71Let jobs
$145,040,687Total low bids
—Total estimates
—Low bids vs estimates
Aug 2023 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Aug 4, 2023 | 62N36 | Cook District 1 |
2021-003-RS · | — | $26,289,947 | D. Construction, Inc. & K-Five Construction Corporation & Iroquois Paving Corporation JV | 1 | |
| Aug 4, 2023 | 68698 | Stark District 4 |
(11B)BR-1 · | — | $13,207,000 | ICC Group Inc. | 1 | |
| Aug 4, 2023 | 70860 | Vermilion District 5 |
(92-12HB-4)BR-1 · | — | $10,240,000 | White Construction LLC | 3 | |
| Aug 4, 2023 | 89804 | Tazewell District 4 |
20-00196-00-RS · | — | $9,959,061 | R. A. Cullinan and Son, a div of UCM, Inc. | 2 | |
| Aug 4, 2023 | 89849 | Tazewell District 4 |
23-00113-00-SP · | — | $6,846,974 | Gensini Excavating, Inc. | 4 | |
| Aug 4, 2023 | 64K08 | Whiteside District 2 |
15R-1 · | — | $5,087,535 | Fischer Excavating, Inc. | 6 | |
| Aug 4, 2023 | 76T09 | Madison District 8 |
(108,109,110-2)RS-3 · | — | $4,788,328 | Christ Bros. Asphalt, Inc. | 2 | |
| Aug 4, 2023 | 62P00 | Cook District 1 |
2021-063-B · Bridge superstructure replacement of the structure on 1-57 at Parnell Avenue in the City of Chicago, Cook Coun | — | $4,577,544 | Lorig Construction Company | 4 | |
| Aug 4, 2023 | 62R18 | Lake District 1 |
FA 333 21 INTERSECTION · | — | $4,281,204 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. | 3 | |
| Aug 4, 2023 | 76L29 | Marion District 8 |
(7Z-2,8Z,8Z-2)RS-2,SW-1 · | — | $4,015,807 | The Kilian Corporation | 2 | |
| Aug 4, 2023 | 62U08 | Cook District 1 |
FAP 353 22 RS · | — | $3,987,890 | Iroquois Paving Corporation | 4 | |
| Aug 4, 2023 | 76P67 | Madison, St Clair District 8 |
82-8SG-1, 60-7SG-1 · | — | $3,386,988 | Keeley & Sons, Inc. and Wissehr Electric, Inc. JV | 2 | |
| Aug 4, 2023 | 85744 | Rock Island District 2 |
19-00271-00-BT · | — | $3,136,598 | Valley Construction Co. | 3 | |
| Aug 4, 2023 | 99704 | Williamson District 9 |
21-00128-00-PV · | — | $3,131,313 | Samron Midwest Contracting, Inc. | 2 | |
| Aug 4, 2023 | 60R77 | Cook District 1 |
1112-701HB-BR · | — | $2,767,449 | Lorig Construction Company | 4 | |
| Aug 4, 2023 | 66M89 | Iroquois District 3 |
(20,21)RS-6 · HMA milling and resurfacing, culvert replacement, ditch cleaning, pavement marking, and raised reflectors | — | $2,370,974 | Iroquois Paving Corporation | 1 | |
| Aug 4, 2023 | 61H88 | Cook District 1 |
22-00176-00-RS · | — | $2,144,525 | K-Five Construction Corporation | 2 | |
| Aug 4, 2023 | 87841 | Dekalb District 3 |
23-00019-01-LS · | — | $1,654,900 | Elliott and Wood, Inc. | 4 | |
| Aug 4, 2023 | 61J40 | Dupage District 1 |
22-00084-00-RS · | — | $1,620,838 | K-Five Construction Corporation | 5 | |
| Aug 4, 2023 | 95927 | Clark District 7 |
18-00057-00-SW · | — | $1,521,510 | Feutz Contractors, Inc. | 2 | |
| Aug 4, 2023 | 62U47 | Cook, Kane District 1 |
2022 VAR TSM · | — | $1,389,836 | Home Towne Electric, Inc. | 1 | |
| Aug 4, 2023 | 62U18 | Cook District 1 |
FAI 90/94 22 BP · A full bridge painting of span 2 of the structure (016-1110) carrying 1-90/94 over 15th to 16th Streets in the | — | $1,380,000 | ERA-Valdivia Contractors, Inc. | 1 | |
| Aug 4, 2023 | 72300 | Various District 6 |
D6 CABLE/GUARDRAIL 2023-2 · | — | $1,370,056 | COLLINS & HERMANN, INC. | 1 | |
| Aug 4, 2023 | 61J64 | Lake District 1 |
