BRIDGE AND APPROACHES COUNTY ROAD (NS-228): OVER CUDDY CREEK , 5.1 MILES NORTH OF US-412, AND 3.5 MILES WEST OF US -281. PROJECT LENGTH = 0.197 MILES
Project number
STP-247D(011)CI

Bidders 8

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$746,253
1 Bridges, Inc. DBA Scudder Bridge Co. Low bidder $732,866 -1.8%
2 SEWELL BROS., INC. $764,321 +2.4% +4.3%
3 B & B BRIDGE COMPANY, LLC $772,988 +3.6% +5.5%
4 K & R BUILDERS, INC. $782,688 +4.9% +6.8%
5 BRIDGECO CONTRACTORS, INC. $794,469 +6.5% +8.4%
6 MERIDIAN CONTRACTING, INC. $869,708 +16.5% +18.7%
7 RRY SERVICES LLC $879,980 +17.9% +20.1%
8 OBC, INC. $924,493 +23.9% +26.1%

Bid tab: unit prices 41 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Bridges, Inc. D…#2 SEWELL BROS., I…#3 B & B BRIDGE CO…#4 K & R BUILDERS,…#5 BRIDGECO CONTRA…#6 MERIDIAN CONTRA…#7 RRY SERVICES LLC#8 OBC, INC.
1202(H) 0185 EARTHWORK1LSUM $50,000.00 $34,000.00 $45,000.00 $33,785.33 $43,014.00 $45,000.00 $100,000.00 $65,000.00 $66,976.00
2221(C) 2801 TEMPORARY SILT FENCE720LF $1.50 $1.50 $1.60 $1.44 $2.60 $1.65 $2.00 $1.65 $1.61
3221(F) 0100 TEMPORARY SILT DIKE364LF $5.00 $8.00 $8.40 $7.66 $4.10 $8.50 $8.50 $8.50 $8.58
4230(A) 2806 SOLID SLAB SODDING8,600SY $2.00 $1.68 $2.00 $1.68 $2.05 $1.80 $2.50 $1.80 $1.88
5233(A) 2817 VEGETATIVE MULCHING1.7AC $675.00 $588.00 $588.00 $588.00 $300.00 $650.00 $250.00 $600.00 $658.56
6402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E568TON $40.00 $38.00 $39.00 $40.00 $45.09 $44.00 $55.00 $44.00 $49.66
7509(D) 0325 CLASS C CONCRETE10CY $250.00 $400.00 $400.00 $500.00 $350.00 $450.00 $250.00 $200.00 $498.18
8601(B) 0536 TYPE I-A PLAIN RIPRAP178TON $47.00 $52.00 $50.00 $55.00 $60.92 $58.00 $60.00 $65.00 $67.58
9601(C) 0538 TYPE I-A FILTER BLANKET60TON $42.00 $45.00 $42.00 $45.00 $51.34 $44.00 $60.00 $53.00 $60.03
10613(B) 0690 24" CORR. GALV. STEEL PIPE54LF $36.00 $34.00 $35.00 $30.00 $33.00 $28.00 $35.00 $35.00 $44.37
11613(B) 0694 48" CORR. GALV. STEEL PIPE102LF $65.00 $71.00 $62.00 $60.00 $135.00 $50.00 $150.00 $85.00 $83.21
12613(M) 7187 TYPE B4 CULVERT END TREATMENT2EA $1,350.00 $1,200.00 $1,200.00 $1,500.00 $1,600.00 $1,500.00 $1,000.00 $1,400.00 $1,830.13
13613(M) 7190 TYPE E4 CULVERT END TREATMENT2EA $2,200.00 $1,200.00 $1,200.00 $2,000.00 $3,100.00 $1,900.00 $1,200.00 $2,500.00 $2,706.63
14501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON180CY $14.00 $18.00 $15.00 $32.00 $11.00 $20.00 $12.00 $25.00 $16.80
15501(F) 6352 GRANULAR BACKFILL66CY $88.00 $80.00 $85.00 $90.00 $77.17 $89.00 $80.00 $85.00 $140.23
16503(A) 1311 PRESTRESSED CONCRETE BEAMS (TYPE II)537LF $190.00 $260.00 $186.00 $200.00 $192.00 $203.41 $190.00 $205.00 $204.76
17504(C) 6250 SEALED EXPANSION JOINT58.34LF $270.00 $325.00 $250.00 $275.00 $295.00 $272.00 $200.00 $260.00 $356.70
