22-00200-00-PV
- Let date
- Friday, June 14, 2024
- Contract
- 87832 · job page
- District
- District 3
- County
- Dekalb
- Highway
- Limits
- Construction of single lane roundabout at the intersection of Lucinda Avenue an d Normal Road in the City of Dekalb. Work includes aggregate subgrade improveme nt, HMA pavement, driveways, sewer construction, pavement markings, traffic sig nal removal, lighting, and other necessary work.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Elliott and Wood, Inc. Low bidder | $1,820,000 | ||
| 2 | Fischer Excavating, Inc. | $2,259,079 | +24.1% | |
| 3 | Alliance Contractors, Inc. | $2,294,306 | +26.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Elliott and Woo… | #2 Fischer Excavat… | #3 Alliance Contra… |
|---|---|---|---|---|---|---|---|---|
| 1 | C2C01124 | S-BUXUS KORE X GV 2 | 8 | EACH | $225.00 | $225.00 | $330.00 | |
| 2 | K0013000 | P PL PRAIRI 2X4 DPPLG | 150 | UNIT | $17.50 | $15.00 | $10.00 | |
| 3 | X0326806 | WASHOUT BASIN | 1 | L SUM | $100.00 | $1,500.00 | $1,500.00 | |
| 4 | X0540000 | BRICK PAVERS | 1,888 | SQ FT | $17.50 | $29.50 | $17.50 | |
| 5 | X1400268 | REMVL LMNAIR SALVAGE | 1 | EACH | $500.00 | $882.00 | $500.00 | |
| 6 | X1400326 | R R FL BEACON A COMP | 3 | EACH | $38,500.00 | $35,168.00 | $38,500.00 | |
| 7 | X1700107 | CURB WALL SPL | 47 | SQ FT | $80.00 | $50.00 | $25.00 | |
| 8 | X1700112 | BRICK PAVER REMOVAL | 907 | SQ FT | $1.50 | $3.00 | $2.00 | |
| 9 | X5510010 | STORM SEW CONNECTION | 27 | EACH | $2,000.00 | $3,800.00 | $500.00 | |
| 10 | X5610706 | WATER MAIN REMOV 6 | 41 | FOOT | $100.00 | $75.00 | $100.00 | |
| 11 | X5640150 | FIRE HYDNT ASSY COMP | 2 | EACH | $12,000.00 | $14,000.00 | $25,000.00 | |
| 12 | X6026050 | SANITARY MANHOLE ADJ | 1 | EACH | $1,200.00 | $1,800.00 | $1,500.00 | |
| 13 | X6026051 | SAN MAN RECONST | 4 | EACH | $5,500.00 | $2,300.00 | $3,580.00 | |
| 14 | X6030310 | FR & LIDS ADJUST SPL | 2 | EACH | $1,600.00 | $1,665.00 | $3,900.00 | |
| 15 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $15,300.00 | $33,000.00 | $65,300.00 | |
| 16 | X8300001 | LIGHT POLE SPECIAL | 8 | EACH | $6,100.00 | $9,700.00 | $6,100.00 | |
| 17 | X8410102 | TEMP LIGHTING SYSTEM | 1 | L SUM | $30,000.00 | $26,194.00 | $30,000.00 | |
| 18 | Z0004514 | HMA DRIVEWAY PAVT 4 | 33 | SQ YD | $101.53 | $70.00 | $120.00 | |
| 19 | Z0013797 | STAB CONSTR ENTRANCE | 700 | SQ YD | $1.00 | $23.00 | $1.00 | |
