$104.79Avg low bid / LF
$109.94Avg of all bids
$98.26Avg engineer's estimate
55Jobs · 16,152 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 11 | 2,805 | $112.66 | $112.03 |
| 2020 | 19 | 3,734 | $102.85 | $113.59 |
| 2019 | 19 | 4,671 | $114.00 | $124.40 |
| 2018 | 6 | 4,942 | $93.11 | $89.95 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 16, 2021 | 210179 | MurrayDivision 7 | 164 LF | $126.00 | Pavers, Inc. |
| Aug 19, 2021 | 210149 | Nhpp-260n(054)pm | 104 LF | $126.38 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Aug 19, 2021 | 210232 | GarfieldDivision 4 | 830 LF | $118.75 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210142 | Nhpp-022n(225)pm | 72 LF | $123.60 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210082 | McclainDivision 3 | 152 LF | $95.00 | Silver Star Construction Company, Inc. |
| May 20, 2021 | 210142 | Nhpp-022n(225)pm | 642 LF | $111.25 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210127 | BlaineDivision 5 | 149 LF | $81.05 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210133 | EllisDivision 6 | 210 LF | $107.60 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210136 | HughesDivision 3 | 38 LF | $107.00 | C-GAWF CONSTRUCTION, INC. |
| Apr 15, 2021 | 210114 | NobleDivision 4 | 80 LF | $110.00 | T.J. CAMPBELL CONSTRUCTION COMPANY |
| Mar 18, 2021 | 210072 | CaddoDivision 7 | 260 LF | $115.00 | OVERLAND CORPORATION |
| Feb 18, 2021 | 210046 | ComancheDivision 7 | 104 LF | $110.00 | K & R BUILDERS, INC. |
| Nov 19, 2020 | 200357 | SequoyahDivision 1 | 90 LF | $113.00 | APAC-CENTRAL, INC. |
| Sep 17, 2020 | 200273 | Stp-208b(091)pm | 56 LF | $80.55 | OVERLAND CORPORATION |
| Sep 17, 2020 | 200200 | McintoshDivision 1 | 263 LF | $115.00 | KOSS CONSTRUCTION COMPANY & SUBSIDIARY |
| Sep 17, 2020 | 200292 | PottawatomieDivision 3 | 116 LF | $124.00 | Silver Star Construction Company, Inc. |
| Aug 20, 2020 | 200225 | GradyDivision 7 | 390 LF | $90.00 | SEWELL BROS., INC. |
| Aug 20, 2020 | 200010 | DeweyDivision 5 | 86 LF | $100.00 | SEWELL BROS., INC. |
| Jul 23, 2020 | 200251 | HarmonDivision 5 | 284 LF | $105.00 | Frontier Bridge, Inc. |
| May 14, 2020 | 200241 | Nhppi-4000-(095)pm | 696 LF | $100.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| May 14, 2020 | 200193 | EllisDivision 6 | 160 LF | $120.00 | J & R SAND COMPANY, INC. |
| May 14, 2020 | 200208 | PittsburgDivision 2 | 98 LF | $95.00 | DUIT CONSTRUCTION COMPANY, INC. |
| Apr 16, 2020 | 200175 | WagonerDivision 1 | 131 LF | $107.00 | APAC-CENTRAL, INC. |
| Apr 16, 2020 | 200028 | Cirb-264d(069)rb | 44 LF | $120.20 | THE CUMMINS CONSTRUCTION CO., INC. |
| Apr 16, 2020 | 200138 | BeaverDivision 6 | 44 LF | $155.00 | K & R BUILDERS, INC. |
| Mar 19, 2020 | 200120 | Pontotoc | 222 LF | $59.20 | OVERLAND CORPORATION |
