2Let jobs
$2,251,164Total low bids
$2,590,279Total estimates
-13.1%Low bids vs estimates
Feb 2013 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Feb 21, 2013 | 130026STP-114B(301)AG | Cleveland Division 3 |
RESURFACE (ASPHALT ) CITY STREETS (TECUMSEH RD)/24TH AVE /LINDSEY ST ): AT MULTIPLE LOCATIONS IN THE CITY OF NORMAN . PROJECT LENGTH = 2.927 MILES · | $1,796,701 | $1,393,772 | HASKELL LEMON CONSTRUCTION CO. | -22.4% | 4 |
| Feb 21, 2013 | 130010CIRB-106D(087)RB | Blaine Division 5 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-262): OVER SALT CREEK , 7.2 MILES AND 1.0 MILE WEST OF THE SH -8/SH-51 JCT IN OKEENE . PROJECT LENGTH = 0.189 MILES · | $793,578 | $857,392 | RRY SERVICES LLC | +8.0% | 4 |
1–2 of 2
Source: ODOT bid tabulations for each letting on Contracts and Proposals, read from ODOT's published bid tab reports, including the engineer's estimate. Bid Potato loads new lettings as ODOT posts them and backfills the last two years. Confirm against ODOT's official tabulations.