| 20 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,000.00 | $32,450.00 | $23,750.00 | |
| 21 | Z0030850 | TEMP INFO SIGNING | 84 | SQ FT | $18.00 | $16.00 | $18.00 | |
| 22 | Z0033026 | MAIN EX LT SYS COMP | 1 | L SUM | $12,000.00 | $14,280.00 | $12,000.00 | |
| 23 | Z0055300 | RUMBLE STRIP | 3 | EACH | $2,600.00 | $2,537.00 | $500.00 | |
| 24 | Z0056608 | STORM SEW WM REQ 12 | 177 | FOOT | $101.00 | $140.00 | $126.00 | |
| 25 | Z0056612 | STORM SEW WM REQ 18 | 43 | FOOT | $130.00 | $200.00 | $181.30 | |
| 26 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 27 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 28 | 20101100 | TREE TRUNK PROTECTION | 5 | EACH | $500.00 | $350.00 | $250.00 | |
| 29 | 20101200 | TREE ROOT PRUNING | 6 | EACH | $450.00 | $450.00 | $300.00 | |
| 30 | 20101350 | TREE PRUN OVER 10 | 1 | EACH | $1,500.00 | $1,250.00 | $500.00 | |
| 31 | 20200100 | EARTH EXCAVATION | 2,159 | CU YD | $45.00 | $80.00 | $10.00 | |
| 32 | 20201200 | REM & DISP UNS MATL | 216 | CU YD | $45.00 | $30.00 | $10.00 | |
| 33 | 20800150 | TRENCH BACKFILL | 90 | CU YD | $1.00 | $45.00 | $75.00 | |
| 34 | 21001000 | GEOTECH FAB F/GR STAB | 648 | SQ YD | $4.75 | $3.00 | $2.00 | |
| 35 | 21101615 | TOPSOIL F & P 4 | 1,375 | SQ YD | $8.25 | $9.00 | $10.50 | |
| 36 | 21101685 | TOPSOIL F & P 24 | 487 | SQ YD | $35.00 | $51.00 | $49.00 | |
| 37 | 21301084 | EXPLOR TRENCH 84 | 50 | FOOT | $55.00 | $50.00 | $50.00 | |
| 38 | 25000210 | SEEDING CL 2A | 0.5 | ACRE | $4,500.00 | $3,600.00 | $4,500.00 | |
| 39 | 25000400 | NITROGEN FERT NUTR | 34 | POUND | $5.00 | $5.00 | $5.00 | |
| 40 | 25000500 | PHOSPHORUS FERT NUTR | 34 | POUND | $5.00 | $5.00 | $5.00 | |
| 41 | 25000600 | POTASSIUM FERT NUTR | 34 | POUND | $5.00 | $5.00 | $5.00 | |
| 42 | 25100630 | EROSION CONTR BLANKET | 1,818 | SQ YD | $3.25 | $3.25 | $2.00 | |
| 43 | 28000250 | TEMP EROS CONTR SEED | 38 | POUND | $25.00 | $25.00 | $14.00 | |
| 44 | 28000510 | INLET FILTERS | 29 | EACH | $285.00 | $285.00 | $25.00 | |
| 45 | 28001100 | TEMP EROS CONTR BLANK | 1,818 | SQ YD | $1.00 | $1.00 | $1.40 | |
| 46 | 30300001 | AGG SUBGRADE IMPROVE | 216 | CU YD | $55.00 | $80.00 | $19.00 | |
| 47 | 30300112 | AGG SUBGRADE IMPR 12 | 3,651 | SQ YD | $18.00 | $30.00 | $14.35 | |
| 48 | 35101600 | AGG BASE CSE B 4 | 1,127 | SQ YD | $13.00 | $29.00 | $4.25 | |
| 49 | 35102000 | AGG BASE CSE B 8 | 88 | SQ YD | $30.00 | $18.00 | $8.50 | |
| 50 | 35501314 | HMA BASE CSE 7 1/2 | 2,801 | SQ YD | $40.00 | $40.00 | $43.13 | |
