22-00069-00-SP
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lovewell Fencing, Inc. Low bidder | $998,390 | ||
| 2 | Clevenger Contractors, Inc. | $1,092,959 | +9.5% | |
| 3 | Midwest Fence Corporation | $1,104,227 | +10.6% | |
| 4 | COLLINS & HERMANN, INC. | $1,142,434 | +14.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lovewell Fencin… | #2 Clevenger Contr… | #3 Midwest Fence C… | #4 COLLINS & HERMA… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | XZ127902 | RETAINING WALL SPL | 3,275 | SQ FT | $25.00 | $47.23 | $26.00 | $42.48 | |
| 2 | X2810208 | STONE RIPRAP CL A4 SP | 527 | TON | $100.00 | $108.15 | $141.00 | $106.61 | |
| 3 | X4811900 | AGGREGATE SHLDS SPL | 3,280 | TON | $40.00 | $77.25 | $78.00 | $76.15 | |
| 4 | Z0027800 | GEOTECH FABRIC | 1,456 | SQ YD | $5.00 | $5.15 | $7.00 | $5.08 | |
| 5 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 6 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 1,155 | CU YD | $30.00 | $71.05 | $135.00 | $70.06 | |
| 8 | 63000003 | SPBGR TY A 9FT POSTS | 5,962.5 | FOOT | $42.00 | $37.20 | $37.00 | $45.32 | |
| 9 | 63100167 | TR BAR TRM T1 SPL TAN | 41 | EACH | $5,500.00 | $3,610.00 | $3,800.00 | $3,898.39 | |
| 10 | 67100100 | MOBILIZATION | 1 | L SUM | $125,000.00 | $85,000.00 | $70,500.00 | $52,075.14 | |
| 11 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $79,000.00 | $73,005.00 | $65,000.00 | $117,385.24 | |
| 12 | 72501000 | TERMINAL MARKER - DA | 41 | EACH | $35.00 | $42.00 | $50.00 | $25.11 | |
| 13 | 78200005 | GRDRAIL REF TYPE A | 95 | EACH | $15.00 | $9.50 | $10.00 | $6.28 |