$185.91Avg low bid / FOOT
$170.61Avg of all bids
—Avg engineer's estimate
7Jobs · 5,366 FOOT
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 4 | 474 | $238.72 | $242.17 |
| 2025 | 3 | 4,892 | $180.80 | $160.62 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 12, 2026 | 62U72 | MchenryDistrict 1 | 46 FOOT | $385.00 | Martam Construction Incorporated |
| Feb 27, 2026 | 61M26 | CookDistrict 1 | 271 FOOT | $219.00 | A Lamp Concrete Contractors, Inc. |
| Feb 27, 2026 | 61M27 | CookDistrict 1 | 64 FOOT | $285.00 | A Lamp Concrete Contractors, Inc. |
| Jan 16, 2026 | 61M09 | CookDistrict 1 | 93 FOOT | $192.00 | Martam Construction Incorporated |
| Apr 25, 2025 | 62X94 | MchenryDistrict 1 | 1,915 FOOT | $230.00 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. |
| Mar 7, 2025 | 87875 | DekalbDistrict 3 | 2,795 FOOT | $150.00 | Fischer Excavating, Inc. |
| Mar 7, 2025 | 61J84 | KaneDistrict 1 | 182 FOOT | $136.00 | R. W. Dunteman Company |