2021-065-CR
- Let date
- Friday, August 4, 2023
- Contract
- 62P03 · job page
- District
- District 1
- County
- Dupage
- Highway
- Limits
- (900-Ft) The proposed improvement consists of culvert repair of IL 83 (Kingery Hwy) over drainage ditch, 0.6 miles south of 91st Street in the Village of Burr Ridge in DuPage County.
- Classification
- Culvert repair of IL 83 (Kingery Hwy) over drainage ditch, 0
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $324,577 | ||
| 2 | Herlihy Mid-Continent Company | $348,777 | +7.5% | |
| 3 | Lorig Construction Company | $386,288 | +19.0% | |
| 4 | Alliance Contractors, Inc. | $445,378 | +37.2% | |
| 5 | Areatha Construction Co., Inc. | $509,057 | +56.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Herlihy Mid-Con… | #3 Lorig Construct… | #4 Alliance Contra… | #5 Areatha Constru… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0900075 | COFFERDAM TYP 1 IS WW | 1 | EACH | $5,000.00 | $7,654.00 | $100.00 | $1,470.00 | $34,701.80 | |
| 2 | X5060702 | CLN & PT EXP RE-BAR | 1 | L SUM | $5,000.00 | $5,710.00 | $250.00 | $1,000.00 | $6,000.00 | |
| 3 | X6700407 | ENGR FLD OFF A D1 | 12 | CAL MO | $5,000.00 | $4,432.00 | $1,600.00 | $500.00 | $2,500.00 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $5,000.00 | $3,350.00 | $94,000.00 | $53,350.00 | $3,350.00 | |
| 5 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $6,640.00 | $16,000.00 | $10,000.00 | $4,500.00 | $3,430.00 | |
| 6 | Z0016002 | DECK SLAB REP (FD-T2) | 1 | SQ YD | $2,500.00 | $2,325.00 | $3,500.00 | $6,000.00 | $10,523.00 | |
| 7 | Z0030850 | TEMP INFO SIGNING | 26 | SQ FT | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 | |
| 8 | 20101100 | TREE TRUNK PROTECTION | 1 | EACH | $275.00 | $500.00 | $250.00 | $500.00 | $500.00 | |
| 9 | 20700220 | POROUS GRAN EMBANK | 191 | CU YD | $65.00 | $62.00 | $50.00 | $50.00 | $89.00 | |
| 10 | 21101625 | TOPSOIL F & P 6 | 69 | SQ YD | $20.63 | $18.75 | $12.00 | $18.75 | $35.00 | |
| 11 | 25000312 | SEEDING CL 4A | 0.25 | ACRE | $3,438.16 | $3,125.60 | $4,500.00 | $3,125.60 | $4,800.00 | |
| 12 | 25000314 | SEEDING CL 4B | 0.25 | ACRE | $6,102.36 | $5,547.60 | $4,800.00 | $5,547.60 | $6,000.00 | |
| 13 | 25000400 | NITROGEN FERT NUTR | 45 | POUND | $2.44 | $2.22 | $6.00 | $2.22 | $3.00 | |
| 14 | 25000500 | PHOSPHORUS FERT NUTR | 45 | POUND | $2.44 | $2.22 | $6.00 | $2.22 | $3.00 | |
| 15 | 25100630 | EROSION CONTR BLANKET | 393 | SQ YD | $3.48 | $3.16 | $4.00 | $3.16 | $4.00 | |
| 16 | 28000250 | TEMP EROS CONTR SEED | 8 | POUND | $18.70 | $17.00 | $10.00 | $17.00 | $50.00 | |
| 17 | 28000305 | TEMP DITCH CHECKS | 28 | FOOT | $12.29 | $11.17 | $20.00 | $11.17 | $30.00 | |
| 18 | 28000400 | PERIMETER EROS BAR | 333 | FOOT | $3.55 | $3.23 | $7.00 | $3.23 | $5.00 | |
