$2,106.75Avg low bid / EACH
$2,416.05Avg of all bids
—Avg engineer's estimate
37Jobs · 598 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 20 | 300 | $2,112.82 | $2,281.39 |
| 2025 | 17 | 298 | $2,100.64 | $2,569.39 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 18, 2026 | 97892 | St. ClairDistrict 8 | 4 EACH | $3,500.00 | Plocher Construction Company, Inc. |
| Sep 18, 2026 | 80D33 | CookDistrict 1 | 2 EACH | $1,600.00 | K-Five Construction Corporation |
| Jul 31, 2026 | 62T84 | CookDistrict 1 | 2 EACH | $2,500.00 | D. Construction, Inc. |
| Jul 31, 2026 | 61K19 | CookDistrict 1 | 1 EACH | $4,785.00 | R. W. Dunteman Company |
| Jul 31, 2026 | 61M13 | KaneDistrict 1 | 35 EACH | $1,780.55 | Dunnet Bay Construction Company |
| Jun 12, 2026 | 62M71 | Kane, KendallDistrict 1 | 46 EACH | $2,000.00 | D. Construction, Inc. |
| Jun 12, 2026 | 62U72 | MchenryDistrict 1 | 39 EACH | $1,807.09 | Martam Construction Incorporated |
| Jun 12, 2026 | 97827 | St. ClairDistrict 8 | 2 EACH | $2,300.00 | Hank's Excavating & Landscaping, Inc. |
| Apr 24, 2026 | 87899 | KendallDistrict 3 | 23 EACH | $1,900.00 | Austin Tyler Construction, Inc. |
| Apr 24, 2026 | 61M15 | CookDistrict 1 | 1 EACH | $3,100.00 | Dunnet Bay Construction Company |
| Apr 24, 2026 | 80B76 | WillDistrict 1 | 3 EACH | $2,440.00 | D. Construction, Inc. |
| Apr 24, 2026 | 80C85 | MchenryDistrict 1 | 113 EACH | $2,100.00 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. |
| Feb 27, 2026 | 68F91 | Fulton, McdonoughDistrict 4 | 2 EACH | $3,872.00 | Gunther Construction, a div of UCM, Inc. |
| Feb 27, 2026 | 97872 | St. ClairDistrict 8 | 7 EACH | $2,500.00 | DMS Contracting, Inc. |
| Feb 27, 2026 | 97882 | MadisonDistrict 8 | 5 EACH | $3,700.00 | Stutz Excavating, Inc. |
| Jan 16, 2026 | 61J01 | DupageDistrict 1 | 2 EACH | $2,010.00 | R. W. Dunteman Company |
| Jan 16, 2026 | 61L42 | LakeDistrict 1 | 8 EACH | $2,675.00 | D'Land Construction, LLC |
| Jan 16, 2026 | 61M01 | WillDistrict 1 | 1 EACH | $1,900.00 | Austin Tyler Construction, Inc. |
| Jan 16, 2026 | 62W47 | CookDistrict 1 | 2 EACH | $3,000.00 | D. Construction, Inc. |
| Jan 16, 2026 | 97881 | MadisonDistrict 8 | 2 EACH | $4,490.00 | Stutz Excavating, Inc. |
| Nov 7, 2025 | 62R63 | CookDistrict 1 | 8 EACH | $3,600.00 | Dunnet Bay Construction Company |
| Sep 19, 2025 | 61L28 | KaneDistrict 1 | 34 EACH | $1,450.24 | Martam Construction Incorporated |
| Sep 19, 2025 | 70F21 | McleanDistrict 5 | 1 EACH | $3,166.85 | Rowe Construction, a div of UCM, Inc. |
| Sep 19, 2025 | 87846 | KendallDistrict 3 | 36 EACH | $2,000.00 | D. Construction, Inc. |
| Sep 19, 2025 | 97869 | MadisonDistrict 8 | 28 EACH | $4,670.00 | Stutz Excavating, Inc. |
| Sep 19, 2025 | 97874 | MadisonDistrict 8 | 1 EACH | $2,900.00 | RCS Construction, Inc. |
| Aug 1, 2025 | 62N97 | CookDistrict 1 | 14 EACH | $2,450.00 | Everlast Blacktop Inc. |
| Aug 1, 2025 | 61L58 | KaneDistrict 1 | 2 EACH | $2,000.00 | Plote Construction, Inc. |
| Jun 13, 2025 | 97848 | St. ClairDistrict 8 | 7 EACH | $1,760.00 | Stutz Excavating, Inc. |
| Apr 25, 2025 | 97862 | MadisonDistrict 8 | 4 EACH | $4,215.00 | Keller Construction, Inc. |
| Apr 25, 2025 | 61G79 | DupageDistrict 1 | 20 EACH | $1,900.00 | OHLA Central, Inc. |
| Mar 7, 2025 | 72321 | SangamonDistrict 6 | 1 EACH | $4,400.00 | Illinois Valley Paving, a div of UCM, Inc. |
| Mar 7, 2025 | 62R73 | CookDistrict 1 | 1 EACH | $2,800.00 | Martam Construction Incorporated |
| Mar 7, 2025 | 61J84 | KaneDistrict 1 | 74 EACH | $1,660.00 | R. W. Dunteman Company |
| Jan 17, 2025 | 93773 | SangamonDistrict 6 | 2 EACH | $1,942.50 | Freesen, a div of UCM, Inc. |
| Jan 17, 2025 | 87805 | KankakeeDistrict 3 | 64 EACH | $1,525.00 | Kankakee Valley Construction Company, Inc. |
| Jan 17, 2025 | 61J25 | WillDistrict 1 | 1 EACH | $2,050.00 | P. T. Ferro Construction Co. |