101Let jobs
$370,743,152Total low bids
—Total estimates
—Low bids vs estimates
Nov 2024 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Nov 8, 2024 | 62W38 | Cook District 1 |
(531)BR 23 · | — | $82,838,696 | Judlau Contracting, Inc. | 4 | |
| Nov 8, 2024 | 61J87 | Lake District 1 |
11-00087-02-GS · | — | $69,424,887 | IHC Construction Companies LLC and Curran Contracting Company JV | 7 | |
| Nov 8, 2024 | 62B66 | Lake District 1 |
(125S-1)I-4 · Decommissioning of existing Pump Station 37 located in the IL 176 over US 41 bridge abutment (SN 049-0131), an | — | $15,494,185 | F. H. Paschen, S.N. Nielsen & Associates LLC | 3 | |
| Nov 8, 2024 | 97372 | St. Clair District 8 |
95-00301-03-PV · | — | $13,628,661 | DMS Contracting, Inc. | 4 | |
| Nov 8, 2024 | 64P26 | Jodaviess District 2 |
43N · | — | $13,559,978 | McCarthy Improvement Company | 2 | |
| Nov 8, 2024 | 62W30 | Cook District 1 |
(531-2-HB)BR 23 · | — | $10,802,029 | Dunnet Bay Construction Company | 4 | |
| Nov 8, 2024 | 68D84 | Peoria District 4 |
(72-3HVB)BR · | — | $10,741,237 | Stark Excavating, Inc. | 2 | |
| Nov 8, 2024 | 61K74 | Lake District 1 |
20-00108-00-PV · | — | $10,184,632 | A Lamp Concrete Contractors, Inc. | 5 | |
| Nov 8, 2024 | 62G63 | Dupage District 1 |
2018-027-RS-SW · | — | $8,631,060 | R. W. Dunteman Company | 2 | |
| Nov 8, 2024 | 89816 | Peoria District 4 |
19-00115-01-PV · | — | $7,099,475 | Gensini Excavating, Inc. | 5 | |
| Nov 8, 2024 | 85743 | Whiteside District 2 |
17-00152-00-BT · | — | $6,232,140 | Gensini Excavating, Inc. | 4 | |
| Nov 8, 2024 | 62T10 | Dupage District 1 |
FAP 0338 22 RS · | — | $5,630,000 | Plote Construction, Inc. | 3 | |
| Nov 8, 2024 | 62G18 | Cook District 1 |
86Y-RS-4 · | — | $5,291,877 | K-Five Construction Corporation | 3 | |
| Nov 8, 2024 | 91599 | Mclean District 5 |
16-00360-00-PV · | — | $4,698,912 | Stark Excavating, Inc. | 2 | |
| Nov 8, 2024 | 61K21 | Cook District 1 |
19-00070-00-BR · | — | $4,310,271 | Martam Construction Incorporated | 2 | |
| Nov 8, 2024 | 61J90 | Cook District 1 |
15-00082-00-CH · | — | $4,279,092 | A Lamp Concrete Contractors, Inc. | 3 | |
| Nov 8, 2024 | 70629 | Piatt District 5 |
74-69BR · | — | $4,199,611 | Stark Excavating, Inc. | 3 | |
| Nov 8, 2024 | 64P06 | Winnebago District 2 |
111BR · | — | $3,998,708 | Sjostrom & Sons, Inc. | 3 | |
| Nov 8, 2024 | 72A59 | Montgomery District 6 |
(68-5HB-1,2)BRR,BY,D · | — | $3,787,000 | William Charles Construction Company, LLC | 2 | |
| Nov 8, 2024 | 78906 | Williamson District 9 |
(130,1)N-3 · | — | $3,758,898 | Samron Midwest Contracting, Inc. | 2 | |
| Nov 8, 2024 | 68801 | Mercer District 4 |
(102)BR-1 · | — | $3,450,000 | Brandt Construction Co. | 3 | |
| Nov 8, 2024 | 61K54 | Cook District 1 |
17-00034-05-BT · | — | $3,447,132 | Martam Construction Incorporated | 3 | |
| Nov 8, 2024 | 97846 | Madison District 8 |
20-00109-01-BR · | — | $3,435,037 | Keller Construction, Inc. | 1 | |
| Nov 8, 2024 | 68989 | Henderson District 4 |
(14-2Q)BR · | — | $3,329,664 | County Contractors, Inc. | 3 | |
| Nov 8, 2024 | 46651 | Various District 7 |
D7 REFLECTOR REPL 25-08 · | — | $3,213,213 | ROADSAFE TRAFFIC SYSTEMS, INC. | 1 | |
| Nov 8, 2024 | 61K48 | Cook District 1 |
11-00052-00-CH · | — | $3,094,447 | D. Construction, Inc. | 4 | |
| Nov 8, 2024 | 61H32 | Will District 1 |
