23-00405-00-WR
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $1,868,000 | ||
| 2 | Advanced Asphalt Company | $2,012,012 | +7.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Advanced Asphal… |
|---|---|---|---|---|---|---|---|
| 1 | X2020410 | EARTH EXCAVATION SPL | 0.1 | CU YD | $10,000.00 | $500.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $52,000.00 | $11,350.00 | |
| 3 | Z0055600 | RUMBLE STRIP | 92 | SQ YD | $105.00 | $24.00 | |
| 4 | 20200500 | EARTH EXC WID | 2,730 | CU YD | $35.00 | $30.00 | |
| 5 | 40600275 | BIT MATLS PR CT | 4 | POUND | $0.0100 | $5.00 | |
| 6 | 40600290 | BIT MATLS TACK CT | 63,764 | POUND | $0.0100 | $0.8000 | |
| 7 | 40600370 | LONG JOINT SEALANT | 30,800 | FOOT | $3.00 | $2.15 | |
| 8 | 40600982 | HMA SURF REM BUTT JT | 245 | SQ YD | $10.00 | $25.00 | |
| 9 | 40602965 | HMA BC IL-9.5FG N50 | 6,211 | TON | $75.00 | $85.00 | |
| 10 | 40604000 | HMA SC IL-9.5FG C N50 | 6,404 | TON | $79.00 | $85.00 | |
| 11 | 44000152 | HMA SURF REM 3/4 | 92 | SQ YD | $10.00 | $6.00 | |
| 12 | 44000153 | HMA SURF REM 1 | 1,284 | SQ YD | $5.00 | $6.00 | |
| 13 | 48102100 | AGG WEDGE SHLD TYPE B | 1,528 | TON | $35.00 | $40.45 | |
| 14 | 48203021 | HMA SHOULDERS 6 | 14,716 | SQ YD | $26.80 | $33.50 | |
| 15 | 64200108 | SHOULDER RUM STRIP 8 | 59,931 | FOOT | $0.1800 | $0.1800 | |
| 16 | 67100100 | MOBILIZATION | 1 | L SUM | $112,500.00 | $120,000.00 | |
| 17 | 70300100 | SHORT TERM PAVT MKING | 31,872 | FOOT | $0.0100 | $0.0100 | |
| 18 | 78001110 | PAINT PVT MK LINE 4 | 34,830 | FOOT | $0.4400 | $0.1800 | |
| 19 | 78001130 | PAINT PVT MK LINE 6 | 61,433 | FOOT | $0.7200 | $0.2400 | |
| 20 | 78001150 | PAINT PVT MK LINE 12 | 14 | FOOT | $12.05 | $0.5500 | |
| 21 | 78004280 | PREF PL PM TB INL L24 | 43 | FOOT | $93.50 | $132.00 |