16-14122-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Curnyn Construction Co. Low bidder | $429,897 | ||
| 2 | D. Construction, Inc. | $444,221 | +3.3% | |
| 3 | Brandt Construction Co. | $454,411 | +5.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Curnyn Construc… | #2 D. Construction… | #3 Brandt Construc… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2020410 | EARTH EXCAVATION SPL | 174 | CU YD | $28.00 | $80.00 | $20.00 | |
| 2 | X2501000 | SEEDING CL 2 SPL | 0.21 | ACRE | $8,000.00 | $13,200.00 | $8,400.00 | |
| 3 | X2810208 | STONE RIPRAP CL A4 SP | 484 | TON | $88.00 | $75.00 | $105.00 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $3,500.00 | $10,000.00 | $6,600.00 | |
| 5 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $5,000.00 | $10,000.00 | $5,000.00 | |
| 6 | 20300100 | CHANNEL EXCAVATION | 228 | CU YD | $18.00 | $35.00 | $20.00 | |
| 7 | 25100630 | EROSION CONTR BLANKET | 977 | SQ YD | $3.00 | $2.20 | $4.50 | |
| 8 | 28000305 | TEMP DITCH CHECKS | 80 | FOOT | $20.00 | $13.20 | $16.00 | |
| 9 | 28000400 | PERIMETER EROS BAR | 620 | FOOT | $3.00 | $7.70 | $3.00 | |
| 10 | 35101400 | AGG BASE CSE B | 202 | TON | $38.00 | $35.00 | $55.00 | |
| 11 | 40200100 | AGG SURF CSE A | 91 | TON | $38.00 | $35.00 | $65.00 | |
| 12 | 50100100 | REM EXIST STRUCT | 1 | EACH | $24,000.00 | $30,000.00 | $30,000.00 | |
| 13 | 50200100 | STRUCTURE EXCAVATION | 112 | CU YD | $28.00 | $40.00 | $25.00 | |
| 14 | 50300225 | CONC STRUCT | 27 | CU YD | $1,000.00 | $1,200.00 | $1,790.00 | |
| 15 | 50300280 | CONCRETE ENCASEMENT | 5.5 | CU YD | $1,200.00 | $1,200.00 | $2,225.00 | |
| 16 | 50400505 | P P CONC DK BM 27 DP | 1,680 | SQ FT | $100.00 | $85.55 | $90.00 | |
| 17 | 50800205 | REINF BARS, EPOXY CTD | 3,390 | POUND | $3.00 | $3.25 | $3.00 | |
| 18 | 50901050 | STEEL RAILING TY SM | 143 | FOOT | $250.00 | $256.74 | $245.00 | |
| 19 | 51200959 | FUR M S PILE 14X0.312 | 248 | FOOT | $98.00 | $144.10 | $45.00 | |
| 20 | 51202305 | DRIVING PILES | 248 | FOOT | $3.00 | $0.0100 | $1.00 | |
| 21 | 51203200 | TEST PILE MET SHELLS | 2 | EACH | $8,500.00 | $4,500.00 | $8,500.00 | |
| 22 | 51204650 | PILE SHOES | 10 | EACH | $450.00 | $375.00 | $400.00 | |
| 23 | 51500100 | NAME PLATES | 1 | EACH | $500.00 | $1,000.00 | $985.00 | |
| 24 | 58600101 | GRANULAR BACKFILL STR | 62 | CU YD | $60.00 | $60.00 | $150.00 | |
| 25 | 67100100 | MOBILIZATION | 1 | L SUM | $25,000.00 | $26,650.00 | $25,000.00 | |
| 26 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $50.00 | $55.00 | $40.00 |