Filtered by: County: Peoria Clear all
| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Jan 19, 2018 | 68B67 | PeoriaDistrict 4 | Resurfacing on US 24 from south of IL 9 to north of Pfeiffer Road and on IL 9 from US 24 to 0.27 miles east. | — | Executed | Advanced Asphalt Company $3,038,514 · | ||
| Jan 19, 2018 | 89709 | PeoriaDistrict 4 | Reconstruction of Old Galena Road between Boy Scout Road and Cedar Hills Drive, including new traffic signals at Cedar Hills Drive. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $3,759,289 · | ||
| Mar 9, 2018 | 68887 | PeoriaDistrict 4 | Bridge rehabilitation to structure numbers: 072-0127, 072-0128, 072-0129, 072-0130, 072-0131 and 072-0132. | — | Executed | Stark Excavating, Inc. $11,778,628 · | ||
| Mar 9, 2018 | 68D15 | PeoriaDistrict 4 | Patching, resurfacing, ADA ramp improvements and signal upgrades on IL 40 from West Corrington Ave. to Pennsylavania Ave. in Peoria. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $2,429,480 · | ||
| Mar 9, 2018 | 68D16 | PeoriaTazewellDistrict 4 | Resurfacing on I-74 from Washington St. to Muller Road, from Morton Ave. to Mainstreet, from Sterling Ave. to the Union Pacific Railroad structure. Also, resurfacing on I-474 Roadway A and B in Peoria. | — | Executed | Advanced Asphalt Company $6,988,434 · | ||
| Mar 9, 2018 | 68E04 | PeoriaPutnamTazewellDistrict 4 | 31 miles of crack and joint sealing on US 150, IL 26 and I-155. | — | Executed | Complete Asphalt Service Co. $164,160 · | ||
| Mar 9, 2018 | 68E06 | PeoriaDistrict 4 | Landscaping along I-74 from Ellis Street in Peoria to the Illinois River. | — | Executed | Central Landscaping, LP $88,972 · | ||
| Jun 15, 2018 | 68B59 | KnoxPeoriaDistrict 4 | Guardrail removal and culvert extensions at various locations on IL 8 and US 150, culvert replacement at Location 18 on US 150. | — | Executed | Illinois Civil Contractors, Inc. $1,589,198 · | ||
| Jun 15, 2018 | 68E03 | PeoriaDistrict 4 | Installation of traffic signals and an eastbound left-turn lane at the intersection of US 24 and Cameron Lane (IL 9). | — | Executed | Oberlander Electric Co. $595,444 · | ||
| Jun 15, 2018 | 68E15 | PeoriaDistrict 4 | 2.7 miles of shoulder restoration along IL 6 from IL 40 to IL 29. | — | Rejected | |||
| Jun 15, 2018 | 68E39 | PeoriaTazewellDistrict 4 | Installation of turn signals, luminaires, light poles, lighting controller and relocation of existing railroad interconnected traffic signal controller cabinet at various locations. | — | Executed | Laser Electric, Inc. $183,757 · | ||
| Aug 3, 2018 | 68D96 | PeoriaDistrict 4 | Construction of an HMA parking lot with fence east of the District 4 materials lab, off US 150 in Edwards. | — | Rejected | |||
| Sep 21, 2018 | 68E47 | PeoriaDistrict 4 | Scour mitigation at SN 072-0034 carrying IL 90 over Prince Run. | — | Executed | Illinois Civil Contractors, Inc. $155,436 · | ||
| Nov 9, 2018 | 68185 | PeoriaDistrict 4 | Replacement of the structure carrying Farminton Road over Kickapoo Creek and reconstruction of the Farmington Road/Kickapoo Creek intersection, includes pavement improvements from west of the railroad tracks to west of Redbud Drive. | — | Executed | Stark Excavating, Inc. $10,061,876 · | ||
| Jan 18, 2019 | 68E20 | PeoriaDistrict 4 | Installation of fiber optic cable, communications equipment and CCTV for a new traffic signal system in Peoria. | — | Rejected | Oberlander Electric Co. $790,000 · | ||