14-12112-01-BR · | — | $2,994,900 | D. Construction, Inc. | 3 | |
| Nov 8, 2024 | 76N47 | Clinton District 8 |
481W-1 · | — | $2,978,735 | The Kilian Corporation | 2 | |
| Nov 8, 2024 | 87868 | Kendall District 3 |
21-00053-00-BR · | — | $2,509,615 | D. Construction, Inc. | 3 | |
| Nov 8, 2024 | 61K83 | Cook District 1 |
22-00140-00-PV · | — | $2,379,003 | A Lamp Concrete Contractors, Inc. | 6 | |
| Nov 8, 2024 | 62W28 | Cook District 1 |
2024-994-I · The graffiti cleaning on I-290 between Mannheim (US 45) and Wells Street | — | $2,230,000 | ERA-Valdivia Contractors, Inc. | 2 | |
| Nov 8, 2024 | 85766 | Jo Daviess District 2 |
22-00162-00-RS · | — | $2,153,129 | Civil Constructors, Inc. d/b/a/ Helm Civil | 1 | |
| Nov 8, 2024 | 70G13 | Douglas, Vermilion District 5 |
D5 BRIDGE PAINTING 2025-1 · | — | $1,931,612 | Venus Painting Co. | 6 | |
| Nov 8, 2024 | 66L79 | Livingston District 3 |
(112BR)BR · | — | $1,865,719 | Riber Construction, Inc. | 2 | |
| Nov 8, 2024 | 78A16 | Jackson District 9 |
(12-1)TS-2 · | — | $1,745,537 | Samron Midwest Contracting, Inc. | 2 | |
| Nov 8, 2024 | 61K76 | Mchenry District 1 |
19-00508-00-BR · | — | $1,739,696 | Sjostrom & Sons, Inc. | 2 | |
| Nov 8, 2024 | 62R00 | Cook District 1 |
2021-179-SW · Hot-mix asphalt surface removal and resurfacing, pavement patching, concrete curb and gutter removal and repla | — | $1,688,085 | Alliance Contractors, Inc. | 1 | |
| Nov 8, 2024 | 61K80 | Mchenry District 1 |
18-00489-00-BR · | — | $1,503,245 | Sjostrom & Sons, Inc. | 2 | |
| Nov 8, 2024 | 62P98 | Cook District 1 |
2021-177-SW · | — | $1,498,868 | Acura Inc. | 4 | |
| Nov 8, 2024 | 61K59 | Cook District 1 |
20-00038-00-SW · | — | $1,464,176 | A Lamp Concrete Contractors, Inc. | 6 | |
| Nov 8, 2024 | 74D02 | Various District 7 |
D7 BRIDGE PAINTING 2025-2 · | — | $1,410,755 | Venus Painting Co. | 5 | |
| Nov 8, 2024 | 61K64 | Kane District 1 |
23-00356-00-RS · | — | $1,369,171 | Geneva Construction Company | 4 | |
| Nov 8, 2024 | 62P92 | Cook District 1 |
2021-171-SW · Curb ramps (ADA) improvements consists of sidewalk removal, combination concrete curb and gutter removal and r | — | $1,217,181 | Acura Inc. | 4 | |
| Nov 8, 2024 | 61K66 | Kane District 1 |
23-00366-00-RS · | — | $1,157,514 | Geneva Construction Company | 3 | |
| Nov 8, 2024 | 76T82 | Bond District 8 |
3-4BI · | — | $1,116,073 | The Kilian Corporation | 1 | |
| Nov 8, 2024 | 68J34 | Various District 4 |
D4 BRIDGE PAINTING 2025 · | — | $1,057,011 | Venus Painting Co. | 5 | |
| Nov 8, 2024 | 62W03 | Cook District 1 |
2023 DB YARD PARKING · | — | $1,055,604 | A Lamp Concrete Contractors, Inc. | 9 | |
| Nov 8, 2024 | 72648 | Logan District 6 |
(54-1HB,54-5B)BP · | — | $984,000 | Venus Painting Co. | 5 | |
| Nov 8, 2024 | 62P94 | Cook District 1 |
2021-173-SW · Sidewalk removal, combination concrete curb and gutter removal and replacement, concrete sidewalk and detectab | — | $979,267 | Acura Inc. | 3 | |
| Nov 8, 2024 | 76U22 | Monroe, St.clair District 8 |
67-(1,2,3)-PP,82-(6,7,8)-PP · | — | $959,922 | Keeley & Sons, Inc. | 2 | |
| Nov 8, 2024 | 61K75 | Dupage District 1 |
23-00077-00-RS · | — | $939,975 | K-Five Construction Corporation | 8 | |
| Nov 8, 2024 | 76T75 | Marion District 8 |
(16,16-1)RS · | — | $905,388 | Howell Paving, Inc. | 1 | |
| Nov 8, 2024 | 46654 | Various District 7 |
