, Inc. $74,028 · | ||
| Mar 7, 2025 | 66N42 | LaSalleDistrict 3 | Washing the entire structural steel superstructure, washing and sealing the concrete (deck surface, inside face of parapets, top surface of the abutments and piers) at various structures over the Illinois River in LaSalle County. | — | Executed | Interstate Maintenance, Incorporated $262,302 · | ||
| Mar 7, 2025 | 66P49 | DeKalbDistrict 3 | HMA milling and resurfacing patching, pavement marking and reflective markers on FAP 307 (IL 64), from 0.2 mile east of Airport Rd to Kane County Line in DeKalb County. Approximately 2.946 miles gross length. | — | Executed | Curran Contracting Company $1,541,645 · | ||
| Mar 7, 2025 | 66P51 | GrundyDistrict 3 | Milling and resurfacing 1.15 miles of OR 129 from Main St. to Carbon Hill Rd. in Gardner, along with the replacement of 3 culverts within the Project Bounds. | — | Executed | D. Construction, Inc. $680,856 · | ||
| Mar 7, 2025 | 66P78 | VariousDistrict 3 | Weed spraying to aid in weed control along various routes in Bureau, LaSalle, Grundy, Livingston, Kankakee, Iroquois, and Ford Counties. | — | Executed | The Daltons Inc. $168,697 · | ||
| Mar 7, 2025 | 66P83 | LivingstonDistrict 3 | Cleaning and painting all structural steel of SN 053-0160 carrying IL 17 over Prairie Creek, 1.0 mile east of IL 23. | — | Executed | ERA-Valdivia Contractors, Inc. $143,680 · | ||
| Mar 7, 2025 | 66P84 | KankakeeDistrict 3 | Cleaning and painting all steel components of structure 046-0114 carrying I-57 over Minnie Creek, 4.3 miles north of the Chebanse interchange. | — | Executed | ERA-Valdivia Contractors, Inc. $127,908 · | ||
| Mar 7, 2025 | 66P95 | LaSalleDistrict 3 | HMA milling and resurfacing on the frontage road, parallel to IL 23 on the north side of Streator, and is approximately 0.22 mile long. | — | Executed | Kankakee Valley Construction Company, Inc. $180,130 · | ||
| Mar 7, 2025 | 66R00 | VariousDistrict 3 | Litter removal from the interstate highways at interchanges and rest areas throughout District 3. | — | Active | The Final Connection, Inc. $327,337 · | ||
| Mar 7, 2025 | 66R05 | LaSalleDistrict 3 | Replacing the 6" centerline pavement marking with 9" contrast pavement marking tape and replacing the 8" lane lines at interchange ramps on I-39 from north of Oglesby Interchange at M.M. 54 to M.M. 76.4. | — | Executed | A. C. Pavement Striping Co. $936,906 · | ||
| Mar 7, 2025 | 66R06 | LaSalleLivingstonDistrict 3 | Contrast pavement marking of the 8" lane lines on IL 23 at Richards Rd in LaSalle County and ending at Adams St in Livingston County and also on IL 18 beginning at Second Ave and ending at Wasson St in LaSalle County. | — | Executed | Varsity Striping & Construction Co. $268,247 · | ||
| Mar 7, 2025 | 66R07 | VariousDistrict 3 | Removal and replacement of damaged or deteriorated sand module impact attenuators on various interstate routes in various counties in District 3. | — | Executed | |||
| Mar 7, 2025 | 66R09 | LivingstonDistrict 3 | Excavating and grading existing shoulders and placing aggregate shoulders on OR 66 from IL Route 116 to E. 1600 Road. | — | Executed | H. J. Eppel & Co. $88,186 · | ||
| Mar 7, 2025 | 66R29 | BureauDistrict 3 | 2.3 miles HMA milling and resurfacing, patching, pavement marking, and reflective markers on SBI 7C (2775E RD), from US 6 to IL 29 in Bureau County. | — | Executed | Advanced Asphalt Company $1,461,525 · | ||
| Mar 7, 2025 | 66R30 | BureauDistrict 3 | HMA milling and resurfacing, patching, pavement marking and reflective markers on SBI 88 (NEW BEDFORD RD), from Main St in New Bedford to IL 40 in Bureau County. 1.74 mile gross length. | — | Executed | Advanced Asphalt Company $985,903 · | ||