22-00244-00-RS · | — | $1,253,279 | Peter Baker & Son Co. | 3 | |
| Aug 4, 2023 | 97810 | Monroe District 8 |
16-00053-00-PV · | — | $1,215,909 | DMS Contracting, Inc. | 3 | |
| Aug 4, 2023 | 78A01 | Various District 9 |
D9 GUARDRAIL REPAIR FY24-1 · | — | $1,169,530 | COLLINS & HERMANN, INC. | 1 | |
| Aug 4, 2023 | 93806 | Mason District 6 |
22-00069-00-SP · | — | $998,390 | Lovewell Fencing, Inc. | 4 | |
| Aug 4, 2023 | 62T35 | Will District 1 |
FAU 0383 22 RS · | — | $995,198 | Austin Tyler Construction, Inc. | 4 | |
| Aug 4, 2023 | 78964 | Alexander District 9 |
138D(I-10) · | — | $957,293 | Bodine Electric of Decatur | 1 | |
| Aug 4, 2023 | 97811 | Madison District 8 |
21-00033-00-BT · | — | $907,108 | Baxmeyer Construction, Inc. | 3 | |
| Aug 4, 2023 | 62R59 | Cook District 1 |
FAI 290 22 PF · | — | $891,023 | K-Five Construction Corporation | 1 | |
| Aug 4, 2023 | 62P42 | Kane District 1 |
2021-121-SW · ADA Improvements at Various locations throughout Kane and McHenry counties | — | $881,658 | Copenhaver Construction, Inc. | 4 | |
| Aug 4, 2023 | 62T39 | Cook District 1 |
FAU 1350 22 BJ · | — | $867,410 | Rausch Infrastructure, LLC | 5 | |
| Aug 4, 2023 | 62U94 | Various District 1 |
2023 VAR FENCE · The repair and installation of fence along various expressway and arterial highways in various counties throug | — | $809,009 | Fence Masters, Inc. | 2 | |
| Aug 4, 2023 | 62T01 | Mchenry District 1 |
FAP 0326 22 BJ · | — | $769,506 | Areatha Construction Co., Inc. | 4 | |
| Aug 4, 2023 | 70G83 | Mclean District 5 |
D5 CM PATCHING 2024-1 · | — | $762,847 | Kinney Contractors, Inc. | 2 | |
| Aug 4, 2023 | 61J52 | Dupage District 1 |
20-00098-00-BT · | — | $738,989 | A Lamp Concrete Contractors, Inc. | 5 | |
| Aug 4, 2023 | 62T73 | Cook District 1 |
FAP 0350 22 RS2 · | — | $722,978 | Iroquois Paving Corporation | 4 | |
| Aug 4, 2023 | 99706 | Gallatin District 9 |
19-00083-00-BR · | — | $704,636 | Dees, Inc. | 2 | |
| Aug 4, 2023 | 66N29 | Various District 3 |
D3 SFY ITS SMT WZ TECH 2024-01 · The installation, maintenance, and pickup/removal of smart traffic monitoring systems or real-time traffic con | — | $648,625 | ROADSAFE TRAFFIC SYSTEMS, INC. | 1 | |
| Aug 4, 2023 | 62U93 | Various District 1 |
2023 VAR CABLE · Repairing high tension cable median barrier systems throughout District 1 on a work order basis | — | $644,494 | Northern Contracting, Inc. | 3 | |
| Aug 4, 2023 | 78971 | Hardin District 9 |
D9 BRIDGE REPAIR 2023-2 · | — | $589,268 | E. T. Simonds Construction Company | 1 | |
| Aug 4, 2023 | 76R27 | Madison District 8 |
60-(1,2)HL-1 · | — | $577,727 | Gerstner Electric, Inc. | 2 | |
| Aug 4, 2023 | 62T93 | Cook District 1 |
FAP 0370 22 RS · Smart overlay resurfacing on Western Ave from 87th St | — | $571,193 | MAT Construction Leasing, Inc. | 4 | |
| Aug 4, 2023 | 68H72 | Peoria District 4 |
(10,11,G)PP · | — | $570,899 | R. A. Cullinan and Son, a div of UCM, Inc. | 1 | |
| Aug 4, 2023 | 76R65 | Randolph District 8 |
(108R)RS-5 · | — | $554,302 | Keeley & Sons, Inc. | 2 | |
| Aug 4, 2023 | 78944 | Franklin District 9 |
106RS-10 · | — | $544,594 | E. T. Simonds Construction Company | 2 | |
| Aug 4, 2023 | 87828 | Iroquois District 3 |
19-00156-01-RS · | — | $495,258 | Iroquois Paving Corporation | 1 | |
| Aug 4, 2023 | 66N37 | Lasalle District 3 |
