D7 CULVERT LINING 2025-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Phoenix Corporation of the Quad Cities Low bidder | $622,603 | ||
| 2 | Temple & Temple Excavating and Paving Inc. | $632,500 | +1.6% | |
| 3 | Samron Midwest Contracting, Inc. | $788,425 | +26.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Phoenix Corpora… | #2 Temple & Temple… | #3 Samron Midwest … |
|---|---|---|---|---|---|---|---|---|
| 1 | 54390230 | INSERT CUL LIN 36 | 845 | FOOT | $417.50 | $400.00 | $495.00 | |
| 2 | 54390250 | INSERT CUL LIN 42 | 145 | FOOT | $561.50 | $500.00 | $510.00 | |
| 3 | 54390260 | INSERT CUL LIN 48 | 195 | FOOT | $665.50 | $600.00 | $560.00 | |
| 4 | 67100100 | MOBILIZATION | 1 | L SUM | $46,500.00 | $45,000.00 | $47,000.00 | |
| 5 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $12,125.00 | $60,000.00 | $140,000.00 |