| Jan 18, 2019 | 89712 | PeoriaDistrict 4 | Pavement reconstruction, PCC pavement, curb and gutter, storm sewers, PCC multi-use path, street lighting and pedestrian signals, on Dirksen Parkway from Middle Road to Airport Road. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $5,449,818 · | ||
| Jan 18, 2019 | 89732 | PeoriaDistrict 4 | Construction of 4' HMA shoulders with rumble strips, 2' aggregate shoulders and the reconstruction of ditches on Kickapoo-Edwards Road from Shamrock Lane to Countryside Lane. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $1,175,654 · | ||
| Mar 8, 2019 | 68D22 | PeoriaDistrict 4 | Resurfacing, ADA improvements, traffic signal improvements, and drainage improvements along IL Rte 29 south of US Rte 150 to Abington St in Peoria. | — | Executed | Advanced Asphalt Company $1,972,818 · | ||
| Mar 8, 2019 | 68E36 | PeoriaDistrict 4 | Bituminous surface treatment- A1 on IL Rte 91 from the Stark county line. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $169,369 · | ||
| Mar 8, 2019 | 68E62 | PeoriaDistrict 4 | Landscaping along I-74 from Ellis St to the Illinois River. | — | Executed | Central Landscaping, LP $122,806 · | ||
| Mar 8, 2019 | 68E80 | PeoriaDistrict 4 | Construction of an aggregate parking lot with fence east of District 4 materials lab off of US 150 in Edwards. | — | Executed | Otto Baum Company, Inc. $218,121 · | ||
| Apr 26, 2019 | 68D98 | PeoriaDistrict 4 | Surfacing maintenance including pavement patching, HMA surface removal, HMA surface course, and the construction of ADA ramps at various locations on IL Rte 40. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $919,865 · | ||
| Jun 14, 2019 | 68D99 | PeoriaTazewellDistrict 4 | TEMPORARY SIGNUNG FOR I-74 CLOSURE AND DETOUR ROUTES FOR THE MURRAY BAKER BRIDGE REHABILITATION PROJECT. | — | Executed | T.M.F. Construction Company $824,481 · | ||
| Jun 14, 2019 | 68E71 | PeoriaTazewellDistrict 4 | DETOUR ROUTE PREPARATION, INCLUDING TEMPORARY PAVEMENT AND MISCELLANEOUS ELECTRICAL WORK, ALONG IL RTE 40 IN PEORIA AND EAST PEORIA FOR MURRAY BAKER REHABILITATION PROJECT. | — | Executed | Otto Baum Company, Inc. $1,476,305 · | ||
| Jun 14, 2019 | 68E87 | PeoriaDistrict 4 | PATCHING ON IL 6 AND I-474 FROM IL 40 (KNOXVILLE AVE) TO STRUCTURE OVER IL 8 IN PEORIA. | — | Executed | G. M. Sipes Construction, Inc. $432,414 · | ||
| Jun 14, 2019 | 68E91 | PeoriaDistrict 4 | INSTALLATION OF CENTRAL TRAFFIC SIGNAL SYSTEM SOFTWARE, TRAFFIC SIGNAL CONTROLLERS, AND TRAFFIC SIGNAL CABINETS AT VARIOUS INTERSECTIONS LOCATED WITH- IN PEORIA. | — | Rejected | Oberlander Electric Co. $540,150 · | ||
| Jun 14, 2019 | 68F02 | PeoriaDistrict 4 | MILL AND OVERLAY SN 072-0012 AND 072-0133 CARRYING ADAMS ST OVER BNSF AND UP RAILROADS AT THE WESTERN CITY LIMITS OF PEORIA. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $261,161 · | ||
| Jun 14, 2019 | 89750 | PeoriaDistrict 4 | Replace the bridge carrying Streitmattes Road over a Branch of Spoon River, located 1.6 miles Southeast of Duncan. | — | Executed | Stark Excavating, Inc. $823,220 · | ||
| Jul 12, 2019 | 68D68 | MarshallPeoriaDistrict 4 | 7.5 miles of resurfacing on IL-29 from Senachwine Creek in Chilicothe to IL-17 E in Sparland. | — | Executed | Advanced Asphalt Company $3,791,715 · | ||
| Jul 12, 2019 | 68D88 | PeoriaDistrict 4 | Milling and resurfacing on IL-9 from 0.27 miles E of US 24 to the McNaughton bridge. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $2,138,535 · | ||
