| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$5,000.00 |
$20,000.00 |
$8,200.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 3,495 | CY |
$8.50 |
$4.60 |
$13.20 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 500 | CY |
$15.00 |
$5.25 |
$9.50 |
| 4 | 221(C) 2801 |
TEMPORARY SILT FENCE | 250 | LF |
$2.10 |
$3.94 |
$4.40 |
| 5 | 221(F) 0100 |
TEMPORARY SILT DIKE | 200 | LF |
$10.00 |
$7.44 |
$8.35 |
| 6 | 230(A) 2806 |
SOLID SLAB SODDING | 10,000 | SY |
$2.10 |
$1.37 |
$1.55 |
| 7 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 1,778 | CY |
$50.00 |
$57.30 |
$62.40 |
| 8 | 325 5271 |
SEPARATOR FABRIC | 6,797 | SY |
$2.25 |
$0.8000 |
$0.7000 |
| 9 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 5,715 | TON |
$28.00 |
$29.25 |
$23.10 |
| 10 | 407(B) 0250 |
TACK COAT | 12,364 | GAL |
$3.15 |
$3.70 |
$3.00 |
| 11 | 408 5774 |
PRIME COAT | 1,404 | GAL |
$5.15 |
$4.65 |
$2.00 |
| 12 | 409(A) 4242 |
FABRIC REINFORCEMENT | 81,334 | SY |
$0.9500 |
$1.01 |
$0.7500 |
| 13 | 409(B) 4268 |
BITUMINOUS BINDER | 16,267 | GAL |
$3.00 |
$4.87 |
$3.00 |
| 14 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 783.3 | TON |
$95.00 |
$139.25 |
$145.05 |
| 15 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 18,379.6 | TON |
$85.00 |
$73.10 |
$80.65 |
| 16 | 412 5267 |
COLD MILLING PAVEMENT | 1,677 | SY |
$6.00 |
$6.50 |
$8.00 |
| 17 | 509(D) 0325 |
CLASS C CONCRETE | 10 | CY |
$285.00 |
$700.00 |
$210.00 |
| 18 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 4,498 | SY |
$6.35 |
$3.85 |
$18.60 |
| 19 | 619(B) 4780 |
REMOVAL OF GUARDRAIL | 1,325 | LF |
$4.50 |
$2.25 |
$2.95 |
| 20 | 619(C) 0924 |
SAWING PAVEMENT | 3,253 | LF |
$4.00 |
$1.80 |
$1.10 |
| 21 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 900 | LF |
$16.50 |
$16.95 |
$25.55 |
| 22 | 623(D) 5203 |
BEAM GUARDRAIL THRIE-BEAM DOUBLE | 225 | LF |
$50.00 |
$121.50 |
$55.90 |
| 23 | 623(E) 7113 |
BEAM GUARDRAIL TRANSITION SECTION | 8 | EA |
$1,000.00 |
$225.00 |
$445.00 |
| 24 | 623(F) 8300 |
GUARDRAIL TRAIL END TURNDOWN (31") | 8 | EA |
$850.00 |
$725.00 |
$875.00 |
| 25 | 629(A) 4958 |
MAILBOX INSTALLATION-SINGLE | 8 | EA |
$100.00 |
$100.00 |
$105.00 |
| 26 | 629(C) 4960 |
MAILBOX | 8 | EA |
$50.00 |
$65.00 |
$70.00 |
| 27 | 629(D) 4961 |
REMOVAL OF MAILBOX INSTALLATION | 8 | EA |
$30.00 |
$25.00 |
$25.00 |
| 28 | 629(E) 5048 |
REMOVE AND RESET MAILBOX | 3 | EA |
$150.00 |
$150.00 |
$160.00 |
| 29 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 68.4 | SF |
$20.00 |
$15.00 |
$15.85 |
| 30 | 851(C) 8327 |
2 1/4" SQUARE TUBE POST | 156 | LF |
$9.00 |
$9.00 |
$9.50 |
| 31 | 855(A) 8812 |
TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 88,389 | LF |
$0.6000 |
$0.4200 |
$0.4500 |
| 32 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$40,000.00 |
$4,450.00 |
$65,000.00 |
| 33 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$20,000.00 |
$1,000.00 |
$5,000.00 |
| 34 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$3,000.00 |
$5,000.00 |
$2,000.00 |
| 35 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$115,000.00 |
$78,500.00 |
$77,500.00 |