| 19 | 28100107 | STONE RIPRAP CL A4 | 50 | SQ YD | $100.00 | $120.00 | $225.00 | $200.00 | $144.40 | |
| 20 | 28200200 | FILTER FABRIC | 50 | SQ YD | $8.00 | $4.00 | $6.00 | $1.00 | $21.90 | |
| 21 | 50102400 | CONC REM | 9 | CU YD | $800.00 | $180.00 | $1,200.00 | $1,000.00 | $2,223.65 | |
| 22 | 50200100 | STRUCTURE EXCAVATION | 204 | CU YD | $40.00 | $36.00 | $50.00 | $10.00 | $63.90 | |
| 23 | 50500505 | STUD SHEAR CONNECTORS | 64 | EACH | $0.0100 | $35.00 | $33.00 | $50.00 | $65.00 | |
| 24 | 50800205 | REINF BARS, EPOXY CTD | 2,053 | POUND | $4.00 | $3.85 | $4.00 | $3.00 | $8.20 | |
| 25 | 51500100 | NAME PLATES | 1 | EACH | $750.00 | $533.00 | $800.00 | $750.00 | $844.85 | |
| 26 | 52200020 | TEMP SOIL RETEN SYSTM | 154 | SQ FT | $80.00 | $50.00 | $1.00 | $91.00 | $231.25 | |
| 27 | 52200100 | FUR SOLDIER PILES HP | 132 | FOOT | $215.00 | $100.00 | $90.00 | $100.00 | $417.00 | |
| 28 | 52200200 | DRILL SET SLD PI SOIL | 415 | CU FT | $0.0100 | $60.00 | $75.00 | $130.00 | $35.75 | |
| 29 | 52200250 | UNTREATED TIMBER LAG | 352 | SQ FT | $21.00 | $20.00 | $30.00 | $10.00 | $10.50 | |
| 30 | 54002020 | EXPAN BOLTS 3/4 | 14 | EACH | $100.00 | $60.00 | $90.00 | $50.00 | $32.80 | |
| 31 | 54003000 | CONC BOX CUL | 15 | CU YD | $1,600.00 | $4,700.00 | $3,800.00 | $4,500.00 | $5,868.85 | |
| 32 | 59100100 | GEOCOMPOSITE WALL DR | 32 | SQ YD | $50.00 | $51.00 | $42.00 | $10.00 | $100.75 | |
| 33 | 63000001 | SPBGR TY A 6FT POSTS | 128 | FOOT | $36.30 | $33.00 | $35.00 | $33.00 | $33.00 | |
| 34 | 63100045 | TRAF BAR TERM T2 | 1 | EACH | $2,090.00 | $1,900.00 | $2,000.00 | $1,900.00 | $1,900.00 | |
| 35 | 63100167 | TR BAR TRM T1 SPL TAN | 1 | EACH | $3,630.00 | $3,300.00 | $3,300.00 | $3,300.00 | $3,300.00 | |
| 36 | 66900200 | NON SPL WASTE DISPOSL | 300 | CU YD | $100.00 | $58.10 | $70.00 | $45.00 | $123.45 | |
| 37 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,815.00 | $1,500.00 | $2,100.00 | $1,500.00 | $1,500.00 | |
| 38 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,475.00 | $5,400.00 | $3,100.00 | $2,600.00 | $4,400.00 | |
| 39 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,475.00 | $500.00 | $1,200.00 | $1,500.00 | $500.00 | |
| 40 | 66901006 | REG SUB MON | 30 | CAL DA | $990.00 | $550.00 | $425.00 | $500.00 | $600.00 | |
| 41 | 67100100 | MOBILIZATION | 1 | L SUM | $18,000.00 | $20,904.37 | $20,000.00 | $105,078.00 | $30,600.00 | |
| 42 | 70107025 | CHANGEABLE MESSAGE SN | 30 | CAL DA | $100.00 | $35.00 | $50.00 | $35.00 | $35.00 | |
| 43 | 70400100 | TEMP CONC BARRIER | 325 | FOOT | $35.00 | $39.30 | $25.00 | $55.00 | $69.00 | |
| 44 | 70600250 | IMP ATTN TEMP NRD TL3 | 1 | EACH | $6,000.00 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 |