16-00053-00-PV
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | DMS Contracting, Inc. Low bidder | $1,215,909 | ||
| 2 | Baxmeyer Construction, Inc. | $1,310,138 | +7.7% | |
| 3 | Hank's Excavating & Landscaping, Inc. | $1,360,593 | +11.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 DMS Contracting… | #2 Baxmeyer Constr… | #3 Hank's Excavati… |
|---|---|---|---|---|---|---|---|---|
| 1 | X4401198 | HMA SURF REM VAR DP | 4,074 | SQ YD | $7.00 | $7.30 | $7.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $17,200.00 | $61,660.00 | $26,000.00 | |
| 3 | X8030106 | LOC UNDERGR UTILITIES | 150 | FOOT | $0.0100 | $111.00 | $112.00 | |
| 4 | Z0034105 | MATL TRANSFER DEVICE | 1,333 | TON | $10.20 | $10.65 | $10.00 | |
| 5 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 6 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 1,410 | CU YD | $57.00 | $63.70 | $73.00 | |
| 8 | 20800150 | TRENCH BACKFILL | 607 | CU YD | $39.00 | $24.65 | $40.00 | |
| 9 | 25000100 | SEEDING CL 1 | 0.9 | ACRE | $5,800.00 | $1,845.00 | $5,000.00 | |
| 10 | 25000400 | NITROGEN FERT NUTR | 81 | POUND | $7.40 | $5.80 | $1.70 | |
| 11 | 25000500 | PHOSPHORUS FERT NUTR | 81 | POUND | $7.40 | $5.80 | $1.70 | |
| 12 | 25000600 | POTASSIUM FERT NUTR | 81 | POUND | $7.40 | $5.80 | $1.70 | |
| 13 | 25100115 | MULCH METHOD 2 | 0.9 | ACRE | $5,800.00 | $4,655.00 | $4,500.00 | |
| 14 | 28000250 | TEMP EROS CONTR SEED | 90 | POUND | $7.00 | $11.50 | $13.50 | |
| 15 | 28000400 | PERIMETER EROS BAR | 1,768 | FOOT | $0.3000 | $9.00 | $3.00 | |
| 16 | 28000500 | INLET & PIPE PROTECT | 23 | EACH | $291.00 | $305.00 | $290.00 | |
| 17 | 28001100 | TEMP EROS CONTR BLANK | 731 | SQ YD | $1.90 | $7.50 | $2.00 | |
| 18 | 31100910 | SUB GRAN MAT A 12 | 1,775 | SQ YD | $12.40 | $17.35 | $17.00 | |
| 19 | 31101191 | SUB GRAN MAT B 3 | 698 | SQ YD | $5.30 | $13.75 | $36.00 | |
| 20 | 31101200 | SUB GRAN MAT B 4 | 2,221 | SQ YD | $20.20 | $13.25 | $16.00 | |
| 21 | 35100300 | AGG BASE CSE A 4 | 240 | SQ YD | $18.00 | $15.00 | $25.00 | |
| 22 | 35101600 | AGG BASE CSE B 4 | 421 | SQ YD | $20.27 | $21.25 | $35.00 | |
| 23 | 35102000 | AGG BASE CSE B 8 | 116 | SQ YD | $26.50 | $25.70 | $65.00 | |
| 24 | 35400100 | PCC BASE CSE W 6 | 1,397 | SQ YD | $45.00 | $52.00 | $70.00 | |
| 25 | 40200500 | AGG SURF CSE A 6 | 14 | SQ YD | $92.00 | $65.25 | $130.00 | |
| 26 | 40201000 | AGGREGATE-TEMP ACCESS | 200 | TON | $30.00 | $31.50 | $36.00 | |
| 27 | 40600275 | BIT MATLS PR CT | 5,496 | POUND | $2.00 | $2.00 | $1.90 | |
| 28 | 40600290 | BIT MATLS TACK CT | 1,355 | POUND | $3.85 | $4.00 | $3.85 | |
| 29 | 40600990 | TEMPORARY RAMP | 131 | SQ YD | $0.0100 | $0.0100 | $0.0100 | |
| 30 | 40603080 | HMA BC IL-19.0 N50 | 506 | TON | $144.60 | $151.30 | $144.00 | |