| Mar 7, 2025 | 66R34 | IroquoisDistrict 3 | HMA milling and resurfacing 2" (SMART) of the mainline, shoulder work, pavement marking, and raised reflectors on FAI 57 from 0.5 mile north of IL 116 to 1.6 miles north of CH4. 4.88 miles gross. | — | Executed | Iroquois Paving Corporation $9,823,667 · | ||
| Mar 7, 2025 | 87738 | BureauDistrict 3 | Construct a single span PPC deck beam bridge to carrying 600 Avenue North over Silver Creek. | — | Executed | Curnyn Construction Co. $429,897 · | ||
| Mar 7, 2025 | 87850 | IroquoisDistrict 3 | Removal of the existing sub-structure, and construction of a new concrete stub abutments, bearing and joint replacement, and reconstruction of the approaches to the bridge carrying CH 31 over the Iroquois River, one mile north of Watseka. | — | Executed | Iroquois Paving Corporation $1,179,351 · | ||
| Mar 7, 2025 | 87853 | LaSalleDistrict 3 | Replace the bridge carrying Kelly Street over Prairie Creek, north of Bluff Street. | — | Executed | D. Construction, Inc. $852,364 · | ||
| Mar 7, 2025 | 87861 | LaSalleDistrict 3 | HMA resurfacing wiht HMA and Aggregate shoulders on County Highway 51 from Old Chicago Road to the City of Marseilles. | — | Executed | Advanced Asphalt Company $1,516,752 · | ||
| Mar 7, 2025 | 87866 | DeKalbDistrict 3 | Reconstrut the intersection of Glidden Road and Baseline Road. | — | Executed | Martin & Company Excavating $442,950 · | ||
| Mar 7, 2025 | 87875 | DeKalbDistrict 3 | Reconstruction of Main Street between BNSF Railroad and Knights Road in Sandwich. Work includes fulldepth pavement reclamation, PCC and HMA Pavement, sidewalks, curb and gutter, and storm sewers. | — | Executed | Fischer Excavating, Inc. $4,466,099 · | ||
| Mar 7, 2025 | 87876 | LaSalleDistrict 3 | Construct a PCC Shared-use path with a pedestrian bridge over Il 125. This project is located south of Wenzel Road in the City of Peru. | — | Executed | D. Construction, Inc. $4,565,811 · | ||
| Mar 7, 2025 | 87877 | LaSalleDistrict 3 | Resurfacing and Shoulder Widening on CH 4 from CH 15 to the Grundy County Line. | — | Executed | D. Construction, Inc. $1,868,000 · | ||
| Mar 7, 2025 | 87878 | LaSalleDistrict 3 | Resurfacing and shoulder widening on CH 4 from IL 71 to CH 15. | — | Executed | Advanced Asphalt Company $1,448,524 · | ||
| Mar 7, 2025 | 87879 | LaSalleDistrict 3 | HMA resurfacing of Iowa Avenue, Proter Street, and Bronson Street from Main Street to Johnson Street in Streator. Inlcudes Curb and Gutter, sidewalks, and storm sewers. | — | Executed | Advanced Asphalt Company $1,674,922 · | ||
| Apr 25, 2025 | 46662 | VariousDistrict 3 | Removing and replacing raised reflective pavement markers and reflectors in Bureau, Grundy, Kendall, LaSalle, and Putnam Counties. | — | Executed | Marking Specialists Corporation $412,448 · | ||
| Apr 25, 2025 | 46663 | VariousDistrict 3 | Removing and replacing raised reflective pavement markers and reflectors_on various highways in Ford, Iroquois, Kankakee, and Livingston Counties. | — | Executed | Marking Specialists Corporation $583,460 · | ||
| Apr 25, 2025 | 46940 | GrundyDistrict 3 | Roadway and parking lot improvements (HMA resurfacing, removal and replacement of existing parking lot, drainage improvements, ADA sidewalk, and pavement marking and other work) within the_Goose Lake Prairie State Natural Area in Grundy County. 1.4 miles gross length internal park roads. | — | Executed | D. Construction, Inc. $1,889,874 · | ||
| Apr 25, 2025 | 66A85 | KankakeeDistrict 3 | HMA milling and resurfacing (designed overlay), culvert replacement, pavement marking, ditch cleaning and raised reflective markers on FAS 1317 (IL 113) from the Will County Line to Edgewater Dr in Limestone, 6.14 miles gross. | — | Executed | Kankakee Valley Construction Company, Inc. $3,511,811 · | ||
