(128)RS-5 & (25)RS-5
- Let date
- Friday, March 7, 2025
- Contract
- 66M57 · job page
- District
- District 3
- County
- Dekalb
- Highway
- Limits
- HMA milling and resurfacing (designed overlay), culvert replacement, pavement marking, ditch cleaning and raised reflective markers on IL 72 beginning at IL-23 (N) and ends at Kane County Line; HMA milling and resurfacing (standard overlay), pavement marking, and raised reflective markers on IL 23 beginning at IL 72 and ends at the McHenry County line. 7.183 miles gross length.
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Curran Contracting Company Low bidder | $2,734,986 | ||
| 2 | Peter Baker & Son Co. | $2,890,298 | +5.7% | |
| 3 | Plote Construction, Inc. | $3,091,121 | +13.0% | |
| 4 | Rock Road Companies, Inc. | $3,297,470 | +20.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Curran Contract… | #2 Peter Baker & S… | #3 Plote Construct… | #4 Rock Road Compa… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X1200050 | BOX CULVERT REMOVAL | 53 | FOOT | $100.00 | $100.00 | $78.50 | $250.00 | |
| 2 | X2040805 | FURNISHED EXCAV SPL | 5 | CU YD | $0.0100 | $887.00 | $75.00 | $101.00 | |
| 3 | X4401198 | HMA SURF REM VAR DP | 4,216 | SQ YD | $5.40 | $6.40 | $7.50 | $6.49 | |
| 4 | X6350204 | LINEAR DELIN PANELS 4 | 29 | EACH | $55.00 | $58.60 | $58.10 | $65.65 | |
| 5 | X6350206 | LINEAR DELIN PANELS 6 | 4 | EACH | $65.00 | $58.03 | $68.00 | $95.95 | |
| 6 | X7200061 | TEMP INFO SIGNING | 84 | SQ FT | $25.00 | $25.00 | $25.00 | $12.12 | |
| 7 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $4,000.00 | $5,000.00 | $6,000.00 | $12,758.52 | |
| 8 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 9 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 10 | 20101400 | NITROGEN FERT NUTR | 33 | POUND | $2.00 | $5.00 | $2.00 | $2.02 | |
| 11 | 20101500 | PHOSPHORUS FERT NUTR | 33 | POUND | $2.00 | $5.00 | $2.00 | $2.02 | |
| 12 | 20101600 | POTASSIUM FERT NUTR | 33 | POUND | $2.00 | $5.00 | $2.00 | $2.02 | |
| 13 | 20200100 | EARTH EXCAVATION | 300 | CU YD | $45.00 | $5.90 | $28.00 | $63.00 | |
| 14 | 20800150 | TRENCH BACKFILL | 18 | CU YD | $40.00 | $40.00 | $61.10 | $50.00 | |
| 15 | 21400100 | GRADING & SHAP DITCH | 2,630 | FOOT | $7.15 | $14.60 | $8.55 | $18.45 | |
| 16 | 25000210 | SEEDING CL 2A | 0.4 | ACRE | $2,700.00 | $8,000.00 | $2,700.00 | $2,727.00 | |
| 17 | 25100630 | EROSION CONTR BLANKET | 1,753 | SQ YD | $2.00 | $2.00 | $2.00 | $2.02 | |
| 18 | 28100707 | STONE DUMP RIP CL A4 | 6 | SQ YD | $170.00 | $400.00 | $165.00 | $350.00 | |
| 19 | 28200200 | FILTER FABRIC | 6 | SQ YD | $1.00 | $22.00 | $84.70 | $20.00 | |
| 20 | 31100100 | SUB GRAN MAT A | 9 | TON | $80.00 | $80.00 | $59.30 | $50.00 | |
| 21 | 40200800 | AGG SURF COURSE TY B | 148 | TON | $50.00 | $46.85 | $45.00 | $51.88 | |
| 22 | 40600290 | BIT MATLS TACK CT | 86,504 | POUND | $1.00 | $0.0100 | $0.0100 | $0.7500 | |
| 23 | 40600370 | LONG JOINT SEALANT | 37,709 | FOOT | $2.45 | $3.19 | $2.32 | $2.50 | |
| 24 | 40600400 | MIX CR JTS FLANGEWYS | 37 | TON | $350.00 | $55.00 | $600.00 | $236.14 | |
| 25 | 40600405 | MATL TRANSFER DEVICE | 21,368 | TON | $2.20 | $1.85 | $3.25 | $2.25 | |
| 26 | 40600990 | TEMPORARY RAMP | 988 | SQ YD | $10.00 | $3.40 | $1.00 | $18.88 | |
| 27 | 40603085 | HMA BC IL-19.0 N70 | 6,845 | TON | $62.00 | $70.25 | $80.00 | $76.94 | |