| Jul 12, 2019 | 68E93 | PeoriaDistrict 4 | Resurfacing on IL-40 from Ravinswood Rd. to N of Timber Lane. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $2,243,611 · | ||
| Aug 2, 2019 | 68E96 | PeoriaDistrict 4 | 1.7 miles of patching and joint repair on IL 40 (Knoxville Avenue) from Timber Lane to Bethany Way in Peoria. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $276,562 · | ||
| Sep 20, 2019 | 68C57 | PeoriaDistrict 4 | SUPERSTRUCTURE REPLACEMENT TO SN 072-0073 CARRYING BELL SCHOOL RD OVER I-74 AND RESURFACE IL 78 FROM I-74 N 0.13 MI AND 0.2 MI S. | — | Executed | Stark Excavating, Inc. $2,937,974 · | ||
| Sep 20, 2019 | 68E16 | PeoriaTazewellDistrict 4 | CULVERT LINING ON VARIOUS ROUTES WITHIN PEORIA AND TAZEWELL COUNTIES. | — | Executed | Hoerr Construction, Inc. $769,350 · | ||
| Sep 20, 2019 | 68E53 | PeoriaTazewellDistrict 4 | CONSTRUCTION, REPLACEMENT OR CROSSWALKS ALONG IL 29 (ADAMS and JEFFERSON ST) FROM HANCOCK ST TO WAYNE STREET IN PEORIA, IL 8 FROM CHERRY LANE TO MEADOWVIEW LN IN SUNNYLAND, IL 8 AT LEGION RD AND BUS 24 AT BONDURANT ST IN WASHINGTON. | — | Executed | Otto Baum Company, Inc. $537,618 · | ||
| Nov 8, 2019 | 89744 | PeoriaDistrict 4 | Replace bridge carrying Smithville Road over Copperas Creek, located 0.6 miles west of Trivoli Road. | — | Executed | Stark Excavating, Inc. $1,238,874 · | ||
| Nov 8, 2019 | 89748 | PeoriaDistrict 4 | Replace bridge carrying Kickapoo Creek Road over an unnamed tributary to Kickapoo Creek, located 0.10 miles north of Adams Street. | — | Active | |||
| Mar 6, 2020 | 68A76 | PeoriaDistrict 4 | Resurfacing on IL Rte 91 from the IL Rte 90E junction to S of Parks School Rd in Dunlap. | — | Executed | Advanced Asphalt Company $1,656,535 · | ||
| Mar 6, 2020 | 68C98 | PeoriaDistrict 4 | Approximately 4.4 miles of ramp pavement and approximately 3.0 miles of Class A and B patching, resurfacing the concrete pavement, drainage improvements, guardrail replacement, pavement markings, aggregate shoulders, construction of detour route turnaround, electrical improvements, and structural repairs. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $13,768,359 · | ||
| Mar 6, 2020 | 68E58 | PeoriaDistrict 4 | 1.0 mile milling and resurfacing along US 150 from W of Northland Ave to W of Brandywine Dr. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $3,379,094 · | ||
| Mar 6, 2020 | 68E72 | PeoriaTazewellDistrict 4 | Installation of dynamic message signs and associated work at four locations along I-74. | — | Executed | Western Remac, Inc. $1,157,885 · | ||
| Mar 6, 2020 | 68F05 | PeoriaDistrict 4 | Landscaping along I-74 from Ellis St in Peoria to the Illinois River. | — | Executed | Central Landscaping, LP $181,242 · | ||
| Mar 6, 2020 | 89778 | PeoriaDistrict 4 | Resurfacing Allen Road from Walton Road to 0.2 mile south of Altorfer Drive in the City of Peoria. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $1,067,381 · | ||
| Apr 24, 2020 | 68A81 | PeoriaDistrict 4 | Resurfacing on IL 29 from 0.2 mile S of Cloverdale Rd in Chillicothe to Dickison Run Creek, N of IL 6 in Peoria County. | — | Executed | Advanced Asphalt Company $9,418,655 · | ||
| Apr 24, 2020 | 68C92 | PeoriaDistrict 4 | Intersection improvement at IL Rte 40 and Lake Ave in Peoria. (Offset left turn lanes.) | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $915,345 · | ||
| Apr 24, 2020 | 68E88 | PeoriaDistrict 4 | Repair to ramps on I-474 at Airport Rd and US Rte 24 interchanges in Peoria. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $476,329 · | ||