| Apr 25, 2025 | 66M48 | BureauDistrict 3 | Replacing the deck and approaches, abutment conversion to semi-integral abutments, substructure repairs, slope wall replacement, roadway resurfacing, guardrail replacement as needed, a private driveway reconstruction, and pavement marking on FAP 646 (IL 40) on the south side of Buda at SN 006-0138 carrying FAP 646 over the Burlington Northern Santa Fe Railroad. | — | Executed | D. Construction, Inc. $1,939,442 · | ||
| Apr 25, 2025 | 66M99 | LivingstonDistrict 3 | Milling and resurfacing (Standard Overlay) and ADA improvement on US 24 from the Mclean Co line to 0.3 mi E of 7th St in Fairbury City, 4.32 miles gross length. | — | Executed | Iroquois Paving Corporation $2,667,505 · | ||
| Apr 25, 2025 | 66N61 | KankakeeDistrict 3 | Installation of a flashing red beacon at each of the stop controlled approaches to the intersection of IL 115 and S 7000 W Rd (Lehigh RD), and installation of a flashing yellow beacon at each of the advanced intersection warning signs adjacent to IL 115. | — | Executed | D. Construction, Inc. $165,198 · | ||
| Apr 25, 2025 | 66P37 | LivingstonDistrict 3 | Bridge repairs including paved shoulder replacement, expansion joint replacement, bearing replacement, PPC I-Beam Repairs, approach slab repairs, deck patching and other related construction items at dual Structures, 053-0007 EB and 053-0008 WB carrying O.R. 66 over the Vermilion River, 0.55 miles south of IL Route 23 in Pontiac. | — | Executed | Tobey's Construction & Cartage, Inc. $1,048,761 · | ||
| Apr 25, 2025 | 66P47 | GrundyDistrict 3 | 6.77 miles of crack and joint sealing on FAS 301 from IL-47_to Mary Ave in Coal City. | — | Executed | Denler, Inc. $62,830 · | ||
| Apr 25, 2025 | 66P48 | LivingstonDistrict 3 | Routing and filling the cracks along the centerline, as well as any significant transverse cracks, and pavement markings along various routes in Livingston County. 45.61 miles gross length. | — | Executed | Denler, Inc. $193,871 · | ||
| Apr 25, 2025 | 66P73 | GrundyDistrict 3 | Furnishing and installing Buttertfly Dynamic Message Signs on I-80 in Grundy County at M.M. 108.5 and M.M. 119.5. 1.663 miles gross length. | — | Executed | John Burns Construction Company $1,251,719 · | ||
| Apr 25, 2025 | 66P89 | BureauDistrict 3 | Removing existing inlets, storm sewer, installing inlets, paved ditch, guardrail removal and replacement, pipe drains, pipe underdrains, grading and shaping ditches and other related construction items on IL 26 from the intersection with 1950 Ave North and ending at the City County Park Rd entrance north of Princeton. 1.1 mile gross lenth. | — | Executed | Gillan Construction LLC $601,985 · | ||
| Apr 25, 2025 | 66R11 | LaSalleDistrict 3 | Aggregate Wedge Shoulder, Type B along I 39 at LaSalle county extending from Marshall County Line (M.M. 40.32) to Lee County Line (M.M. 76.85) and includes exit and entrance ramps at the IL 18, Tonica, IL 71, IL 251, Oglesby Spur, US 6, US 52 and US 34 Interchanges, 36.5 miles gross length. | — | Executed | Phoenix Corporation of the Quad Cities $704,100 · | ||
| Apr 25, 2025 | 66R12 | GrundyLaSalleDistrict 3 | Pavement patching along I-80 in LaSalle and Grundy counties_extending from east of Illinois 23 interchange (M.M.90) to Grundy county line (M.M.103), LaSalle County Line (M.M.103) to Seneca interchange (M.M.105), Brisbon interchange Grundy county, and Minooka interchange (Ridge Rd), 15 miles gross length. | — | Executed | D. Construction, Inc. $579,432 · | ||