| 51 | 40201000 | AGGREGATE-TEMP ACCESS | 259 | TON | $25.00 | $54.00 | $15.00 | |
| 52 | 40600290 | BIT MATLS TACK CT | 1,382 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 53 | 40600370 | LONG JOINT SEALANT | 379 | FOOT | $20.00 | $20.00 | $21.00 | |
| 54 | 40603080 | HMA BC IL-19.0 N50 | 353 | TON | $100.00 | $100.00 | $120.61 | |
| 55 | 40604060 | HMA SC IL-9.5 D N50 | 403 | TON | $100.00 | $100.00 | $122.70 | |
| 56 | 42000501 | PCC PVT 10 JOINTED | 281 | SQ YD | $185.00 | $170.00 | $284.50 | |
| 57 | 42300200 | PCC DRIVEWAY PAVT 6 | 55 | SQ YD | $85.00 | $95.00 | $98.00 | |
| 58 | 42400200 | PC CONC SIDEWALK 5 | 9,500 | SQ FT | $8.50 | $10.00 | $15.05 | |
| 59 | 42400300 | PC CONC SIDEWALK 6 | 646 | SQ FT | $9.50 | $11.25 | $15.80 | |
| 60 | 42400800 | DETECTABLE WARNINGS | 342 | SQ FT | $35.00 | $35.00 | $40.00 | |
| 61 | 44000100 | PAVEMENT REM | 3,945 | SQ YD | $35.00 | $18.00 | $40.00 | |
| 62 | 44000157 | HMA SURF REM 2 | 647 | SQ YD | $10.00 | $15.50 | $12.43 | |
| 63 | 44000200 | DRIVE PAVEMENT REM | 68 | SQ YD | $17.00 | $14.00 | $20.00 | |
| 64 | 44000500 | COMB CURB GUTTER REM | 1,493 | FOOT | $8.00 | $8.00 | $40.00 | |
| 65 | 44000600 | SIDEWALK REM | 9,983 | SQ FT | $1.50 | $4.00 | $5.00 | |
| 66 | 44003100 | MEDIAN REMOVAL | 3,754 | SQ FT | $2.00 | $15.00 | $6.00 | |
| 67 | 44201373 | CL C PATCH T1 12 | 4 | SQ YD | $255.00 | $311.00 | $143.50 | |
| 68 | 44201377 | CL C PATCH T2 12 | 25 | SQ YD | $175.00 | $210.00 | $143.50 | |
| 69 | 44201381 | CL C PATCH T3 12 | 17 | SQ YD | $172.00 | $207.00 | $143.50 | |
| 70 | 44201383 | CL C PATCH T4 12 | 80 | SQ YD | $155.00 | $192.00 | $143.50 | |
| 71 | 44201796 | CL D PATCH T4 12 | 45 | SQ YD | $130.00 | $100.00 | $172.00 | |
| 72 | 550A0050 | STORM SEW CL A 1 12 | 28 | FOOT | $90.00 | $110.00 | $111.05 | |
| 73 | 550A0340 | STORM SEW CL A 2 12 | 27 | FOOT | $91.00 | $110.00 | $111.05 | |
| 74 | 550A0360 | STORM SEW CL A 2 15 | 71 | FOOT | $92.00 | $115.00 | $114.55 | |
| 75 | 550A0380 | STORM SEW CL A 2 18 | 10 | FOOT | $93.00 | $165.00 | $119.45 | |
| 76 | 550A0410 | STORM SEW CL A 2 24 | 37 | FOOT | $94.00 | $145.00 | $144.70 | |
| 77 | 55100200 | STORM SEWER REM 6 | 41 | FOOT | $24.00 | $36.00 | $10.00 | |
| 78 | 55100500 | STORM SEWER REM 12 | 29 | FOOT | $25.00 | $40.00 | $10.00 | |
| 79 | 55100700 | STORM SEWER REM 15 | 85 | FOOT | $26.00 | $40.00 | $15.00 | |
| 80 | 55100900 | STORM SEWER REM 18 | 43 | FOOT | $27.00 | $40.00 | $15.00 | |
