22-00042-00-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Peter Baker & Son Co. Low bidder | $253,877 | ||
| 2 | Curran Contracting Company | $289,915 | +14.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Peter Baker & S… | #2 Curran Contract… |
|---|---|---|---|---|---|---|---|
| 1 | XX009588 | SEEDING COMPLETE | 1 | L SUM | $9,890.00 | $8,890.00 | |
| 2 | X0326806 | WASHOUT BASIN | 1 | L SUM | $1,837.50 | $100.00 | |
| 3 | X4240420 | PC CONC SIDEWALK 4 SP | 471 | SQ FT | $17.85 | $25.00 | |
| 4 | X4404400 | PAVT REMOVAL SPL | 20 | SQ YD | $41.55 | $40.00 | |
| 5 | X4810200 | AGGREGATE SHLD REMOVL | 51 | CU YD | $107.00 | $90.00 | |
| 6 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $9,205.00 | $15,000.00 | |
| 7 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $4,900.00 | $5,000.00 | |
| 8 | 28000500 | INLET & PIPE PROTECT | 11 | EACH | $375.00 | $285.00 | |
| 9 | 30300001 | AGG SUBGRADE IMPROVE | 141 | CU YD | $121.00 | $75.00 | |
| 10 | 35102200 | AGG BASE CSE B 10 | 14 | SQ YD | $53.00 | $30.00 | |
| 11 | 40600290 | BIT MATLS TACK CT | 5,086 | POUND | $0.0100 | $0.0100 | |
| 12 | 40600370 | LONG JOINT SEALANT | 1,897 | FOOT | $6.10 | $5.50 | |
| 13 | 40600990 | TEMPORARY RAMP | 572 | SQ YD | $1.00 | $7.50 | |
| 14 | 40602978 | HMA BC IL-9.5 N50 | 475 | TON | $86.00 | $117.00 | |
| 15 | 40604060 | HMA SC IL-9.5 D N50 | 475 | TON | $90.00 | $117.00 | |
| 16 | 42400800 | DETECTABLE WARNINGS | 40 | SQ FT | $47.25 | $35.00 | |
| 17 | 44000161 | HMA SURF REM 3 | 5,685 | SQ YD | $5.40 | $5.25 | |
| 18 | 44000500 | COMB CURB GUTTER REM | 74 | FOOT | $36.75 | $1.00 | |
| 19 | 44000600 | SIDEWALK REM | 518 | SQ FT | $4.20 | $1.00 | |
| 20 | 44201682 | CL D PATCH T2 3 | 14 | SQ YD | $100.00 | $110.00 | |
| 21 | 48101500 | AGGREGATE SHLDS B 6 | 313 | SQ YD | $41.50 | $25.00 | |
| 22 | 60255500 | MAN ADJUST | 5 | EACH | $1,087.00 | $1,800.00 | |
| 23 | 60265700 | VV ADJUST | 7 | EACH | $1,587.00 | $1,800.00 | |
| 24 | 60603800 | COMB CC&G TB6.12 | 73 | FOOT | $94.50 | $110.00 | |
| 25 | 67100100 | MOBILIZATION | 1 | L SUM | $15,048.00 | $27,000.00 | |
| 26 | 72400205 | REM & REL SIGN PANEL ASMBLY TA | 1 | EACH | $420.00 | $1,030.00 | |
| 27 | 78000100 | THPL PVT MK LTR & SYM | 75 | SQ FT | $6.60 | $6.60 | |
| 28 | 78000200 | THPL PVT MK LINE 4 | 2,889 | FOOT | $1.10 | $1.10 | |
| 29 | 78000400 | THPL PVT MK LINE 6 | 325 | FOOT | $1.65 | $1.65 | |
| 30 | 78000650 | THPL PVT MK LINE 24 | 96 | FOOT | $6.60 | $6.60 |