| 31 | 40604050 | HMA SC IL-9.5 C N50 | 827 | TON | $144.60 | $151.30 | $144.00 | |
| 32 | 40800050 | INCIDENTAL HMA SURF | 14 | TON | $258.00 | $270.00 | $255.00 | |
| 33 | 42000200 | PCC PVT 7 | 240 | SQ YD | $117.70 | $120.00 | $145.00 | |
| 34 | 42300200 | PCC DRIVEWAY PAVT 6 | 421 | SQ YD | $98.50 | $104.00 | $135.00 | |
| 35 | 42400100 | PC CONC SIDEWALK 4 | 7,027 | SQ FT | $8.25 | $9.00 | $9.50 | |
| 36 | 42400800 | DETECTABLE WARNINGS | 98 | SQ FT | $65.70 | $37.00 | $56.70 | |
| 37 | 44000100 | PAVEMENT REM | 1,178 | SQ YD | $5.65 | $17.00 | $8.60 | |
| 38 | 44000200 | DRIVE PAVEMENT REM | 507 | SQ YD | $16.25 | $23.00 | $18.00 | |
| 39 | 44000500 | COMB CURB GUTTER REM | 1,406 | FOOT | $7.60 | $18.25 | $10.00 | |
| 40 | 44000600 | SIDEWALK REM | 3,925 | SQ FT | $1.30 | $1.00 | $2.00 | |
| 41 | 44200120 | PAVT PATCH T2 10 | 124 | SQ YD | $133.25 | $333.00 | $175.00 | |
| 42 | 50105220 | PIPE CULVERT REMOV | 333 | FOOT | $9.90 | $10.40 | $15.00 | |
| 43 | 550A2320 | SS RG CL A 1 12 | 309 | FOOT | $72.65 | $62.00 | $60.00 | |
| 44 | 550A2330 | SS RG CL A 1 15 | 1,031 | FOOT | $79.40 | $52.00 | $65.00 | |
| 45 | 550A2340 | SS RG CL A 1 18 | 703 | FOOT | $68.70 | $60.00 | $73.00 | |
| 46 | 60221200 | MAN TA 5 DIA T3F&G | 1 | EACH | $6,800.00 | $5,000.00 | $6,275.00 | |
| 47 | 60234200 | INLETS TA T1F OL | 2 | EACH | $2,155.00 | $2,200.00 | $2,400.00 | |
| 48 | 60235700 | INLETS TA T3F&G | 8 | EACH | $2,350.00 | $2,400.00 | $2,400.00 | |
| 49 | 60236200 | INLETS TA T8G | 1 | EACH | $2,100.00 | $2,000.00 | $2,400.00 | |
| 50 | 60240220 | INLETS TB T3F&G | 12 | EACH | $2,700.00 | $2,700.00 | $2,760.00 | |
| 51 | 60255500 | MAN ADJUST | 2 | EACH | $1,320.00 | $1,000.00 | $1,225.00 | |
| 52 | 60500060 | REMOV INLETS | 2 | EACH | $412.00 | $370.00 | $850.00 | |
| 53 | 60605000 | COMB CC&G TB6.24 | 3,470 | FOOT | $45.00 | $41.00 | $50.00 | |
| 54 | 67100100 | MOBILIZATION | 1 | L SUM | $62,300.00 | $63,677.06 | $50,000.00 | |
| 55 | 70300100 | SHORT TERM PAVT MKING | 207 | FOOT | $2.15 | $2.25 | $2.10 | |
| 56 | 70300150 | SHRT TRM PAVT MK REM | 69 | SQ FT | $6.30 | $12.00 | $10.00 | |
| 57 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 4,558 | FOOT | $0.9500 | $0.4000 | $0.3500 | |
| 58 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 269 | FOOT | $2.85 | $9.50 | $9.00 | |
| 59 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 50 | FOOT | $5.70 | $17.00 | $16.00 | |
| 60 | 78000200 | THPL PVT MK LINE 4 | 4,558 | FOOT | $3.70 | $1.60 | $1.50 | |
| 61 | 78000600 | THPL PVT MK LINE 12 | 79 | FOOT | $11.10 | $15.50 | $14.70 | |
| 62 | 78000650 | THPL PVT MK LINE 24 | 14 | FOOT | $22.25 | $47.50 | $45.00 | |
| 63 | 78001150 | PAINT PVT MK LINE 12 | 190 | FOOT | $23.30 | $14.70 | $14.00 | |
| 64 | 78001180 | PAINT PVT MK LINE 24 | 36 | FOOT | $45.55 | $22.50 | $21.00 |