| Feb 20, 2020 | 200183 | Stp-170c(127)pm | 412 LF | $90.00 | J & R SAND COMPANY, INC. |
| Feb 20, 2020 | 200089 | CimarronDivision 6 | 176 LF | $130.00 | J & R SAND COMPANY, INC. |
| Jan 16, 2020 | 190356 | KayDivision 4 | 16 LF | $145.00 | Evans & Associates Construction Co., Inc. |
| Jan 16, 2020 | 190214 | LoveDivision 7 | 42 LF | $110.00 | Silver Star Construction Company, Inc. |
| Jan 16, 2020 | 200009 | CusterDivision 5 | 408 LF | $115.00 | SEWELL BROS., INC. |
| Nov 14, 2019 | 190341 | CaddoDivision 7 | 132 LF | $115.00 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Nov 14, 2019 | 190109 | CanadianDivision 4 | 40 LF | $80.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Oct 17, 2019 | 190380 | BeckhamDivision 5 | 216 LF | $153.12 | Frontier Bridge, Inc. |
| Sep 19, 2019 | 190216 | McclainDivision 3 | 128 LF | $110.00 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Sep 19, 2019 | 190272 | AlfalfaDivision 6 | 416 LF | $142.10 | THE CUMMINS CONSTRUCTION CO., INC. |
| Aug 22, 2019 | 190257 | SequoyahDivision 1 | 122 LF | $130.00 | JOB CONSTRUCTION CO., INC. |
| Jul 25, 2019 | 190145 | BryanDivision 2 | 1,775 LF | $114.17 | DUIT CONSTRUCTION COMPANY, INC. |
| Jun 20, 2019 | 190142 | Jefferson | 126 LF | $74.20 | OVERLAND CORPORATION |
| May 16, 2019 | 190132 | Pontotoc | 60 LF | $107.35 | OVERLAND CORPORATION |
| May 16, 2019 | 180277 | BlaineDivision 5 | 72 LF | $97.70 | HASKELL LEMON CONSTRUCTION CO. |
| Apr 18, 2019 | 190169 | GrantDivision 4 | 120 LF | $150.00 | Venture Corporation dba VCO Paving |
| Mar 14, 2019 | 190140 | MurrayDivision 7 | 104 LF | $92.52 | BRIDGECO CONTRACTORS, INC. |
| Feb 14, 2019 | 190101 | Pontotoc | 178 LF | $79.40 | THE CUMMINS CONSTRUCTION CO., INC. |
| Feb 14, 2019 | 190097 | Nhpp-008n(090)fp | 72 LF | $80.00 | J & R SAND COMPANY, INC. |
| Jan 17, 2019 | 190020 | Hsipg-256n(041)pm | 320 LF | $116.00 | SHERWOOD CONSTRUCTION CO., INC. |
| Jan 17, 2019 | 190034 | CimarronDivision 6 | 100 LF | $145.00 | J & R SAND COMPANY, INC. |
| Jan 17, 2019 | 180191 | Cotton | 42 LF | $110.00 | SEWELL BROS., INC. |
| Jan 17, 2019 | 190051 | Ssp-250n(018)pm | 616 LF | $98.00 | Pavers, Inc. |
| Jan 17, 2019 | 190064 | Major, Woodward | 32 LF | $74.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Oct 18, 2018 | 180283 | DelawareDivision 8 | 122 LF | $83.00 | MANHATTAN ROAD & BRIDGE COMPANY, LLC |
| Sep 20, 2018 | 180280 | CraigDivision 8 | 3,692 LF | $93.00 | CROSSLAND HEAVY CONTRACTORS INC. |
| Jun 14, 2018 | 180127 | ClevelandDivision 3 | 258 LF | $68.50 | Silver Star Construction Company, Inc. |
| Mar 15, 2018 | 180137 | NobleDivision 4 | 176 LF | $115.20 | Evans & Associates Construction Co., Inc. |
| Mar 15, 2018 | 180151 | WashingtonDivision 8 | 70 LF | $90.00 | BECCO CONTRACTORS, INC. |
| Jan 18, 2018 | 180030 | RogersDivision 8 | 624 LF | $100.00 | BECCO CONTRACTORS, INC. |