(111)CLV-2 · The removal and replacement of 6 foot of the structrure slab and sidewalls, guardrail replacement, striping, p | — | $495,072 | Riber Construction, Inc. | 3 | |
| Aug 4, 2023 | 72711 | Pike District 6 |
(4BR,4VBR)BDR,BJR,I · | — | $459,690 | Freesen, a div of UCM, Inc. | 3 | |
| Aug 4, 2023 | 66N49 | Livingston District 3 |
(25,26)PP · Class B pavement patching | — | $459,272 | G. M. Sipes Construction, Inc. | 3 | |
| Aug 4, 2023 | 70G84 | Mclean District 5 |
(FR)I-2 · | — | $433,701 | Rowe Construction, a div of UCM, Inc. | 1 | |
| Aug 4, 2023 | 62T05 | Cook District 1 |
FAP 0330 22 BJ3 · | — | $412,484 | MYS, Incorporated | 7 | |
| Aug 4, 2023 | 66N51 | Grundy, Livingston District 3 |
(53-1,32-3)PP-1 · Class A pavement Patching, striping and other related work | — | $378,840 | G. M. Sipes Construction, Inc. | 5 | |
| Aug 4, 2023 | 97805 | Bond District 8 |
22-00046-00-SW · | — | $377,775 | DMS Contracting, Inc. | 3 | |
| Aug 4, 2023 | 66N55 | Kankakee District 3 |
(13,14)RS · Milling and resurfacing a 2 foot wide path along the centerline of roadway and micro-surfacing 4' wide path al | — | $368,861 | Kankakee Valley Construction Company, Inc. | 1 | |
| Aug 4, 2023 | 72714 | Morgan District 6 |
(69-6,7)PP-2 · | — | $363,767 | G. M. Sipes Construction, Inc. | 3 | |
| Aug 4, 2023 | 76R82 | Greene District 8 |
48-PP · | — | $338,723 | G. M. Sipes Construction, Inc. | 3 | |
| Aug 4, 2023 | 62P03 | Dupage District 1 |
2021-065-CR · Culvert repair of IL 83 (Kingery Hwy) over drainage ditch, 0 | — | $324,577 | D. Construction, Inc. | 5 | |
| Aug 4, 2023 | 62T81 | Lake District 1 |
FAP 0352 22 CJ · | — | $231,615 | SKC Construction, Inc. | 3 | |
| Aug 4, 2023 | 66N15 | Kankakee District 3 |
SIGNAL MAST ARM REP 2023-01 · | — | $160,756 | Outsen Electric, Incorporated | 1 | |
| Aug 4, 2023 | 78A11 | Jackson District 9 |
(12-1)BRR-1 · | — | $151,672 | Samron Midwest Contracting, Inc. | 4 | |
| Aug 4, 2023 | 66N27 | Kankakee, Iroquois District 3 |
(138,139)SFY · The installation of a flashing red beacon at each of the stop controlled approaches to the intersection of US | — | $148,037 | Outsen Electric, Incorporated | 1 | |
| Aug 4, 2023 | 76R47 | Madison District 8 |
406N-1 · | — | $143,115 | Stutz Excavating, Inc. | 2 | |
| Aug 4, 2023 | 72712 | Pike District 6 |
(75-10HB)BDR,BJR · | — | $140,703 | Freesen, a div of UCM, Inc. | 4 | |
| Aug 4, 2023 | 72N39 | Adams District 6 |
(10B-1)BRR · | — | $128,340 | County Contractors, Inc. | 4 | |
| Aug 4, 2023 | 61J42 | Cook District 1 |
22-00056-00-SW · | — | $122,184 | Meade Inc. | 2 | |
| Aug 4, 2023 | 76R98 | Various District 8 |
DIST 8 WEED SPRAYING 2023-1 · | — | $121,088 | The Daltons Inc. | 3 | |
| Aug 4, 2023 | 72713 | Pike District 6 |
75-10PP · | — | $109,346 | G. M. Sipes Construction, Inc. | 2 | |
| Aug 4, 2023 | 62T78 | Kane District 1 |
FAP 0341 22 CJ2 · | — | $98,679 | Denler, Inc. | 3 | |
| Aug 4, 2023 | 72H76 | Cass District 6 |
4DR · | — | $74,990 | CSD Environmental Services, Inc. | 2 |
1–71 of 71
Source: IDOT Transportation Bulletin "Unit Price Tabulation of Bids" for each letting. Totals are as read; IDOT does not publish an engineer's estimate there, so estimate columns stay blank. Bid Potato backfills the last two years. Confirm against IDOT's As Accepted tabulation.