Bid tab 87866

Let Mar 7, 2025 · District 3 · Dekalb

‹ Mar 2025 results

20-00272-00-SP

Let date
Friday, March 7, 2025
Contract
87866 · job page
District
District 3
County
Dekalb
Highway
Limits
Reconstrut the intersection of Glidden Road and Baseline Road.
Classification
·
Project number

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Martin & Company Excavating Low bidder $442,950
2 Curran Contracting Company $460,171 +3.9%
3 Elliott and Wood, Inc. $523,254 +18.1%
4 Performance Construction and Engineering, LLC $598,013 +35.0%
5 Fischer Excavating, Inc. $613,914 +38.6%
6 Alliance Contractors, Inc. $670,479 +51.4%

Bid tab: unit prices 33 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Martin & Compan…#2 Curran Contract…#3 Elliott and Woo…#4 Performance Con…#5 Fischer Excavat…#6 Alliance Contra…
1X1200050 BOX CULVERT REMOVAL78FOOT $48.00 $20.00 $20.00 $155.00 $100.00 $100.00
2X7010216 TRAF CONT & PROT SPL1L SUM $10,000.00 $20,000.00 $4,875.00 $30,000.00 $8,900.00 $36,664.00
3Z0013798 CONSTRUCTION LAYOUT1L SUM $4,500.00 $7,000.00 $4,200.00 $12,500.00 $4,850.00 $4,850.00
4Z0030850 TEMP INFO SIGNING42SQ FT $16.00 $25.00 $25.00 $25.00 $14.00 $25.00
520200100 EARTH EXCAVATION3,418CU YD $24.30 $28.00 $38.00 $40.00 $38.00 $15.00
620800150 TRENCH BACKFILL16CU YD $38.00 $40.00 $40.00 $20.00 $25.00 $35.00
725000210 SEEDING CL 2A0.75ACRE $3,000.00 $2,500.00 $2,500.00 $2,500.00 $5,780.00 $2,500.00
825000400 NITROGEN FERT NUTR69POUND $3.00 $2.00 $2.00 $2.00 $4.00 $2.00
925000500 PHOSPHORUS FERT NUTR69POUND $3.00 $2.00 $2.00 $2.00 $4.00 $2.00
1025000600 POTASSIUM FERT NUTR69POUND $3.00 $2.00 $2.00 $2.00 $4.00 $2.00
1125100630 EROSION CONTR BLANKET3,657SQ YD $1.40 $1.00 $1.00 $1.00 $1.45 $1.00
1228000250 TEMP EROS CONTR SEED75POUND $1.90 $1.00 $1.00 $5.00 $7.00 $1.00
1328000305 TEMP DITCH CHECKS180FOOT $18.00 $15.00 $15.00 $15.00 $14.00 $15.00
1428000400 PERIMETER EROS BAR648FOOT $5.00 $4.00 $4.00 $5.00 $3.65 $4.00
1528000500 INLET & PIPE PROTECT2EACH $150.00 $150.00 $330.00 $500.00 $330.00 $50.00
1630300118 AGG SUBGRADE IMPR 181,975SQ YD $24.38 $18.00 $32.00 $22.00 $40.00 $39.50
1735101800 AGG BASE CSE B 61,290SQ YD $8.79 $8.00 $17.50 $13.00 $13.00 $20.35
1840600290 BIT MATLS TACK CT638POUND $0.1000 $2.50 $2.50 $0.0100 $1.00 $2.50
1940600370 LONG JOINT SEALANT656FOOT $22.00 $14.00 $14.00 $16.75 $15.75 $14.00
2040603080 HMA BC IL-19.0 N501,089TON $84.00 $75.00 $75.00 $82.00 $80.00 $75.00
2140604050 HMA SC IL-9.5 C N50198TON $86.00 $92.00 $92.00 $122.00 $120.00 $92.00
2244000100 PAVEMENT REM1,780SQ YD $7.70 $10.12 $15.00 $18.00 $8.00 $25.00
2344000155 HMA SURF REM 1 1/2495SQ YD $7.35 $10.00 $10.00 $30.00 $30.00 $10.00
2444201771 CL D PATCH T4 1068SQ YD $114.00 $110.00 $110.00 $100.00 $350.00 $110.00
2548101600 AGGREGATE SHLDS B 8564SQ YD $11.00 $17.50 $17.50 $19.00 $24.00 $17.50
2648203029 HMA SHOULDERS 8580SQ YD $40.35 $40.00 $40.00 $41.00 $41.00 $40.00
2750104400 CONC HEADWALL REMOVAL3EACH $175.00 $175.00 $175.00 $3,000.00 $1,200.00 $500.00
2850105220 PIPE CULVERT REMOV49FOOT $6.00 $20.00 $20.00 $65.00 $95.00 $25.00
2954001001 BOX CUL END SEC C12EACH $9,200.00 $7,500.00 $7,500.00 $7,000.00 $10,500.00 $9,450.00
3054010402 PCBC 4X278FOOT $465.00 $550.00 $550.00 $625.00 $675.00 $1,358.00
31542D0229 P CUL CL D 1 2451FOOT $105.00 $170.00 $170.00 $125.00 $250.00 $105.50
3267100100 MOBILIZATION1L SUM $24,000.00 $28,000.00 $29,244.00 $34,800.00 $36,000.00 $115,900.00
3378001110 PAINT PVT MK LINE 45,180FOOT $0.6600 $1.25 $0.6000 $0.6000 $1.25 $0.6000