22-00176-00-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | K-Five Construction Corporation Low bidder | $2,144,525 | ||
| 2 | Gallagher Asphalt Corporation | $2,381,778 | +11.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K-Five Construc… | #2 Gallagher Aspha… |
|---|---|---|---|---|---|---|---|
| 1 | X1400326 | R R FL BEACON A COMP | 6 | EACH | $7,540.00 | $8,250.00 | |
| 2 | X2800001 | IMPRTD THPL CROSSWALK | 200 | SQ YD | $175.00 | $185.00 | |
| 3 | Z0004514 | HMA DRIVEWAY PAVT 4 | 215 | SQ YD | $50.00 | $73.00 | |
| 4 | Z0017400 | DRAIN UTIL STR ADJ | 250 | EACH | $850.00 | $930.00 | |
| 5 | Z0017700 | DRAIN UTIL STR RECON | 4 | EACH | $2,000.00 | $2,175.00 | |
| 6 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $14.00 | $27.00 | |
| 7 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | |
| 8 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 9 | 21101615 | TOPSOIL F & P 4 | 810 | SQ YD | $6.00 | $17.00 | |
| 10 | 25200110 | SODDING SALT TOLERANT | 810 | SQ YD | $10.00 | $17.00 | |
| 11 | 25200200 | SUPPLE WATERING | 90 | UNIT | $0.0100 | $270.00 | |
| 12 | 28000250 | TEMP EROS CONTR SEED | 95 | POUND | $5.00 | $8.50 | |
| 13 | 28000510 | INLET FILTERS | 89 | EACH | $165.00 | $270.00 | |
| 14 | 35101600 | AGG BASE CSE B 4 | 500 | SQ YD | $8.00 | $26.50 | |
| 15 | 35800100 | PREPARATION OF BASE | 271 | SQ YD | $10.00 | $4.00 | |
| 16 | 40201000 | AGGREGATE-TEMP ACCESS | 90 | TON | $80.00 | $85.00 | |
| 17 | 40600290 | BIT MATLS TACK CT | 34,485 | POUND | $0.0100 | $0.0100 | |
| 18 | 40600370 | LONG JOINT SEALANT | 21,482 | FOOT | $3.00 | $3.15 | |
| 19 | 40600982 | HMA SURF REM BUTT JT | 640 | SQ YD | $10.00 | $15.75 | |
| 20 | 40603200 | P HMA BC IL-4.75 N50 | 2,150 | TON | $125.00 | $141.00 | |
| 21 | 40604062 | HMA SC IL-9.5 D N70 | 4,295 | TON | $100.00 | $106.00 | |
| 22 | 42300300 | PCC DRIVEWAY PAVT 7 | 210 | SQ YD | $80.00 | $87.00 | |
| 23 | 42400200 | PC CONC SIDEWALK 5 | 14,600 | SQ FT | $8.00 | $8.50 | |
| 24 | 42400800 | DETECTABLE WARNINGS | 960 | SQ FT | $34.00 | $37.00 | |
| 25 | 44000157 | HMA SURF REM 2 | 51,088 | SQ YD | $2.80 | $2.95 | |
| 26 | 44000200 | DRIVE PAVEMENT REM | 425 | SQ YD | $26.00 | $36.00 | |
| 27 | 44000500 | COMB CURB GUTTER REM | 5,360 | FOOT | $7.00 | $7.50 | |
| 28 | 44000600 | SIDEWALK REM | 14,500 | SQ FT | $2.50 | $2.70 | |
| 29 | 44201325 | CL C PATCH T1 8 | 25 | SQ YD | $50.00 | $195.00 | |
| 30 | 44201329 | CL C PATCH T2 8 | 160 | SQ YD | $50.00 | $195.00 | |
| 31 | 44201333 | CL C PATCH T3 8 | 165 | SQ YD | $50.00 | $170.00 | |
| 32 | 44201335 | CL C PATCH T4 8 | 150 | SQ YD | $50.00 | $170.00 | |
| 33 | 44201690 | CL D PATCH T1 4 | 25 | SQ YD | $21.00 | $148.00 | |
| 34 | 44201692 | CL D PATCH T2 4 | 160 | SQ YD | $21.00 | $79.00 | |
