23-00037-00-RS
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | P. T. Ferro Construction Co. Low bidder | $438,984 | ||
| 2 | D. Construction, Inc. | $451,185 | +2.8% | |
| 3 | Austin Tyler Construction, Inc. | $509,783 | +16.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 P. T. Ferro Con… | #2 D. Construction… | #3 Austin Tyler Co… |
|---|---|---|---|---|---|---|---|---|
| 1 | XX006429 | SIDEWALK, SPECIAL | 2,167 | SQ FT | $12.00 | $15.00 | $18.75 | |
| 2 | Z0017400 | DRAIN UTIL STR ADJ | 10 | EACH | $450.00 | $1,000.00 | $745.00 | |
| 3 | 40600290 | BIT MATLS TACK CT | 9,277 | POUND | $0.0100 | $1.00 | $0.0100 | |
| 4 | 40603200 | P HMA BC IL-4.75 N50 | 1,155 | TON | $100.00 | $105.00 | $118.00 | |
| 5 | 40604050 | HMA SC IL-9.5 C N50 | 1,750 | TON | $87.00 | $88.00 | $91.00 | |
| 6 | 42400800 | DETECTABLE WARNINGS | 200 | SQ FT | $19.00 | $35.00 | $46.20 | |
| 7 | 44000157 | HMA SURF REM 2 | 20,615 | SQ YD | $2.50 | $1.80 | $3.00 | |
| 8 | 44000500 | COMB CURB GUTTER REM | 500 | FOOT | $20.00 | $10.00 | $11.00 | |
| 9 | 44000600 | SIDEWALK REM | 1,070 | SQ FT | $4.50 | $5.00 | $4.40 | |
| 10 | 48101200 | AGGREGATE SHLDS B | 25 | TON | $65.00 | $80.00 | $125.00 | |
| 11 | 60604400 | COMB CC&G TB6.18 | 500 | FOOT | $65.00 | $45.00 | $70.00 | |
| 12 | 60605000 | COMB CC&G TY B-6.24 | 25 | FOOT | $70.00 | $75.00 | $95.00 | |
| 13 | 67100100 | MOBILIZATION | 1 | L SUM | $22,500.00 | $27,000.00 | $31,000.00 | |
| 14 | 78000100 | THPL PVT MK LTR & SYM | 160 | SQ FT | $4.75 | $6.60 | $5.23 | |
| 15 | 78000200 | THPL PVT MK LINE 4 | 11,500 | FOOT | $0.7400 | $0.9600 | $0.8100 | |
| 16 | 78000400 | THPL PVT MK LINE 6 | 1,200 | FOOT | $1.20 | $1.82 | $1.32 | |
| 17 | 78000500 | THPL PVT MK LINE 8 | 225 | FOOT | $1.60 | $2.15 | $1.76 | |
| 18 | 78000600 | THPL PVT MK LINE 12 | 275 | FOOT | $2.40 | $3.65 | $2.64 | |
| 19 | 78000650 | THPL PVT MK LINE 24 | 80 | FOOT | $4.75 | $6.60 | $5.23 |