21-00033-00-BT
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Baxmeyer Construction, Inc. Low bidder | $907,108 | ||
| 2 | Keller Construction, Inc. | $1,111,978 | +22.6% | |
| 3 | Stutz Excavating, Inc. | $1,146,039 | +26.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Baxmeyer Constr… | #2 Keller Construc… | #3 Stutz Excavatin… |
|---|---|---|---|---|---|---|---|---|
| 1 | X1400326 | R R FL BEACON A COMP | 2 | EACH | $8,560.00 | $10,500.00 | $11,000.00 | |
| 2 | X4406020 | PART DEP REM T1 2 | 8 | SQ YD | $106.00 | $105.00 | $212.00 | |
| 3 | X5427602 | REMOV EX FLAR END SEC | 3 | EACH | $205.00 | $520.60 | $240.00 | |
| 4 | X6024240 | INLETS SPL | 1 | EACH | $3,130.00 | $3,606.00 | $2,525.00 | |
| 5 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $8,500.00 | $14,769.00 | $6,200.00 | |
| 6 | X8140115 | HANDHOLE TO BE ADJUST | 1 | EACH | $8,650.00 | $6,090.00 | $6,380.00 | |
| 7 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 8 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 9 | 20100110 | TREE REMOV 6-15 | 244 | UNIT | $83.00 | $128.80 | $81.00 | |
| 10 | 20100210 | TREE REMOV OVER 15 | 376 | UNIT | $86.00 | $72.80 | $73.40 | |
| 11 | 20200100 | EARTH EXCAVATION | 550 | CU YD | $89.00 | $31.75 | $135.00 | |
| 12 | 20400800 | FURNISHED EXCAVATION | 3,160 | CU YD | $14.75 | $34.90 | $37.00 | |
| 13 | 20800150 | TRENCH BACKFILL | 205 | CU YD | $30.00 | $36.80 | $38.15 | |
| 14 | 21101615 | TOPSOIL F & P 4 | 8,484 | SQ YD | $4.00 | $12.08 | $12.65 | |
| 15 | 25000115 | SEEDING CL 1B | 2 | ACRE | $3,100.00 | $3,108.00 | $3,250.00 | |
| 16 | 25000400 | NITROGEN FERT NUTR | 181 | POUND | $5.00 | $5.00 | $5.20 | |
| 17 | 25000500 | PHOSPHORUS FERT NUTR | 181 | POUND | $5.00 | $5.00 | $5.20 | |
| 18 | 25000600 | POTASSIUM FERT NUTR | 181 | POUND | $5.00 | $5.00 | $5.20 | |
| 19 | 25100115 | MULCH METHOD 2 | 1.9 | ACRE | $4,450.00 | $4,410.00 | $4,600.00 | |
| 20 | 25100630 | EROSION CONTR BLANKET | 534 | SQ YD | $6.35 | $6.30 | $6.60 | |
| 21 | 28000250 | TEMP EROS CONTR SEED | 386 | POUND | $6.25 | $5.36 | $5.00 | |
| 22 | 28000305 | TEMP DITCH CHECKS | 72 | FOOT | $21.00 | $50.93 | $53.35 | |
| 23 | 28000400 | PERIMETER EROS BAR | 528 | FOOT | $8.75 | $8.00 | $8.35 | |
| 24 | 28000500 | INLET & PIPE PROTECT | 29 | EACH | $200.00 | $182.35 | $75.00 | |
| 25 | 35101800 | AGG BASE CSE B 6 | 3,811 | SQ YD | $11.25 | $15.45 | $16.00 | |
| 26 | 40600275 | BIT MATLS PR CT | 6,999 | POUND | $1.00 | $1.03 | $1.15 | |
| 27 | 40600290 | BIT MATLS TACK CT | 620 | POUND | $5.00 | $5.08 | $1.85 | |
| 28 | 40604000 | HMA SC IL-9.5FG C N50 | 300 | TON | $177.50 | $176.21 | $181.40 | |
| 29 | 40604002 | HMA SC IL-9.5FG C N70 | 307 | TON | $177.50 | $176.21 | $181.65 | |
| 30 | 42400100 | PC CONC SIDEWALK 4 | 1,640 | SQ FT | $15.00 | $14.12 | $14.80 | |
| 31 | 42400800 | DETECTABLE WARNINGS | 180 | SQ FT | $68.00 | $67.46 | $70.00 | |
| 32 | 44000100 | PAVEMENT REM | 24 | SQ YD | $44.00 | $59.16 | $30.40 | |
| 33 | 44000157 | HMA SURF REM 2 | 823 | SQ YD | $20.50 | $20.35 | $15.40 | |
