18-00036-00-SW
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Triggi Construction, Inc. Low bidder | $341,626 | ||
| 2 | R. W. Dunteman Company | $354,197 | +3.7% | |
| 3 | Davis Concrete Construction Co. | $363,564 | +6.4% | |
| 4 | Acura Inc. | $385,210 | +12.8% | |
| 5 | Alliance Contractors, Inc. | $398,600 | +16.7% | |
| 6 | D'Land Construction, LLC | $404,683 | +18.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Triggi Construc… | #2 R. W. Dunteman … | #3 Davis Concrete … | #4 Acura Inc. | #5 Alliance Contra… | #6 D'Land Construc… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X4401198 | HMA SURF REM VAR DP | 115 | SQ YD | $50.00 | $13.64 | $25.00 | $70.00 | $20.00 | $25.00 | |
| 2 | X6640104 | FENCE REMOVAL | 26 | FOOT | $25.00 | $50.00 | $13.00 | $20.00 | $12.40 | $15.00 | |
| 3 | X7240600 | REM RE-ERECT EX SIGN | 11 | EACH | $600.00 | $250.00 | $100.00 | $1,700.00 | $250.00 | $600.00 | |
| 4 | Z0017400 | DRAIN UTIL STR ADJ | 7 | EACH | $500.00 | $685.00 | $700.00 | $1,750.00 | $685.00 | $700.00 | |
| 5 | Z0030850 | TEMP INFO SIGNING | 102 | SQ FT | $18.00 | $15.00 | $16.00 | $20.00 | $15.00 | $30.00 | |
| 6 | 20100110 | TREE REMOV 6-15 | 24 | UNIT | $75.00 | $30.00 | $30.00 | $40.00 | $75.00 | $100.00 | |
| 7 | 20101100 | TREE TRUNK PROTECTION | 10 | EACH | $100.00 | $100.00 | $100.00 | $110.00 | $100.00 | $115.00 | |
| 8 | 20101200 | TREE ROOT PRUNING | 10 | EACH | $100.00 | $45.00 | $45.00 | $55.00 | $100.00 | $115.00 | |
| 9 | 20101300 | TREE PRUN 1-10 | 10 | EACH | $100.00 | $75.00 | $75.00 | $90.00 | $100.00 | $115.00 | |
| 10 | 20200100 | EARTH EXCAVATION | 490 | CU YD | $77.25 | $21.79 | $30.00 | $60.00 | $1.00 | $70.00 | |
| 11 | 21101610 | TOPSOIL F & P 3 | 2,100 | SQ YD | $0.1000 | $5.00 | $5.00 | $6.00 | $0.1000 | $6.00 | |
| 12 | 25000312 | SEEDING CL 4A | 0.35 | ACRE | $35,000.00 | $2,398.00 | $2,400.00 | $3,000.00 | $31,460.00 | $2,500.00 | |
| 13 | 25200110 | SODDING SALT TOLERANT | 600 | SQ YD | $30.00 | $10.00 | $10.00 | $11.00 | $29.00 | $12.00 | |
| 14 | 25200200 | SUPPLE WATERING | 35 | UNIT | $0.1000 | $0.0100 | $0.0100 | $1.00 | $0.1000 | $1.00 | |
| 15 | 28000250 | TEMP EROS CONTR SEED | 35 | POUND | $0.1000 | $4.00 | $4.00 | $5.00 | $0.1000 | $5.00 | |
| 16 | 28000510 | INLET FILTERS | 20 | EACH | $175.00 | $178.00 | $25.00 | $200.00 | $225.00 | $200.00 | |
| 17 | 40800029 | BIT MATLS TACK CT | 200 | POUND | $0.1000 | $1.00 | $1.00 | $1.00 | $0.0100 | $1.00 | |
| 18 | 40800050 | INCIDENTAL HMA SURF | 20 | TON | $350.00 | $142.23 | $400.00 | $400.00 | $460.00 | $350.00 | |
| 19 | 42001300 | PROTECTIVE COAT | 1,800 | SQ YD | $0.1000 | $0.7000 | $0.2500 | $1.00 | $0.0100 | $0.0100 | |
| 20 | 42400200 | PC CONC SIDEWALK 5 | 16,000 | SQ FT | $9.50 | $10.03 | $13.40 | $9.00 | $10.95 | $10.00 | |
| 21 | 42400800 | DETECTABLE WARNINGS | 156 | SQ FT | $30.00 | $34.54 | $24.00 | $50.00 | $40.00 | $40.00 | |
| 22 | 44000500 | COMB CURB GUTTER REM | 60 | FOOT | $15.00 | $34.62 | $22.00 | $8.00 | $15.00 | $15.00 | |
| 23 | 44000600 | SIDEWALK REM | 100 | SQ FT | $2.50 | $16.61 | $6.00 | $5.00 | $2.00 | $2.50 | |
| 24 | 60406000 | FR & LIDS T1 OL | 2 | EACH | $500.00 | $565.00 | $600.00 | $600.00 | $565.00 | $600.00 | |
| 25 | 60406100 | FR & LIDS T1 CL | 1 | EACH | $500.00 | $565.00 | $600.00 | $600.00 | $565.00 | $600.00 | |
| 26 | 60600605 | CONC CURB TB | 70 | FOOT | $50.00 | $48.63 | $55.00 | $60.00 | $42.95 | $50.00 | |
| 27 | 60603800 | COMB CC&G TB6.12 | 60 | FOOT | $50.00 | $60.66 | $45.00 | $60.00 | $48.75 | $55.00 | |
| 28 | 66400105 | CH LK FENCE 4 | 1,280 | FOOT | $25.00 | $40.00 | $25.00 | $30.00 | $24.79 | $28.00 | |
| 29 | 66401300 | CH LK GATE 4X10 SINGL | 3 | EACH | $1,750.00 | $3,600.00 | $1,700.00 | $2,000.00 | $1,674.00 | $1,750.00 | |
| 30 | 66900200 | NON SPL WASTE DISPOSL | 95 | CU YD | $75.00 | $112.06 | $100.00 | $80.00 | $92.10 | $125.00 | |
| 31 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,500.00 | $1,500.00 | $1,600.00 | $2,000.00 | $1,900.00 | $1,750.00 | |
| 32 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,500.00 | $3,400.00 | $5,200.00 | $6,000.00 | $2,300.00 | $3,800.00 | |
| 33 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $500.00 | $500.00 | $500.00 | $500.00 | $2,100.00 | $600.00 | |
| 34 | 66901006 | REG SUB MON | 15 | CAL DA | $1.00 | $700.00 | $390.00 | $1,000.00 | $940.00 | $850.00 | |
| 35 | 67100100 | MOBILIZATION | 1 | L SUM | $10,000.00 | $20,224.32 | $11,000.00 | $21,150.00 | $74,244.40 | $40,000.00 | |
| 36 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $3,500.00 | $9,183.65 | $4,500.00 | $6,000.00 | $4,000.00 | $1,500.00 | |
| 37 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $5,000.00 | $1.00 | $5.00 | $6,000.00 | $1.00 | $20,000.00 | |
| 38 | 78000600 | THPL PVT MK LINE 12 | 150 | FOOT | $35.00 | $46.75 | $32.00 | $35.00 | $33.00 | $35.00 |