D7 HT PVMNT MRK RPR 25-11 · | — | $825,998 | STF, LLC d/b/a Traffic Control Company | 3 | |
| Nov 8, 2024 | 74D25 | Various District 7 |
D7 CULVERT LINING 2025-2 · | — | $794,740 | Phoenix Corporation of the Quad Cities | 3 | |
| Nov 8, 2024 | 78A77 | Pulaski District 9 |
D9 BRIDGE REPAIR 2025-2 · | — | $787,433 | Samron Midwest Contracting, Inc. | 2 | |
| Nov 8, 2024 | 61K65 | Dupage District 1 |
23-00364-00-RS · | — | $734,188 | K-Five Construction Corporation | 4 | |
| Nov 8, 2024 | 76R77 | Various District 8 |
DIST 8 BRIDGE DECK REPAIRS 2025-1 · | — | $718,550 | Keeley & Sons, Inc. | 2 | |
| Nov 8, 2024 | 62X19 | Cook District 1 |
(21BZ-1-1213)BP 24 · Bridge Painting of the structures (Foster Ave over North Branch Chicago River SN: 016-0249, Foster Ave over No | — | $700,460 | Eagle Painting & Maintenance Company, Inc. | 3 | |
| Nov 8, 2024 | 62X13 | Kane District 1 |
2024-988-I · | — | $675,550 | Areatha Construction Co., Inc. | 2 | |
| Nov 8, 2024 | 61K69 | Cook District 1 |
23-00020-00-RS · | — | $670,114 | K-Five Construction Corporation | 4 | |
| Nov 8, 2024 | 68J49 | Various District 4 |
D4 BRIDGE PAINTING 2025-1 · | — | $662,498 | Eagle Painting & Maintenance Company, Inc. | 5 | |
| Nov 8, 2024 | 72516 | Logan District 6 |
D6 PATCHING 2025-2 · | — | $633,081 | Kinney Contractors, Inc. | 2 | |
| Nov 8, 2024 | 74D24 | Various District 7 |
D7 CULVERT LINING 2025-1 · | — | $622,603 | Phoenix Corporation of the Quad Cities | 3 | |
| Nov 8, 2024 | 74D26 | Clark District 7 |
D7 CULVERT LINING 2025-3 · | — | $597,325 | Temple & Temple Excavating and Paving Inc. | 3 | |
| Nov 8, 2024 | 62R21 | Will District 1 |
FAI 80 21 DEMO · The building demolition at various locations | — | $597,064 | P. T. Ferro Construction Co. | 3 | |
| Nov 8, 2024 | 62W05 | Kane District 1 |
2023 ESS YARD PARKING · | — | $584,932 | A Lamp Concrete Contractors, Inc. | 8 | |
| Nov 8, 2024 | 78A40 | Jefferson District 9 |
(41-4,41-4-1)RS-2 · | — | $575,913 | Samron Midwest Contracting, Inc. | 2 | |
| Nov 8, 2024 | 97845 | Madison District 8 |
21-00242-00-RS · | — | $568,967 | Charles E. Mahoney Co. | 2 | |
| Nov 8, 2024 | 78A88 | Franklin District 9 |
D9 WETLAND MAINTENANCE 2024-1 · | — | $555,883 | Mayer Landscaping, Inc. | 2 | |
| Nov 8, 2024 | 61K56 | Cook District 1 |
23-00104-00-RS · | — | $554,455 | A Lamp Concrete Contractors, Inc. | 5 | |
| Nov 8, 2024 | 62X14 | Mchenry District 1 |
2024-989-ATR · Advanced tree removal, selective clearing, as well as all incidental and collateral work necessary to complete | — | $515,021 | Mosley Construction 1, LLC | 3 | |
| Nov 8, 2024 | 76T56 | St.clair District 8 |
82-(1,2,3,4)SG · | — | $513,145 | COLLINS & HERMANN, INC. | 2 | |
| Nov 8, 2024 | 76U19 | Madison District 8 |
(101.102,103,104,119)PP · | — | $449,676 | Keeley & Sons, Inc. | 2 | |
| Nov 8, 2024 | 62X23 | Various District 1 |
2024-997-SG · Installing signs at new locations and repairing existing damaged signs on a work order basis throughout Distri | — | $446,300 | ROADSAFE TRAFFIC SYSTEMS, INC. | 2 | |
| Nov 8, 2024 | 95966 | Wabash District 7 |
20-05124-00-BR · | — | $397,458 | C-Hill Civil Contractors, Inc. | 2 | |
| Nov 8, 2024 | 72745 | Morgan District 6 |
(6VBR,6VBR-1)BDR,BJR · | — | $396,391 | Freesen, a div of UCM, Inc. | 2 | |
| Nov 8, 2024 | 87869 | Kendall District 3 |
24-00053-00-RS · | — | $382,160 | D. Construction, Inc. | 3 | |