| 28 | 40603200 | P HMA BC IL-4.75 N50 | 3,965 | TON | $82.00 | $93.50 | $115.00 | $117.85 | |
| 29 | 40604062 | HMA SC IL-9.5 D N70 | 10,558 | TON | $66.00 | $76.15 | $84.00 | $82.87 | |
| 30 | 40800050 | INCIDENTAL HMA SURF | 468 | TON | $120.00 | $153.55 | $170.00 | $158.21 | |
| 31 | 44000155 | HMA SURF REM 1 1/2 | 308 | SQ YD | $2.65 | $13.52 | $2.10 | $7.74 | |
| 32 | 44000159 | HMA SURF REM 2 1/2 | 70,534 | SQ YD | $2.25 | $2.30 | $1.85 | $3.06 | |
| 33 | 44000164 | HMA SURF REM 3 3/4 | 54,324 | SQ YD | $2.65 | $3.29 | $3.00 | $3.89 | |
| 34 | 44201794 | CL D PATCH T3 12 | 32 | SQ YD | $340.00 | $398.00 | $475.00 | $379.55 | |
| 35 | 48102100 | AGG WEDGE SHLD TYPE B | 2,933 | TON | $15.00 | $37.30 | $39.00 | $31.96 | |
| 36 | 542A5473 | P CUL CL A 1 EQRS 18 | 72 | FOOT | $200.00 | $200.00 | $300.00 | $300.00 | |
| 37 | 54214713 | PRCF END S EL EQRS 18 | 4 | EACH | $5,000.00 | $5,000.00 | $3,600.00 | $3,000.00 | |
| 38 | 59300100 | CONTR LOW-STRENG MATL | 1.2 | CU YD | $1,000.00 | $2,694.00 | $952.60 | $2,000.00 | |
| 39 | 60905305 | BOX CUL TO BE CLEANED | 156 | FOOT | $59.00 | $55.00 | $55.00 | $195.00 | |
| 40 | 63500105 | DELINEATORS | 34 | EACH | $100.00 | $68.00 | $58.60 | $65.65 | |
| 41 | 64200108 | SHOULDER RUM STRIP 8 | 32,594 | FOOT | $0.4500 | $0.5000 | $0.5000 | $0.7300 | |
| 42 | 66900200 | NON SPL WASTE DISPOSL | 126 | CU YD | $60.00 | $79.00 | $61.00 | $139.70 | |
| 43 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,500.00 | $1,125.00 | $1,125.00 | $1,225.00 | |
| 44 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,900.00 | $4,100.00 | $4,100.00 | $3,500.00 | |
| 45 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $900.00 | $500.00 | $500.00 | $900.00 | |
| 46 | 66901006 | REG SUB MON | 3 | CAL DA | $700.00 | $700.00 | $700.00 | $890.00 | |
| 47 | 67000400 | ENGR FIELD OFFICE A | 5 | CAL MO | $2,500.00 | $3,500.00 | $3,500.00 | $2,184.09 | |
| 48 | 67100100 | MOBILIZATION | 1 | L SUM | $236,000.00 | $145,816.78 | $133,000.00 | $92,266.59 | |
| 49 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $100.00 | $11,700.00 | $20,400.00 | $1.01 | |
| 50 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $10,700.00 | $100.00 | $100.00 | $12,928.00 | |
| 51 | 70300100 | SHORT TERM PAVT MKING | 11,143 | FOOT | $0.5000 | $0.4600 | $1.25 | $0.8600 | |
| 52 | 70300150 | SHRT TRM PAVT MK REM | 1,240 | SQ FT | $2.50 | $5.40 | $3.70 | $2.52 | |
| 53 | 78004600 | PREF PL PM TD STD LTR/SYM | 122 | SQ FT | $50.00 | $20.00 | $20.00 | $50.50 | |
| 54 | 78004640 | PREF PL PM TD STD L 8 | 194 | FOOT | $10.00 | $10.00 | $10.00 | $10.10 | |
| 55 | 78004720 | PREF PL PM TD STD L24 | 146 | FOOT | $50.00 | $20.00 | $20.00 | $50.50 | |
| 56 | 78005150 | EPOXY PVT MK LINE 12 | 148 | FOOT | $15.00 | $18.00 | $18.00 | $15.15 | |
| 57 | 78009004 | MOD URETH PM LINE 4 | 202,473 | FOOT | $0.5000 | $0.4900 | $0.4900 | $0.5000 | |
| 58 | 78009006 | MOD URETH PM LINE 6 | 19,186 | FOOT | $1.00 | $0.5500 | $0.5500 | $1.01 | |
| 59 | 78011000 | GRV RCSD PM LTR & SYM | 122 | SQ FT | $45.00 | $5.00 | $5.00 | $45.45 | |
| 60 | 78011040 | GRV RCSD PVT MRKG 8 | 194 | FOOT | $7.50 | $2.00 | $2.00 | $7.57 | |
| 61 | 78011125 | GRV RCSD PVT MRKG 25 | 146 | FOOT | $45.00 | $5.00 | $5.00 | $45.45 | |
| 62 | 78100100 | RAISED REFL PAVT MKR | 470 | EACH | $42.50 | $34.00 | $34.00 | $42.92 | |
| 63 | 78300200 | RAISED REF PVT MK REM | 470 | EACH | $13.50 | $1.00 | $0.5000 | $13.28 |