26Let jobs
$68,325,112Total low bids
$63,471,647Total estimates
+7.6%Low bids vs estimates
Jul 2014 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Jul 24, 2014 | 140237STPY-127B(135) | Stpy-127b(136) |
GRANT SHOULDER IMPROVEMENT, RESURFACE (ASPHALT ), AND BRIDGE SH-11: FROM 6.43 MILES EAST OF THE ALFALFA COUNTY LINE. PROJECT LENGTH = 6.978 MILES · | $10,956,002 | $9,950,141 | THE CUMMINS CONSTRUCTION CO., INC. | -9.2% | 3 |
| Jul 24, 2014 | 140246CIRB-155D(644)RB | Oklahoma Division 4 |
GRADE, DRAIN, SURFACE , AND BRIDGE COUNTY ROAD (NS-328/HARRAH RD): BEGIN AT THE JUNCTION OF SE 29TH STREET AND SH -270, EXTEND SOUTH. PROJECT LENGTH = 1.294 MILES · | $4,879,654 | $5,665,349 | Allen Contracting, Inc. | +16.1% | 3 |
| Jul 24, 2014 | 140116STPY-068C(231)SS | Sequoyah Division 1 |
BRIDGE AND APPROACHES US -64: OVER BIG SALLISAW CREEK , 3.1 MILES WEST OF US -59 IN SALLISAW . PROJECT LENGTH = 1.320 MILES · | $5,744,591 | $5,579,176 | GLOVER & ASSOCIATES, INC. | -2.9% | 3 |
| Jul 24, 2014 | 140251SBR-266N(025)SB | Sbr-266n(026)sb |
29777(04) SBR-266N(027)SB ROGERS BRIDGE REHABILITATION SH -266/SH-167: SH-266 OVER SH-66. SH-167 OVER CO RD/BNSF RR AND OVER BIRD CR O'FLOW, 1.3 MI AND 2.7 MI N OF I-44. · | $5,080,426 | $5,463,999 | BECCO CONTRACTORS, INC. | +7.6% | 2 |
| Jul 24, 2014 | 140172CIRB-136D(188)RB | Kay Division 4 |
GRADE, DRAIN, AND SURFACE COUNTY ROAD (EW-18/HUBBARD RD): BEGIN AT US -77 IN PONCA CITY, EXTEND WEST. PROJECT LENGTH = 1.943 MILES · | $5,308,866 | $5,411,667 | Evans & Associates Construction Co., Inc. | +1.9% | 1 |
| Jul 24, 2014 | 140238SSP-160B(132)SS | Payne Division 4 |
WIDEN, RESURFACE , AND BRIDGE SH-33: OVER AN UNNAMED CREEK , 3.2 MILES WEST OF THE SH-108 JCT. PROJECT LENGTH = 1.647 MILES · | $4,375,845 | $4,981,308 | Allen Contracting, Inc. | +13.8% | 3 |
| Jul 24, 2014 | 140248SSP-160B(129)SS | Payne Division 4 |
BRIDGE AND APPROACHES SH -18: OVER SALT CREEK , 0.3 MILES SOUTH OF THE PAWNEE COUNTY LINE . PROJECT LENGTH = 0.728 MILES · | $3,662,425 | $4,127,873 | OBC, INC. | +12.7% | 1 |
| Jul 24, 2014 | 140240STPY-240C(021) | Leflore |
BRIDGE REHABILITATION US -271: OVER JACKSON CREEK AND ROCK CREEK , 2.5 AND 3.5 MILES NORTH OF THE PUSHMATAHA COUNTY LINE . · | $2,944,397 | $3,439,314 | OBC, INC. | +16.8% | 3 |
| Jul 24, 2014 | 140168SSP-226N(011)SS | Grady Division 7 |
PAVEMENT REHABILITATION (P.C. CONCRETE) US-81: BEGIN AT EAST SH -19, EXTEND NORTH . PROJECT LENGTH = 3.704 MILES · | $3,429,055 | $3,323,805 | INTERSTATE IMPROVEMENT, INC. | -3.1% | 6 |
| Jul 24, 2014 | 140244SSP-149C(103)SS | Mayes Division 8 |
BRIDGE REHABILITATION SH -69A: OVER PRYOR CREEK , 4.2 MILES EAST OF US -69. PROJECT LENGTH = 0.239 MILES · | $2,475,451 | $2,874,918 | BECCO CONTRACTORS, INC. | +16.1% | 2 |
| Jul 24, 2014 | 140235SSP-217C(009)SS | Ssp-217c(010)ss |
COTTON BRIDGE REHABILITATION US -70: OVER CACHE CREEK O'FLOW 12.6 AND 12.0 MILES EAST OF THE H.E. BAILEY TURNPIKE . · | $2,251,822 | $2,618,906 | K & R BUILDERS, INC. | +16.3% | 3 |
| Jul 24, 2014 | 140247SSP-158C(125)SS | Ssp-158c(131)ss |
OTTAWA BRIDGE AND APPROACHES SH -10C/SH-137: SH-137 OVER AN UNNAMED CR , 2.7 MI S OF SH-10. SH-10C OVER LOST CR , 3.3 MI E OF SH-10. PROJECT LENGTH = 0.265 MILES · | $2,197,987 | $2,342,933 | GLOVER & ASSOCIATES, INC. | +6.6% | 3 |
| Jul 24, 2014 | 140239STP-135C(129)CI | Johnston Division 3 |
RESURFACE (ASPHALT ) COUNTY ROAD (NS-363/WILEY ROAD ): BEGIN AT SH -7, EXTEND SOUTH. PROJECT LENGTH = 6.007 MILES · | — | $2,220,342 | THE CUMMINS CONSTRUCTION CO., INC. | 2 | |
| Jul 24, 2014 | 140249STP-263C(018)CI | Pottawatomie Division 3 |