18504(D) 6239 CONCRETE RAIL (TR3)416LF $86.00 $70.00 $75.00 $80.00 $86.00 $80.00 $65.00 $85.00 $99.19
19506(A) 1322 STRUCTURAL STEEL1,060LB $2.35 $5.00 $2.50 $2.80 $2.60 $3.85 $2.00 $2.75 $2.92
20507(A) 6172 WEATHERING STEEL FIXED BEARING ASSEMBLY9EA $900.00 $525.00 $1,000.00 $800.00 $745.00 $1,500.00 $400.00 $825.00 $1,327.19
21507(B) 6176 WEATHERING STEEL EXPANSION BEARING ASSEMBLY9EA $900.00 $525.00 $1,000.00 $800.00 $745.00 $1,500.00 $400.00 $825.00 $1,327.19
22509(A) 1326 CLASS AA CONCRETE138.7CY $600.00 $575.00 $720.00 $680.00 $702.50 $700.00 $850.00 $775.00 $707.46
23509(B) 1328 CLASS A CONCRETE91.2CY $625.00 $775.00 $700.00 $680.00 $722.50 $700.00 $500.00 $800.00 $789.98
24511(A) 1332 REINFORCING STEEL49,568LB $1.00 $1.00 $1.00 $1.00 $0.9500 $1.17 $1.00 $1.10 $1.06
25514(A) 6010 PILES, FURNISHED (HP 10X42)118LF $25.00 $50.00 $30.00 $30.00 $37.10 $47.70 $35.00 $38.00 $47.70
26514(A) 6011 PILES, FURNISHED (HP 12X53)265LF $30.00 $65.00 $35.00 $42.00 $44.10 $56.75 $45.00 $49.00 $57.88
27514(B) 6292 PILES, DRIVEN (HP 10X42)118LF $12.00 $10.00 $15.00 $26.00 $15.90 $15.00 $75.00 $11.00 $16.80
28514(B) 6294 PILES, DRIVEN (HP 12X53)265LF $14.00 $10.00 $15.00 $25.00 $18.90 $15.00 $75.00 $12.00 $16.80
29514(L) 6220 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00
30516(A) 6093 DRILLED SHAFTS 42" DIAMETER154LF $600.00 $500.00 $800.00 $675.00 $670.00 $572.00 $575.00 $850.00 $800.57
31601(B) 1353 TYPE I-A PLAIN RIPRAP431TON $47.00 $52.00 $49.00 $55.00 $57.82 $58.00 $55.00 $65.00 $67.58
32601(C) 1355 TYPE I-A FILTER BLANKET144TON $42.00 $45.00 $42.00 $45.00 $49.34 $50.00 $60.00 $52.00 $60.03
33613(H) 6204 6" PERFORATED PIPE UNDERDRAIN ROUND52LF $40.00 $20.00 $25.00 $40.00 $40.00 $18.00 $25.00 $15.00 $31.17
34613(I) 6207 6" NON-PERF.PIPE UNDERDRAIN RND.30LF $35.00 $20.00 $25.00 $40.00 $40.00 $18.00 $20.00 $15.00 $33.51
35619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $15,000.00 $10,000.00 $18,500.00 $8,435.25 $18,500.00 $12,000.00 $41,603.00 $29,000.00 $39,200.00
36623(F) 5686 GUARDRAIL ANCHOR UNIT (TYPE D-BF)4EA $1,200.00 $2,300.00 $2,300.00 $2,000.00 $2,300.00 $2,200.00 $2,400.00 $2,000.00 $2,525.32
37623(F) 6029 GUARDRAIL ANCHOR UNIT (TYPE A)4EA $1,450.00 $1,500.00 $1,800.00 $1,250.00 $1,500.00 $1,375.00 $1,600.00 $1,250.00 $1,999.20
38880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $3,500.00 $2,800.00 $2,650.00 $2,400.00 $4,200.00 $3,000.00 $3,000.00 $3,000.00 $3,132.00
39642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $7,500.00 $6,650.00 $7,500.00 $8,000.00 $7,800.00 $10,000.00 $7,500.00 $6,650.00 $7,448.00
40220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $3,000.00 $4,000.00 $2,000.00 $4,000.00 $3,900.00 $4,000.00 $2,000.00 $3,000.00 $2,800.00
41641 1399 MOBILIZATION1LSUM $75,000.00 $43,500.00 $40,000.00 $75,275.00 $49,000.00 $63,000.00 $65,000.00 $66,000.00 $71,000.01