| Apr 24, 2020 | 68F20 | PeoriaTazewellDistrict 4 | Replacement of traffic signal mast arms at various locations in Peoria and Tazewell Counties. | — | Executed | Oberlander Electric Co. $374,200 · | ||
| Apr 24, 2020 | 68F42 | PeoriaDistrict 4 | Ramp metering along the entrance ramp from Fayette St to Eastbound I-74 in Peoria. | — | Executed | Laser Electric, Inc. $174,042 · | ||
| Apr 24, 2020 | 89773 | PeoriaDistrict 4 | Construction of new sidewalks and a refuge island, signing and lighting improvements on IL 91, located south of Copperfield Drive in the Village of Dunlap. | — | Executed | Illinois Civil Contractors, Inc. $179,736 · | ||
| Jun 12, 2020 | 68A83 | PeoriaDistrict 4 | Resurfacing on I-74 from E of Il 78 to W of Kickapoo/Edwards Rd including joint replacement and slope wall repair to SN-s 072-0077 and 072-0078 over Schlink Rd and joint replacement to SN-s 072-0078 and 072-0080 on I-74 over Kickapoo Creek. | — | Executed | Advanced Asphalt Company $16,030,666 · | ||
| Jun 12, 2020 | 68F58 | PeoriaDistrict 4 | 2.42 miles of longitudinal joint repair and pavement marking maintenance along US 150 (War Memorial Dr) from N Frostwood Pkwy to W Northbound Ave. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $591,671 · | ||
| Jun 12, 2020 | 68F62 | PeoriaDistrict 4 | Shoulder repair along IL 6 from the IL 29 interchange to E of IL 40 (Knoxville Ave) in Peoria. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $629,048 · | ||
| Jul 31, 2020 | 68F15 | PeoriaDistrict 4 | 5.75 miles of resurfacing on I-74 from W of Kickapoo/Edwards Rd to 0.7 mile E of I-474. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $10,969,411 · | ||
| Jul 31, 2020 | 68F61 | PeoriaDistrict 4 | Substructure repair to SN 072-0138 carrying IL 6 over Charter Oak Rd in Peoria. | — | Executed | Halverson Construction Co., Inc. $190,984 · | ||
| Jul 31, 2020 | 68F66 | PeoriaDistrict 4 | Bridge beam replacement on SN 072-0056 at Dry Run Creek E of Sterling Ave in West Peoria. | — | Executed | Otto Baum Company, Inc. $132,756 · | ||
| Nov 6, 2020 | 68E60 | PeoriaDistrict 4 | Building Demo at 1229 Kickapoo Creek Road in Peoria. | — | Executed | Illinois Civil Contractors, Inc. $45,885 · | ||
| Nov 6, 2020 | 68G05 | PeoriaTazewellDistrict 4 | Replacement of existing video detection systems at various locations in Peoria various locations in Peoria and Tazewell Counties in District Four. | — | Executed | Oberlander Electric Co. $406,250 · | ||
| Nov 6, 2020 | 89745 | PeoriaDistrict 4 | Replace the bridge carrying CH 29D over Jubilee Creek, 2.7 miles east of Brimfield | — | Executed | Stark Excavating, Inc. $1,296,220 · | ||
| Nov 6, 2020 | 89766 | PeoriaDistrict 4 | Reconstruction of Western Ave, from Adams Street to Lincoln Avenue and a portion of IL 8, from Lincoln Avenue to Howett St in Peoria. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $12,585,868 · | ||
| Jan 15, 2021 | 68F97 | PeoriaDistrict 4 | Landscaping along 1-74 from Ellis Street in Peoria to the Illinois River in Peoria County. | — | Executed | JIMAX Landscape LLC $225,732 · | ||
| Jan 15, 2021 | 68G07 | FultonPeoriaWarrenDistrict 4 | Tree removal and other collateral work located along US 24 at Copperas Creek near Banner in Fulton County, alo This project consists of tree removal and other collateral work located along US 24 at Copperas Creek near Banner in Fulton County, along US 67 north of Monmouth in Warren County, and along IL 40 between Northmoor Road and Mt. Hawley in Peoria County. | — | Executed | Homer Tree Service, Inc. $146,325 · | ||