| 34 | 44000500 | COMB CURB GUTTER REM | 396 | FOOT | $30.00 | $22.51 | $44.20 | |
| 35 | 44000600 | SIDEWALK REM | 393 | SQ FT | $3.00 | $6.90 | $8.55 | |
| 36 | 50105220 | PIPE CULVERT REMOV | 137 | FOOT | $8.00 | $18.65 | $14.40 | |
| 37 | 54213657 | PRC FLAR END SEC 12 | 3 | EACH | $1,030.00 | $1,612.00 | $575.00 | |
| 38 | 54213669 | PRC FLAR END SEC 24 | 1 | EACH | $1,480.00 | $1,870.00 | $870.00 | |
| 39 | 54248510 | CONCRETE COLLAR | 0.2 | CU YD | $1,950.00 | $17,890.00 | $3,160.00 | |
| 40 | 550A0050 | STORM SEW CL A 1 12 | 868 | FOOT | $48.30 | $53.25 | $65.55 | |
| 41 | 550A0070 | STORM SEW CL A 1 15 | 70 | FOOT | $61.00 | $77.00 | $85.75 | |
| 42 | 550A0090 | STORM SEW CL A 1 18 | 499 | FOOT | $62.50 | $68.65 | $76.40 | |
| 43 | 550A0120 | STORM SEW CL A 1 24 | 961 | FOOT | $71.60 | $79.50 | $111.25 | |
| 44 | 55100500 | STORM SEWER REM 12 | 64 | FOOT | $21.30 | $33.35 | $25.70 | |
| 45 | 55100700 | STORM SEWER REM 15 | 293 | FOOT | $15.50 | $13.85 | $34.60 | |
| 46 | 60218400 | MAN TA 4 DIA T1F CL | 8 | EACH | $3,050.00 | $3,646.00 | $3,000.00 | |
| 47 | 60218500 | MAN TA 4 DIA T3F&G | 4 | EACH | $3,264.00 | $3,646.00 | $3,000.00 | |
| 48 | 60219000 | MAN TA 4 DIA T8G | 2 | EACH | $2,850.00 | $3,646.00 | $3,000.00 | |
| 49 | 60236200 | INLETS TA T8G | 3 | EACH | $2,250.00 | $2,810.00 | $1,475.00 | |
| 50 | 60236800 | INLETS TA T11F&G | 5 | EACH | $1,887.00 | $2,781.00 | $1,475.00 | |
| 51 | 60237470 | INLETS TA T24F&G | 1 | EACH | $1,675.00 | $2,846.00 | $1,475.00 | |
| 52 | 60240220 | INLETS TB T3F&G | 1 | EACH | $2,430.00 | $3,318.00 | $2,365.00 | |
| 53 | 60240310 | INLETS TB T11F&G | 4 | EACH | $2,444.00 | $3,318.00 | $2,365.00 | |
| 54 | 60260100 | INLETS ADJUST | 5 | EACH | $523.00 | $728.00 | $305.00 | |
| 55 | 60500060 | REMOV INLETS | 4 | EACH | $375.00 | $520.00 | $195.00 | |
| 56 | 60603800 | COMB CC&G TB6.12 | 1,377 | FOOT | $37.00 | $37.50 | $42.00 | |
| 57 | 60605000 | COMB CC&G TB6.24 | 534 | FOOT | $88.00 | $56.15 | $93.00 | |
| 58 | 63200310 | GUARDRAIL REMOV | 176 | FOOT | $9.00 | $20.65 | $20.00 | |
| 59 | 67100100 | MOBILIZATION | 1 | L SUM | $41,553.42 | $84,000.00 | $15,870.00 | |
| 60 | 72000100 | SIGN PANEL T1 | 93 | SQ FT | $32.00 | $42.50 | $33.50 | |
| 61 | 72800100 | TELES STL SIN SUPPORT | 224 | FOOT | $18.00 | $45.00 | $19.00 | |
| 62 | 78001110 | PAINT PVT MK LINE 4 | 604 | FOOT | $3.00 | $1.05 | $3.00 | |
| 63 | 78001180 | PAINT PVT MK LINE 24 | 401 | FOOT | $13.00 | $2.10 | $13.40 | |
| 64 | 78300202 | PAVMT MRKG REM WTR BL | 54 | SQ FT | $21.00 | $25.00 | $120.00 | |
| 65 | 87301215 | ELCBL C SIGNAL 14 2C | 336 | FOOT | $6.00 | $8.40 | $8.80 | |
| 66 | 87301225 | ELCBL C SIGNAL 14 3C | 350 | FOOT | $8.00 | $10.50 | $11.00 | |
| 67 | 88102717 | PED SH LED 1F BM CDT | 2 | EACH | $2,040.00 | $2,625.00 | $2,750.00 | |
| 68 | 88800100 | PED PUSH-BUTTON | 2 | EACH | $2,250.00 | $1,050.00 | $1,100.00 | |
| 69 | 89502200 | MOD EX CONTR | 1 | EACH | $3,335.00 | $2,625.00 | $2,750.00 |