19-00383-00-WR
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Advanced Asphalt Company Low bidder | $1,516,752 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Advanced Asphal… |
|---|---|---|---|---|---|---|
| 1 | X2020410 | EARTH EXCAVATION SPL | 1 | CU YD | $500.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $13,750.00 | |
| 3 | 20200500 | EARTH EXC WID | 1,813 | CU YD | $26.50 | |
| 4 | 40600275 | BIT MATLS PR CT | 39 | POUND | $5.00 | |
| 5 | 40600290 | BIT MATLS TACK CT | 46,275 | POUND | $0.8000 | |
| 6 | 40600370 | LONG JOINT SEALANT | 24,990 | FOOT | $2.25 | |
| 7 | 40600982 | HMA SURF REM BUTT JT | 1,084 | SQ YD | $25.00 | |
| 8 | 40602965 | HMA BC IL-9.5FG N50 | 4,581 | TON | $85.00 | |
| 9 | 40604000 | HMA SC IL-9.5FG C N50 | 4,754 | TON | $85.00 | |
| 10 | 44000153 | HMA SURF REM 1 | 937 | SQ YD | $7.25 | |
| 11 | 48102100 | AGG WEDGE SHLD TYPE B | 1,955 | TON | $33.35 | |
| 12 | 48203021 | HMA SHOULDERS 6 | 9,771 | SQ YD | $33.50 | |
| 13 | 64200108 | SHOULDER RUM STRIP 8 | 40,672 | FOOT | $0.2500 | |
| 14 | 67100100 | MOBILIZATION | 1 | L SUM | $90,000.00 | |
| 15 | 70300100 | SHORT TERM PAVT MKING | 22,488 | FOOT | $0.0100 | |
| 16 | 78001110 | PAINT PVT MK LINE 4 | 20,003 | FOOT | $0.1300 | |
| 17 | 78001130 | PAINT PVT MK LINE 6 | 43,732 | FOOT | $0.2000 | |
| 18 | 78004200 | PREF PL PM TB INL L&S | 245 | SQ FT | $56.34 | |
| 19 | 78004230 | PREF PL PM TB INL L6 | 116 | FOOT | $34.00 | |
| 20 | 78004250 | PREF PL PM TB INL L12 | 114 | FOOT | $38.00 | |
| 21 | 78004280 | PREF PL PM TB INL L24 | 154 | FOOT | $47.40 |