| Mar 5, 2021 | 68F12 | PeoriaDistrict 4 | Overlay on IL 29 (Fourth Street) from Senachwine Creek to Truitt Avenue in Chillicothe with ADA ramp construction. Length =0.94 mile. | — | Executed | Advanced Asphalt Company $1,042,379 · | ||
| Apr 23, 2021 | 68G18 | PeoriaDistrict 4 | Longitudinal joint repair and partial depth patching along US 150 (War Memorial Drive) from West of Brandywine Drive to IL 29 (Adams St) in Peoria. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $515,084 · | ||
| Apr 23, 2021 | 68G21 | PeoriaTazewellDistrict 4 | Installation of new traffic signal cabinets, traffic signal controllers, communications equipment, and video detection systems at various locations in District Four. | — | Executed | Laser Electric, Inc. $482,887 · | ||
| Apr 23, 2021 | 89723 | PeoriaDistrict 4 | Construction of Rock Island Trail Extension within the City of Peoria, along Park Avenue, from NE Perry Avenue to the old railroad crossing, and along the former Peoria and Peoria Heights railroad bed from Park Avenue to Harvard Avenue, including rehabilitation of the abandoned railroad bridge over War Memorial Drive. | — | Executed | Illinois Civil Contractors, Inc. $1,793,566 · | ||
| Jun 11, 2021 | 46926 | PeoriaDistrict 4 | Removal of the three 36-inch diameter culverts and replacing them witha 54-inch diameter culvert, and other drainage and signage work at Jubilee College State Park in Peoria County. | — | Executed | Stark Excavating, Inc. $272,935 · | ||
| Jun 11, 2021 | 68C45 | PeoriaDistrict 4 | Resurfacing and bridge deck overlays and repairs to various structures on Interstate 474 from Interstate 474 to the Illinois River in Peoria County. | — | Executed | Advanced Asphalt Company $20,960,049 · | ||
| Jun 11, 2021 | 68C58 | PeoriaDistrict 4 | Superstructure replacement to S.N. 072-0076 carrying Maher Road over 1-74 (S.N. 072-0076) near Brimfield in Peoria County. | — | Executed | Stark Excavating, Inc. $3,514,647 · | ||
| Jun 11, 2021 | 68E48 | PeoriaDistrict 4 | Crossover construction to maintain traffic, superstructure replacement, and other minor substructure repairs o This project is approximately 0.6 mile in length and consist of crossover construction to maintain traffic, superstructure replacement, and other minor substructure repairs on S.N. 072-0008, located 1.0 mile West of Mapleton in Peoria County. | — | Executed | Otto Baum Company, Inc. $1,675,118 · | ||
| Jun 11, 2021 | 68E52 | PeoriaDistrict 4 | Bridge Rehabilitation to six (6) structures at the I-74/I-474/IL 6 interchange in Peoria. | — | Executed | Stark Excavating, Inc. $4,067,495 · | ||
| Jun 11, 2021 | 68E82 | PeoriaDistrict 4 | 0.17 mile. Sidewalk replacement, railing repairs, and miscellaneous drainage improvements along US Route 150 (War Memorial Drive) from Grand Avenue to Harvard Avenue in Peoria. | — | Executed | Otto Baum Company, Inc. $208,725 · | ||
| Jun 11, 2021 | 68G03 | PeoriaDistrict 4 | Bridge deck waterproofing and deck overlay to Structure No. 072-0134 carrying US 24 over Kickapoo Creek near Bartonville in Peoria County. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $406,194 · | ||
| Jun 11, 2021 | 68G13 | PeoriaDistrict 4 | This project is approximately 0.06 mile in length, consisting of slope repair and drainage improvements along IL Route 40, between North Mt. Hawley Road and Northmoor Road in Peoria. | — | Executed | Phoenix Corporation of the Quad Cities $437,836 · | ||
