| 1 | 201(A) 0102 |
CLEARING AND GRUBBING | 1 | LSUM |
$10,000.00 |
$10,000.00 |
$20,000.00 |
$12,000.00 |
$17,000.00 |
| 2 | 202(H) 0185 |
EARTHWORK | 1 | LSUM |
$20,000.00 |
$32,000.00 |
$48,000.00 |
$50,000.00 |
$44,000.00 |
| 3 | 210 0121 |
OBLITERATING ABANDONED ROAD | 452 | LF |
$5.00 |
$4.00 |
$7.00 |
$10.00 |
$10.00 |
| 4 | 221(C) 2801 |
TEMPORARY SILT FENCE | 700 | LF |
$2.50 |
$3.00 |
$2.00 |
$2.00 |
$2.20 |
| 5 | 221(F) 0100 |
TEMPORARY SILT DIKE | 100 | LF |
$8.50 |
$8.00 |
$12.00 |
$8.00 |
$12.00 |
| 6 | 230(A) 2806 |
SOLID SLAB SODDING | 5,000 | SY |
$2.35 |
$3.00 |
$2.95 |
$2.95 |
$3.40 |
| 7 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 760 | TON |
$25.00 |
$30.00 |
$31.00 |
$35.00 |
$27.00 |
| 8 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 75 | LF |
$18.75 |
$20.00 |
$17.00 |
$16.50 |
$19.80 |
| 9 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 4 | EA |
$1,500.00 |
$1,900.00 |
$1,500.00 |
$2,200.00 |
$1,770.00 |
| 10 | 623(G) 8571 |
GUARDRAIL END TREATMENT (GET) | 4 | EA |
$2,200.00 |
$2,300.00 |
$2,200.00 |
$1,475.00 |
$2,640.00 |
| 11 | 853 9030 |
DELINEATORS(TYPE 1, CODE 3) | 6 | EA |
$20.00 |
$35.00 |
$20.00 |
$30.00 |
$25.00 |
| 12 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 168 | CY |
$13.00 |
$15.00 |
$25.00 |
$30.00 |
$11.00 |
| 13 | 501(G) 6309 |
CLSM BACKFILL | 64 | CY |
$165.00 |
$150.00 |
$150.00 |
$250.00 |
$190.00 |
| 14 | 504(B) 1305 |
SAW-CUT GROOVING | 152 | SY |
$10.00 |
$15.00 |
$13.50 |
$13.50 |
$16.20 |
| 15 | 504(D) 6239 |
CONCRETE RAIL (TR3) | 178.4 | LF |
$75.00 |
$90.00 |
$75.00 |
$185.00 |
$96.00 |
| 16 | 506(A) 1322 |
STRUCTURAL STEEL | 7,838 | LB |
$2.63 |
$5.50 |
$2.00 |
$2.00 |
$7.15 |
| 17 | 507(A) 6172 |
WEATHERING STEEL FIXED BEARING ASSEMBLY | 8 | EA |
$800.00 |
$1,200.00 |
$1,400.00 |
$2,000.00 |
$1,126.55 |
| 18 | 509(A) 1326 |
CLASS AA CONCRETE | 46.3 | CY |
$600.00 |
$850.00 |
$700.00 |
$1,200.00 |
$872.50 |
| 19 | 509(B) 1328 |
CLASS A CONCRETE | 62.8 | CY |
$640.00 |
$800.00 |
$700.00 |
$1,000.00 |
$712.50 |
| 20 | 511(A) 1332 |
REINFORCING STEEL | 19,920 | LB |
$0.9600 |
$1.00 |
$1.00 |
$1.00 |
$0.9500 |
| 21 | 514(A) 6010 |
PILES, FURNISHED (HP 10X42) | 113.83 | LF |
$40.00 |
$35.00 |
$40.00 |
$29.00 |
$46.20 |
| 22 | 514(A) 6011 |
PILES, FURNISHED (HP 12X53) | 253.56 | LF |
$44.00 |
$45.00 |
$50.00 |
$37.00 |
$46.20 |
| 23 | 514(B) 6292 |
PILES, DRIVEN (HP 10X42) | 113.83 | LF |
$13.75 |
$15.00 |
$11.00 |
$14.00 |
$19.80 |
| 24 | 514(B) 6294 |
PILES, DRIVEN (HP 12X53) | 253.56 | LF |
$15.00 |
$15.00 |
$11.00 |
$16.00 |
$19.80 |
| 25 | 514(L) 6220 |
PILE SPLICE, H-PILE (NON-BIDDABLE) | 1 | EA |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
$400.00 |
| 26 | 535 6225 |
HAUL AND ERECT STEEL BEAMS | 1 | LSUM |
$40,000.00 |
$50,000.00 |
$52,500.00 |
$35,000.00 |
$64,000.00 |
| 27 | 601(B) 1353 |
TYPE I-A PLAIN RIPRAP | 200 | TON |
$40.00 |
$50.00 |
$55.00 |
$35.00 |
$50.04 |
| 28 | 601(I) 6312 |
FILTER FABRIC (RIPRAP) | 240 | SY |
$4.00 |
$2.00 |
$2.00 |
$6.00 |
$8.00 |
| 29 | 619(D) 1397 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$20,000.00 |
$5,000.00 |
$14,000.00 |
$7,500.00 |
$5,375.00 |
| 30 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 15.2 | SF |
$17.00 |
$20.00 |
$16.00 |
$16.00 |
$20.00 |
| 31 | 851(C) 8324 |
2" SQUARE TUBE POST | 56 | LF |
$11.00 |
$20.00 |
$8.00 |
$8.00 |
$12.00 |
| 32 | 853 9030 |
DELINEATORS(TYPE 1, CODE 3) | 4 | EA |
$20.00 |
$50.00 |
$20.00 |
$20.00 |
$25.00 |
| 33 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$4,000.00 |
$6,000.00 |
$2,400.00 |
$2,200.00 |
$3,200.00 |
| 34 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$10,000.00 |
$3,000.00 |
$6,000.00 |
$3,000.00 |
$7,500.00 |
| 35 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$4,000.00 |
$1,500.00 |
$3,000.00 |
$1,500.00 |
$3,800.00 |
| 36 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$50,000.00 |
$10,000.00 |
$44,000.00 |
$45,000.00 |
$31,600.00 |