RESURFACE (ASPHALT ) AND BRIDGE REPAIR COUNTY ROAD (EW-109/MOCCASIN TRAIL ): BEGIN 3.5 MILES NORTH AND 4.0 MILES EAST OF THE I -40/SH-18 JCT, EXTEND EAST. PROJECT LENGTH = 2.950 MILES · | $1,868,887 | $2,165,175 | HASKELL LEMON CONSTRUCTION CO. | +15.9% | 1 |
| Jul 24, 2014 | 140234SSR-114B(273)SR | Cleveland Division 3 |
RESURFACE (ASPHALT ) SH-9: BEGIN 6.0 MILE EAST OF 72ND AVENUE EAST , EXTEND EAST. PROJECT LENGTH = 6.490 MILES · | $1,592,781 | $1,326,177 | MARKWELL PAVING COMPANY, INC. | -16.7% | 4 |
| Jul 24, 2014 | 140232SSP-210B(014)SS | Carter Division 7 |
BRIDGE REHABILITATION US-177: OVER KEMP CREEK, 1.5 MILES SOUTH OF SH-53. · | $1,061,647 | $1,132,450 | B & B CONSTRUCTION SERVICE J.T., INC. | +6.7% | 3 |
| Jul 24, 2014 | 140230STP-106C(126)CI | Blaine Division 5 |
GRADE, DRAIN, AND SURFACE COUNTY ROAD (NS-250): FROM SH-51, EXTEND SOUTH. PROJECT LENGTH = 2.991 MILES · | $1,122,485 | $1,057,933 | CORNELL CONSTRUCTION COMPANY, INC. | -5.8% | 2 |
| Jul 24, 2014 | 140233SBR-211C(011)SB | Cherokee Division 1 |
BRIDGE REHABILITATION SH-10: OVER BLACK FOX CREEK, 19.4 MILES NORTH OF US-62. · | $879,319 | $829,330 | M.J. HUGHES CONSTRUCTION, INC. | -5.7% | 3 |
| Jul 24, 2014 | 140243STP-247D(011)CI | Major Division 6 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-228): OVER CUDDY CREEK , 5.1 MILES NORTH OF US-412, AND 3.5 MILES WEST OF US -281. PROJECT LENGTH = 0.197 MILES · | $746,253 | $732,866 | Bridges, Inc. DBA Scudder Bridge Co. | -1.8% | 8 |
| Jul 24, 2014 | 140245HSIPG-251F(022)TR | Adair, Cherokee, Muskogee, Okmulgee, Sequoyah, Wagoner |
SAFETY IMPROVEMENT (SIGNING AND PAVEMENT MARKING ) US HIGHWAYS /STATE HIGHWAYS : VARIOUS LOCATIONS IN DIVISION I. · | $725,901 | $714,325 | Advanced Work zone Services, LLC | -1.6% | 4 |
| Jul 24, 2014 | 140236STP-124D(142)CI | Garfield Division 4 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-54/REED RD): OVER OTTER CREEK, 5.0 MILES SOUTH AND 2.4 MILES WEST OF THE SH -74/SH-164 JUNCTION. PROJECT LENGTH = 0.255 MILES · | $614,210 | $640,706 | B & B BRIDGE COMPANY, LLC | +4.3% | 8 |
| Jul 24, 2014 | 140252HSIPG-267F(030)TR | Cleveland, Garvin, Hughes, Lincoln, Mcclain, Okfuskee, Potta |
SAFETY IMPROVEMENT (SIGNING AND PAVEMENT MARKING ) I-35/US HIGHWAYS /STATE HIGHWAYS : VARIOUS LOCATIONS IN DIVISION III. · | $471,095 | $528,783 | ACTION SAFETY SUPPLY CO., LLC | +12.2% | 3 |
| Jul 24, 2014 | 140229STP-203D(020)CI | Atoka Division 2 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-395.5): OVER DOUBLE SPRINGS CREEK, 0.5 MILE EAST, AND 0.9 MILE SOUTH OF LANE, OK. PROJECT LENGTH = 0.134 MILES · | $383,166 | $404,607 | HUB Construction, Inc. | +5.6% | 4 |
| Jul 24, 2014 | 140193HSIPG-212F(007)TR | Atoka, Bryan, Choctaw, Leflore, Marshall, Mccurtain, Pittsbu |
INTERSECTION MODIFICATION US HIGHWAYS /STATE HIGHWAYS /CITY STREETS : AT MULTIPLE LOCATIONS IN DIVISION II. · | $345,241 | $384,373 | Advanced Work zone Services, LLC | +11.3% | 4 |
| Jul 24, 2014 | 140250STP-264D(010)CI | Pushmataha Division 2 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-186): OVER DAVENPORT CREEK 3.3 MILES WEST OF THE INDIAN NATION TURNPIKE. PROJECT LENGTH = 0.181 MILES · | $354,142 | $355,907 | HUB Construction, Inc. | +0.5% | 6 |
| Jul 24, 2014 | 140241NHPPY-245N(025)RW | Choctaw, Mccurtain |
RIGHT-OF-WAY CLEARANCE US-70: FROM THE CHOCTAW COUNTY LINE , EXTEND EAST. PRE-QUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTABLE . · | — | $52,750 | J.E. DIRT WURX, LLC | 5 |
1–26 of 26
Source: ODOT bid tabulations for each letting on Contracts and Proposals, read from ODOT's published bid tab reports, including the engineer's estimate. Bid Potato loads new lettings as ODOT posts them and backfills the last two years. Confirm against ODOT's official tabulations.