| Jun 11, 2021 | 68G15 | PeoriaDistrict 4 | Slope stabilization and landscaping along WB Interstate 74 between Ellis Street and North Street in Peoria County. | — | Executed | Central Landscaping, LP $245,433 · | ||
| Jun 11, 2021 | 68G54 | PeoriaDistrict 4 | Traffic signal mast arm replacement at various locations throughout Peoria County. | — | Executed | Oberlander Electric Co. $565,500 · | ||
| Jun 11, 2021 | 89785 | PeoriaDistrict 4 | Sidewalk construction on Allen Road from 0.6 mile north of Wilhelm Rd. to Whilhelm Rd. and on Orange Prairie Road from Landens Way to War Memorial Drive in Peoria | — | Executed | Otto Baum Company, Inc. $109,223 · | ||
| Jun 11, 2021 | 89801 | PeoriaDistrict 4 | Rehabilitate the bridge carrying Truitt Road over Hollow Creek. Remove and replace superstructure, backwalls at the abutments and repair piers. | — | Executed | Stark Excavating, Inc. $827,258 · | ||
| Jul 30, 2021 | 68799 | PeoriaDistrict 4 | Removal and replacement of the existing structure carrying IL Route 8 over BNSF Railway (Existing S.N. 072-0049; Proposed S.N. 072-0248) at Edwards on a realigned IL Route 8. The project length is 0.68 mile. | — | Executed | White Construction LLC $12,957,193 · | ||
| Jul 30, 2021 | 89786 | PeoriaDistrict 4 | Construction of sidewalks and ADA ramps on the south side of West Knolls Road from North University Drive to 0.15 mile east of Allen Road in Peoria. | — | Executed | Illinois Civil Contractors, Inc. $234,082 · | ||
| Nov 5, 2021 | 68F74 | PeoriaDistrict 4 | Bridge deck overlay and bridge joint replace/repair on IL 8 structures; S.N. 072-0164 over Nixon Run Creek; S.N. 072-0165 over Warsaw Creek and S.N. 072-0166 over Kickapo Creek Tributary. | — | Executed | Stark Excavating, Inc. $993,747 · | ||
| Nov 5, 2021 | 89811 | PeoriaDistrict 4 | Replace the bridge carrying CH 23R over the west fork of Kickapoo Creek, located southeast of Elmwood. | — | Executed | Stark Excavating, Inc. $1,996,313 · | ||
| Jan 21, 2022 | 68G59 | PeoriaDistrict 4 | Landscaping along 1-74 from Ellis Street in Peoria to the Illinois River. | — | Executed | Central Landscaping, LP $279,293 · | ||
| Jan 21, 2022 | 68G75 | PeoriaTazewellDistrict 4 | Repair and replace traffic signals, overhead lighting, and ITS facilities at various locations in East Peoria, Peoria, Pekin and Peoria County. | — | Executed | Oberlander Electric Co. $301,890 · | ||
| Mar 11, 2022 | 68G28 | PeoriaTazewellDistrict 4 | Crack and Joint Sealing on US 24/IL 9 from N of Pfeiffer Rd in Bartonville to 0.16 mi SW of IL 9 (E.) and on IL 29 from Margaret Drive in Creve Coeur to N of LaSalle BLVD in Marquette Heights. | — | Executed | Denler, Inc. $214,975 · | ||
| Apr 29, 2022 | 68G34 | PeoriaDistrict 4 | Microsurfacing (1-pass)on IL 116 from IL 78(N) in Farmington to Eden Road. | — | Executed | Microsurfacing Contractors, LLC, a Division of Byrne and Jones Holding Company $553,862 · | ||
| Apr 29, 2022 | 89789 | PeoriaDistrict 4 | Full Depth pavement removal, PCC Pavement, Curb and Gutter, Pipe Underdrains, Storm Sewer, HMA Multi-Use Path, PCC Sidewalks, Pavement Markings, and Landscaping on Gleen Avenue between Sheridan Road and Knoxville Avenue (IL-140) . | — | Executed | Otto Baum Company, Inc. $5,288,286 · | ||