| 81 | 55101200 | STORM SEWER REM 24 | 42 | FOOT | $28.00 | $40.00 | $20.00 | |
| 82 | 56103000 | D I WATER MAIN 6 | 41 | FOOT | $300.00 | $170.00 | $132.95 | |
| 83 | 56103200 | D I WATER MAIN 10 | 6 | FOOT | $400.00 | $650.00 | $361.15 | |
| 84 | 56400500 | FIRE HYDNTS TO BE REM | 2 | EACH | $950.00 | $2,375.00 | $1,200.00 | |
| 85 | 60108501 | PIPE UNDERDR T 3 | 94 | FOOT | $30.00 | $24.00 | $88.10 | |
| 86 | 60201105 | CB TA 4 DIA T11F&G | 12 | EACH | $3,000.00 | $4,370.00 | $8,700.00 | |
| 87 | 60204805 | CB TA 5 DIA T11F&G | 1 | EACH | $4,000.00 | $5,640.00 | $13,500.00 | |
| 88 | 60207905 | CB TC T11F&G | 4 | EACH | $2,500.00 | $3,100.00 | $5,500.00 | |
| 89 | 60218400 | MAN TA 4 DIA T1F CL | 4 | EACH | $3,000.00 | $4,300.00 | $8,450.00 | |
| 90 | 60221100 | MAN TA 5 DIA T1F CL | 3 | EACH | $4,000.00 | $5,400.00 | $13,100.00 | |
| 91 | 60223800 | MAN TA 6 DIA T1F CL | 3 | EACH | $7,000.00 | $7,900.00 | $19,300.00 | |
| 92 | 60224446 | MAN TA 7 DIA T1F CL | 1 | EACH | $11,000.00 | $12,000.00 | $27,100.00 | |
| 93 | 60250200 | CB ADJUST | 3 | EACH | $750.00 | $1,100.00 | $250.00 | |
| 94 | 60250500 | CB ADJ NEW T1F CL | 1 | EACH | $1,100.00 | $1,800.00 | $750.00 | |
| 95 | 60255500 | MAN ADJUST | 7 | EACH | $900.00 | $1,140.00 | $250.00 | |
| 96 | 60255800 | MAN ADJ NEW T1F CL | 2 | EACH | $1,200.00 | $1,800.00 | $750.00 | |
| 97 | 60265700 | VV ADJUST | 7 | EACH | $900.00 | $1,050.00 | $250.00 | |
| 98 | 60266600 | VALVE BOX ADJ | 2 | EACH | $300.00 | $780.00 | $125.00 | |
| 99 | 60500040 | REMOV MANHOLES | 10 | EACH | $1,000.00 | $1,000.00 | $250.00 | |
| 100 | 60500050 | REMOV CATCH BAS | 1 | EACH | $1,000.00 | $1,000.00 | $250.00 | |
| 101 | 60500060 | REMOV INLETS | 2 | EACH | $1,000.00 | $1,000.00 | $150.00 | |
| 102 | 60600605 | CONC CURB TB | 173 | FOOT | $45.00 | $49.00 | $47.00 | |
| 103 | 60603800 | COMB CC&G TB6.12 | 2,382 | FOOT | $42.00 | $48.00 | $41.35 | |
| 104 | 60605900 | COMB CC&G TB9.12 | 53 | FOOT | $45.00 | $57.00 | $72.45 | |
| 105 | 60608582 | COMB CC&G TM4.24 | 264 | FOOT | $45.00 | $65.00 | $78.45 | |
| 106 | 60609200 | COMB CC&G TM6.12 | 60 | FOOT | $44.00 | $50.00 | $52.50 | |
| 107 | 60618320 | CONC MEDIAN SURF 6 | 3,511 | SQ FT | $9.00 | $9.00 | $27.05 | |
| 108 | 60624600 | CORRUGATED MED | 748 | SQ FT | $12.50 | $17.00 | $32.75 | |
| 109 | 67100100 | MOBILIZATION | 1 | L SUM | $85,058.32 | $135,000.00 | $130,000.00 | |
