(109,110,111)RS-4
- Let date
- Friday, September 20, 2024
- Contract
- 66P42 · job page
- District
- District 3
- County
- Lasalle, Livingston
- Highway
- Limits
- 16.21 miles of HMA milling and resurfacing on IL 170 from 0.2 mile south of River Road in Seneca to the intersection with IL 17.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $6,376,242 | ||
| 2 | Advanced Asphalt Company | $7,030,113 | +10.3% | |
| 3 | Kankakee Valley Construction Company, Inc. | $7,527,768 | +18.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Advanced Asphal… | #3 Kankakee Valley… |
|---|---|---|---|---|---|---|---|---|
| 1 | X4401198 | HMA SURF REM VAR DP | 10,856 | SQ YD | $3.50 | $12.50 | $6.00 | |
| 2 | X6350204 | LINEAR DELIN PANELS 4 | 74 | EACH | $55.00 | $125.00 | $50.00 | |
| 3 | X6350206 | LINEAR DELIN PANELS 6 | 6 | EACH | $60.50 | $155.00 | $55.00 | |
| 4 | Z0018900 | DRILL-GROUT DOW BARS | 180 | EACH | $20.00 | $10.00 | $37.00 | |
| 5 | Z0018911 | DRILL-GROUT #6 T-BAR | 30 | EACH | $20.00 | $10.00 | $48.00 | |
| 6 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $25.00 | $30.00 | $25.00 | |
| 7 | Z0034105 | MATL TRANSFER DEVICE | 56,713 | TON | $3.00 | $2.25 | $3.00 | |
| 8 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $4,825.00 | $5,000.00 | $6,200.00 | |
| 9 | Z0070202 | SURVEY MARKER VAULT | 1 | EACH | $1,000.00 | $625.00 | $3,050.00 | |
| 10 | Z0076600 | TRAINEES | 2,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 11 | Z0076604 | TRAINEES TPG | 2,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 12 | 20400800 | FURNISHED EXCAVATION | 11 | CU YD | $150.00 | $1,000.00 | $1,045.00 | |
| 13 | 40200800 | AGG SURF COURSE TY B | 811 | TON | $35.00 | $45.00 | $44.00 | |
| 14 | 40600290 | BIT MATLS TACK CT | 24,916 | POUND | $0.0100 | $1.80 | $3.00 | |
| 15 | 40600370 | LONG JOINT SEALANT | 80,343 | FOOT | $2.64 | $2.50 | $2.45 | |
| 16 | 40600400 | MIX CR JTS FLANGEWYS | 81 | TON | $0.0100 | $150.00 | $257.00 | |
| 17 | 40600990 | TEMPORARY RAMP | 601 | SQ YD | $0.0100 | $20.00 | $0.0100 | |
| 18 | 40603080 | HMA BC IL-19.0 N50 | 34,006 | TON | $68.50 | $74.50 | $83.00 | |
| 19 | 40604050 | HMA SC IL-9.5 C N50 | 22,707 | TON | $72.00 | $74.50 | $85.00 | |
| 20 | 40800050 | INCIDENTAL HMA SURF | 1,531 | TON | $110.00 | $125.00 | $200.00 | |
| 21 | 44000155 | HMA SURF REM 1 1/2 | 144 | SQ YD | $7.50 | $3.65 | $11.20 | |
| 22 | 44000164 | HMA SURF REM 3 3/4 | 273,798 | SQ YD | $2.00 | $3.65 | $3.40 | |
| 23 | 44201102 | CL B PATCH T2 20 | 70 | SQ YD | $400.00 | $400.00 | $480.00 | |
| 24 | 44201106 | CL B PATCH T4 20 | 43 | SQ YD | $400.00 | $400.00 | $480.00 | |
| 25 | 44201299 | DOWEL BARS 1 1/2 | 180 | EACH | $25.00 | $7.50 | $8.00 | |
| 26 | 44213000 | PATCH REINFORCEMENT | 43 | SQ YD | $75.00 | $16.00 | $15.00 | |
| 27 | 44213200 | SAW CUTS | 509 | FOOT | $5.00 | $10.00 | $5.75 | |
| 28 | 44213204 | TIE BARS 3/4 | 30 | EACH | $30.00 | $3.00 | $3.75 | |
| 29 | 48102100 | AGG WEDGE SHLD TYPE B | 6,100 | TON | $25.00 | $34.00 | $36.00 | |
| 30 | 63500105 | DELINEATORS | 106 | EACH | $68.75 | $55.00 | $62.50 | |
| 31 | 64200108 | SHOULDER RUM STRIP 8 | 55,733 | FOOT | $0.2800 | $0.3500 | $0.2900 | |
| 32 | 66700205 | PERM SURV MKRS T1 | 20 | EACH | $750.00 | $285.00 | $381.00 | |
| 33 | 67000400 | ENGR FIELD OFFICE A | 7 | CAL MO | $4,000.00 | $1,975.00 | $2,600.00 | |
| 34 | 67100100 | MOBILIZATION | 1 | L SUM | $318,449.50 | $250,000.00 | $282,000.00 | |
| 35 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $285,749.00 | $45,000.00 | $16,985.00 | |
| 36 | 70300100 | SHORT TERM PAVT MKING | 25,298 | FOOT | $0.0100 | $1.25 | $0.0100 | |
| 37 | 70300150 | SHRT TRM PAVT MK REM | 2,812 | SQ FT | $0.0100 | $2.35 | $0.0100 | |
| 38 | 78000100 | THPL PVT MK LTR & SYM | 122 | SQ FT | $19.80 | $10.65 | $18.00 | |
| 39 | 78000650 | THPL PVT MK LINE 24 | 216 | FOOT | $14.77 | $10.65 | $13.43 | |
| 40 | 78009004 | MOD URETH PM LINE 4 | 395,656 | FOOT | $0.5300 | $0.6500 | $0.4800 | |
| 41 | 78009006 | MOD URETH PM LINE 6 | 42,165 | FOOT | $0.7800 | $0.7500 | $0.7100 | |
| 42 | 78009008 | MOD URETH PM LINE 8 | 368 | FOOT | $5.18 | $2.65 | $4.71 | |
| 43 | 78009012 | MOD URETH PM LINE 12 | 192 | FOOT | $9.55 | $4.05 | $8.68 | |
| 44 | 78011000 | GRV RCSD PM LTR & SYM | 122 | SQ FT | $16.63 | $2.75 | $15.12 | |
| 45 | 78011125 | GRV RCSD PVT MRKG 25 | 216 | FOOT | $11.56 | $3.35 | $10.51 | |
| 46 | 78100100 | RAISED REFL PAVT MKR | 1,054 | EACH | $50.35 | $34.65 | $45.77 | |
| 47 | 78300200 | RAISED REF PVT MK REM | 1,054 | EACH | $8.00 | $12.00 | $0.0100 |