| 35 | 44201694 | CL D PATCH T3 4 | 165 | SQ YD | $21.00 | $66.00 | |
| 36 | 44201696 | CL D PATCH T4 4 | 150 | SQ YD | $21.00 | $50.00 | |
| 37 | 60266600 | VALVE BOX ADJ | 18 | EACH | $300.00 | $325.00 | |
| 38 | 60404800 | FR & GRATES T11 | 4 | EACH | $600.00 | $650.00 | |
| 39 | 60603800 | COMB CC&G TB6.12 | 5,130 | FOOT | $35.00 | $38.00 | |
| 40 | 60605000 | COMB CC&G TB6.24 | 270 | FOOT | $45.00 | $49.00 | |
| 41 | 67100100 | MOBILIZATION | 1 | L SUM | $212,000.00 | $142,000.00 | |
| 42 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $100.00 | |
| 43 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $40,000.00 | $97,172.11 | |
| 44 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $25,003.43 | $100.00 | |
| 45 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1.00 | $100.00 | |
| 46 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $100.00 | |
| 47 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $100.00 | |
| 48 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $100.00 | |
| 49 | 70107025 | CHANGEABLE MESSAGE SN | 65 | CAL DA | $40.00 | $43.75 | |
| 50 | 70300100 | SHORT TERM PAVT MKING | 17,365 | FOOT | $1.00 | $0.0100 | |
| 51 | 70300150 | SHRT TRM PAVT MK REM | 5,788 | SQ FT | $2.00 | $0.0100 | |
| 52 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 1,315 | SQ FT | $1.00 | $1.35 | |
| 53 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 23,015 | FOOT | $0.3000 | $0.4500 | |
| 54 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 3,792 | FOOT | $0.3600 | $0.7000 | |
| 55 | 70300251 | TEMP PVT MK LINE 8 - PAINT | 178 | FOOT | $0.6000 | $0.9000 | |
| 56 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 3,325 | FOOT | $0.9000 | $1.35 | |
| 57 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 860 | FOOT | $1.00 | $2.70 | |
| 58 | 72000100 | SIGN PANEL T1 | 66 | SQ FT | $28.00 | $27.00 | |
| 59 | 72400310 | REMOV SIGN PANEL T1 | 9 | SQ FT | $30.00 | $21.75 | |
| 60 | 72400500 | RELOC SIN PAN ASSY TA | 1 | EACH | $250.00 | $325.00 | |
| 61 | 72800100 | TELES STL SIN SUPPORT | 93 | FOOT | $14.00 | $16.45 | |
| 62 | 73100100 | BASE TEL STL SIN SUPP | 6 | EACH | $225.00 | $215.00 | |
| 63 | 78000100 | THPL PVT MK LTR & SYM | 1,315 | SQ FT | $4.35 | $5.00 | |
| 64 | 78000200 | THPL PVT MK LINE 4 | 23,015 | FOOT | $0.7300 | $0.7500 | |
| 65 | 78000400 | THPL PVT MK LINE 6 | 3,792 | FOOT | $1.10 | $1.30 | |
| 66 | 78000500 | THPL PVT MK LINE 8 | 178 | FOOT | $1.45 | $1.65 | |
| 67 | 78000600 | THPL PVT MK LINE 12 | 3,325 | FOOT | $2.20 | $2.45 | |
| 68 | 78000650 | THPL PVT MK LINE 24 | 860 | FOOT | $4.35 | $5.00 | |
| 69 | 78001130 | PAINT PVT MK LINE 6 | 6,500 | FOOT | $1.25 | $1.85 | |
| 70 | 78300200 | RAISED REF PVT MK REM | 263 | EACH | $18.00 | $0.0100 | |
| 71 | 88600600 | DET LOOP REPL | 325 | FOOT | $18.00 | $19.75 |