| Nov 8, 2024 | 78949 | Perry District 9 |
19CR-1 · | — | $367,180 | Samron Midwest Contracting, Inc. | 3 | |
| Nov 8, 2024 | 91630 | Edgar District 5 |
23-00075-00-SW · | — | $359,182 | McCarthy Improvement Company | 2 | |
| Nov 8, 2024 | 66P32 | Iroquois District 3 |
(22BR-1)BRR · | — | $354,306 | Iroquois Paving Corporation | 2 | |
| Nov 8, 2024 | 74D00 | Various District 7 |
D7 RA 2024-1 · | — | $350,973 | Bodine Electric of Decatur | 2 | |
| Nov 8, 2024 | 64U05 | Jodaviess District 2 |
(24)TR · | — | $349,563 | Homer Tree Service, Inc. | 1 | |
| Nov 8, 2024 | 61K58 | Cook District 1 |
18-00036-00-SW · | — | $341,626 | Triggi Construction, Inc. | 6 | |
| Nov 8, 2024 | 62X05 | Cook District 1 |
2024-984-I · The pickup, removal and satisfactory disposal of debris, deceased animal carcasses, refuse, Litter and any oth | — | $331,356 | The Final Connection, Inc. | 4 | |
| Nov 8, 2024 | 76M49 | St.clair District 8 |
28CR-1 · | — | $296,885 | Stutz Excavating, Inc. | 3 | |
| Nov 8, 2024 | 62X04 | Cook District 1 |
2024-982-I · The pickup, removal and satisfactory disposal of debris, deceased animal carcasses, refuse, Litter and any oth | — | $279,374 | The Final Connection, Inc. | 4 | |
| Nov 8, 2024 | 62X03 | Cook District 1 |
2024-982-I · The pickup, removal and satisfactory disposal of debris, deceased animal carcasses, refuse, Litter and any oth | — | $266,663 | The Final Connection, Inc. | 4 | |
| Nov 8, 2024 | 87870 | Grundy District 3 |
22-00010-00-SW · | — | $248,978 | Gallagher Asphalt Corporation | 4 | |
| Nov 8, 2024 | 62X08 | Kane District 1 |
2024-987-DM · | — | $245,431 | Veterans Vac Services LLC | 1 | |
| Nov 8, 2024 | 66P61 | Bureau District 3 |
(R-4)CLV · | — | $238,332 | D. Construction, Inc. | 3 | |
| Nov 8, 2024 | 62X06 | Cook District 1 |
2024-985-I · The pickup, removal and satisfactory disposal of debris, deceased animal carcasses, refuse, Litter and any oth | — | $200,700 | The Final Connection, Inc. | 4 | |
| Nov 8, 2024 | 87872 | Grundy District 3 |
24-00093-00-RS · | — | $199,524 | D. Construction, Inc. | 4 | |
| Nov 8, 2024 | 72649 | Pike District 6 |
(105BR-1)BP · | — | $173,018 | Civil Coatings and Construction Inc. | 6 | |
| Nov 8, 2024 | 64T37 | Rock Island District 2 |
D2 BC 2025-04 · | — | $147,250 | M & M Concrete, Inc. | 3 | |
| Nov 8, 2024 | 78A73 | Various District 9 |
D9 DECK SEAL 2024-1 · | — | $142,938 | All States Painting, Inc. | 2 | |
| Nov 8, 2024 | 66P35 | Dekalb District 3 |
(26VBR-1)SCR · | — | $137,674 | Phoenix Corporation of the Quad Cities | 3 | |
| Nov 8, 2024 | 64T36 | Carrol, Rock Island Whiteside District 2 |
D2 BC 2025-03 · | — | $114,950 | M & M Concrete, Inc. | 3 | |
| Nov 8, 2024 | 64U06 | Stephenson District 2 |
(22,107)TR · | — | $97,090 | Homer Tree Service, Inc. | 1 | |
| Nov 8, 2024 | 64T38 | Rock Island District 2 |
D2 BC 2025-05 · | — | $57,900 | M & M Concrete, Inc. | 3 | |
| Nov 8, 2024 | 76U12 | Various District 8 |
DIST 8 LITTER REMOVAL 2025-1 · | — | $44,075 | The Final Connection, Inc. | 3 |
1–100 of 101Next ›
Source: IDOT Transportation Bulletin "Unit Price Tabulation of Bids" for each letting. Totals are as read; IDOT does not publish an engineer's estimate there, so estimate columns stay blank. Bid Potato backfills the last two years. Confirm against IDOT's As Accepted tabulation.