| Apr 25, 2025 | 66R13 | KendallDistrict 3 | Pavement patching along F.A.P. Route 326 extending from IL Route 47/71 intersection (L.M. 0.00) to IL Route 47/US 34 Intersection (L.M. 2.80), 2.8 miles gross length. | — | Executed | D. Construction, Inc. $186,398 · | ||
| Apr 25, 2025 | 66R14 | KendallDistrict 3 | Roadway resurfacing along IL 47 in Kendall county and extends from Sta6811 +72.00 to STA 6852+22.00, 0.757 miles gross length. | — | Executed | D. Construction, Inc. $457,951 · | ||
| Apr 25, 2025 | 66R15 | DeKalbLaSalleDistrict 3 | Furnishing and placing Aggregate Wedge Shoulders, Type B adjacent to existing mainline pavement or stabilized shoulders along IL 23 and US 34 in LaSalle County. | — | Executed | Phoenix Corporation of the Quad Cities $199,908 · | ||
| Apr 25, 2025 | 66R16 | LaSalleDistrict 3 | 4 miles Centerline Crack Sealing beginning at 0.3 Mi South of N. 40th Rd and ends at 1.3 MI. South of US Route 34. | — | Executed | SKC Construction, Inc. $23,407 · | ||
| Apr 25, 2025 | 66R17 | IroquoisDistrict 3 | Class B pavement patching and other related construction items on US Route 24 beginning at the east ramps of I-57 Interchange and ends at the US 24/45 intersection. | — | Executed | SNC Construction, Inc. $306,453 · | ||
| Apr 25, 2025 | 66R19 | BureauDistrict 3 | Milling, resurfacing, aggregate shoulders, rumble strips, pavement marking, raised reflective pavement markers, and other related construction items on IL Route 89 beginning at the north approach pavement of SN 006-0178 and ending at Cleveland St in Ladd. It also includes the djacent I-80 Frontage Rd beginning at IL 89 intersection and ends at the Ladd Maintenance facility. | — | Executed | Advanced Asphalt Company $987,951 · | ||
| Apr 25, 2025 | 66R26 | GrundyKendallDistrict 3 | Over 70,000 feet of pavement marking in various locations in District 3. | — | Executed | Precision Pavement Markings Inc. $847,344 · | ||
| Apr 25, 2025 | 66R28 | LivingstonDistrict 3 | CMP culvert entrance removal and replacement with a Precast Concrete Box Culvert on IL 116 0.61 miles east of F.A.I Route 55. At commercial entrance (Walmart Dr). | — | Executed | H. J. Eppel & Co. $257,331 · | ||
| Apr 25, 2025 | 66R31 | GrundyLivingstonDistrict 3 | Milling and resurfacing (Designed Overlay), patching,_pavement marking and raised reflectors on FAS 298 from IL 47 in Dwight to IL 53 in Gardner, for a total of 8.1 miles. | — | Executed | D. Construction, Inc. $3,397,233 · | ||
| Apr 25, 2025 | 66R33 | KankakeeDistrict 3 | Milling and resurfacing 1 1/2" (SMART), patching, aggregate shoulders, pavement marking, and raised reflectors on FAP 332 (IL 1) from Will County Line to IL 17, 3.91 miles total. | — | Executed | Gallagher Asphalt Corporation $1,938,778 · | ||
| Apr 25, 2025 | 66R35 | KankakeeDistrict 3 | 8.84 miles milling and SMART resurfacing from 0.5 miles south of Larry Power Road to Will County Line. | — | Executed | Kankakee Valley Construction Co., Inc. & Gallagher Asphalt Corporation $19,511,604 · | ||
| Apr 25, 2025 | 66R36 | LaSalleDistrict 3 | Milling and resurfacing 2" on I 80 from 1.4 miles east of the Bureau County Line to 0.1 miles east of IL 351. Additional work includes shoulder improvement and ramp resurfacing at IL 251, 2.4 miles gross length. | — | Executed | Advanced Asphalt Company $5,338,646 · | ||
| Apr 25, 2025 | 87862 | LivingstonDistrict 3 | HMA resurfacing with aggregate shoulders on various county highways in Livingston County. | — | Executed | H. J. Eppel & Co. $1,638,174 · | ||
| Apr 25, 2025 | 87880 | BureauDistrict 3 | Replace sidewalks and ADA ramp improvements along Cleveland street from Peru Avenue to Summit Avenue in Ladd. | — | Executed | Gillan Construction LLC $255,362 · |
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.