| 110 | 70307100 | TEMP PVT MK LTR & SYM T4 TAPE | 245 | SQ FT | $6.15 | $3.00 | $6.15 | |
| 111 | 70307120 | TEMP PVT MK L4 T4 TAPE | 1,584 | FOOT | $2.00 | $1.20 | $2.00 | |
| 112 | 70307130 | TEMP PVT MK L6 T4 TAPE | 418 | FOOT | $2.25 | $2.00 | $2.25 | |
| 113 | 70307160 | TEMP PVT MK L12 T4 TAPE | 810 | FOOT | $3.45 | $3.50 | $3.45 | |
| 114 | 70307210 | TEMP PVT MK L24 T4 TAPE | 13 | FOOT | $6.15 | $10.00 | $6.15 | |
| 115 | 72000100 | SIGN PANEL T1 | 179 | SQ FT | $32.00 | $20.00 | $32.00 | |
| 116 | 72400310 | REMOV SIGN PANEL T1 | 28 | SQ FT | $25.00 | $12.00 | $25.00 | |
| 117 | 72900100 | METAL POST TY A | 43 | FOOT | $20.00 | $12.00 | $20.00 | |
| 118 | 72900200 | METAL POST TY B | 314 | FOOT | $22.00 | $13.00 | $22.00 | |
| 119 | 78000100 | THPL PVT MK LTR & SYM | 245 | SQ FT | $6.80 | $10.00 | $6.80 | |
| 120 | 78000200 | THPL PVT MK LINE 4 | 1,584 | FOOT | $1.13 | $2.05 | $1.13 | |
| 121 | 78000400 | THPL PVT MK LINE 6 | 418 | FOOT | $1.70 | $3.18 | $1.70 | |
| 122 | 78000600 | THPL PVT MK LINE 12 | 810 | FOOT | $3.40 | $7.50 | $3.40 | |
| 123 | 78000650 | THPL PVT MK LINE 24 | 13 | FOOT | $6.80 | $15.00 | $6.80 | |
| 124 | 78011000 | GRV RCSD PM LTR & SYM | 245 | SQ FT | $5.50 | $2.00 | $5.50 | |
| 125 | 78011025 | GRV RCSD PVT MRKG 5 | 1,584 | FOOT | $1.15 | $0.5000 | $1.15 | |
| 126 | 78011035 | GRV RCSD PVT MRKG 7 | 418 | FOOT | $1.90 | $1.00 | $1.90 | |
| 127 | 78011065 | GRV RCSD PVT MRKG 13 | 810 | FOOT | $2.70 | $2.50 | $2.70 | |
| 128 | 78011125 | GRV RCSD PVT MRKG 25 | 13 | FOOT | $5.50 | $5.00 | $5.50 | |
| 129 | 78300202 | PVT MKG REM WTR BLAST | 1,817 | SQ FT | $0.1000 | $3.00 | $0.1000 | |
| 130 | 81028360 | UNDRGRD C PVC 2 1/2 | 768 | FOOT | $28.00 | $17.08 | $28.00 | |
| 131 | 81702130 | EC C XLP USE 1C 6 | 942 | FOOT | $2.00 | $2.66 | $2.00 | |
| 132 | 81702160 | EC C XLP USE 1C 1/0 | 4,710 | FOOT | $4.00 | $2.75 | $4.00 | |
| 133 | 83600200 | LIGHT POLE FDN 24D | 44 | FOOT | $320.00 | $278.59 | $320.00 | |
| 134 | 89500120 | REM EX SERV INSTALL | 1 | EACH | $800.00 | $2,204.00 | $800.00 | |
| 135 | 89502300 | REM ELCBL FR CON | 5,000 | FOOT | $2.00 | $0.5600 | $2.00 | |
| 136 | 89502375 | REMOV EX TS EQUIP | 1 | EACH | $12,000.00 | $20,505.00 | $12,000.00 | |
| 137 | 89502380 | REMOV EX HANDHOLE | 4 | EACH | $500.00 | $821.75 | $500.00 | |
| 138 | 89502382 | REMOV EX DBL HANDHOLE | 2 | EACH | $1,500.00 | $1,082.25 | $1,500.00 | |
| 139 | 89502385 | REMOV EX CONC FDN | 9 | EACH | $800.00 | $1,062.50 | $800.00 |