$24,050.00Avg low bid / L SUM
$20,275.00Avg of all bids
—Avg engineer's estimate
2Jobs · 2 L SUM
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2025 | 1 | 1 | $28,100.00 | $28,100.00 |
| 2024 | 1 | 1 | $20,000.00 | $17,666.67 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Mar 7, 2025 | 76R99 | St. ClairDistrict 8 | 1 L SUM | $28,100.00 | The Kilian Corporation and Christ Brothers Asphalt |
| Dec 13, 2024 | 64N05 | HenryDistrict 2 | 1 L SUM | $20,000.00 | Civil Constructors d/b/a Helm Civil and Phoenix Corporation of the Quad Cities |