| Jun 17, 2022 | 68G69 | PeoriaDistrict 4 | Bridge repairs on SN 072-0148, including the replacement of the existing expansion joints with strip seals and This project consists of bridge repairs on SN 072-0148, including the replacement of the existing expansion joints with strip seals and plating all beam ends at both abutments along with other related work necessary to complete the project as shown in the plans and as described herein. Structure carrying Mossville Rd. over IL 6. | — | Executed | Stark Excavating, Inc. $278,003 · | ||
| Jun 17, 2022 | 68G72 | PeoriaDistrict 4 | Patching on IL 6 from US 150 to I-74. | — | Executed | Kinney Contractors, Inc. $627,541 · | ||
| Jul 15, 2022 | 68H07 | PeoriaDistrict 4 | Transverse and longitudinal partial-depth patching along IL 29 from North of Gardner Ln. to North of Lorentz Ave. in Peoria County. Total length is 2.45 miles. | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $1,141,394 · | ||
| Jul 15, 2022 | 68H10 | PeoriaDistrict 4 | 1360 feet of PCC TY B Pavement Patching from Martin to Moss Avenue in Peoria. | — | Executed | G. M. Sipes Construction, Inc. $579,888 · | ||
| Aug 5, 2022 | 68H09 | PeoriaDistrict 4 | Mill and resurface parking area and install parking striping at the Peoria West storage yard (6500 W. Highway 150, Edwards, IL., 2.5 Miles west of Peoria ou US 150). | — | Executed | R. A. Cullinan and Son, a div of UCM, Inc. $204,296 · | ||
| Sep 23, 2022 | 68884 | PeoriaDistrict 4 | 909.3 FT., Bridge Replacements on I-474 over IL 116 (Plank Rd.) in Bellevue. | — | Executed | Stark Excavating, Inc. $11,025,102 · | ||
| Nov 18, 2022 | 68E32 | PeoriaDistrict 4 | The culvert rehabilitation of SN 072-2008, a double 10' x 10' box culvert, at Big Hollow Creek on US 150 (War Project consists of the culvert rehabilitation of SN 072-2008, a double 10' x 10' box culvert, at Big Hollow Creek on US 150 (War Memorial) in Peoria. | — | Executed | Phoenix Corporation of the Quad Cities $329,174 · | ||
| Nov 18, 2022 | 68F38 | PeoriaTazewellDistrict 4 | Bridge Rehabilitation with bridge deck overlay, beam repairs, beam additions, navigation and roadway lighting, traffic signal improvements, drainage improvements, full depth pavement removal and replacement, sidewalk removals, multi-use path construction and related collateral work. Bob Michel Bridge (SN 090-0122) in Peoria and Tazewell Counties on IL 40 (William Kumpf Blvd.) over the Illinois River and Washington Street. | — | Executed | ICC Group Inc. $24,657,000 · | ||
| Jan 20, 2023 | 89821 | PeoriaDistrict 4 | Rehabilitate the bridge carrying CH 23R over Timber Creek, 0.7 mile north of IL 8. | — | Executed | Stark Excavating, Inc. $727,272 · | ||
| Jan 20, 2023 | 89822 | PeoriaDistrict 4 | Replace existing box culvert on Graham Chapel Road at a Tributary of West Fork over Kickapoo Creek, 0.6 mile west of Stone School Road. | — | Executed | Illinois Civil Contractors, Inc. $1,333,481 · | ||
| Jan 20, 2023 | 89826 | PeoriaDistrict 4 | PCC pavement reconstruction, PCC Shoulders, curb and gutter, storm sewer replacement, traffic signal installation and lighting on Old Galena Road from IL 29 north to Neal Lane with a 0.26 mile omission north of IL 29 to south of Engine Drive. | — | Executed | Stark Excavating, Inc. $4,982,316 · | ||
| Mar 10, 2023 | 68G40 | PeoriaDistrict 4 | The project includes bridge deck overlay and scour mitigation to SN 072-0162 carrying IL 8 over Walnut Creek, East of IL 78. The project improvement length is 0.058 miles. | — | Executed | Otto Baum Company, Inc. $523,800 · | ||
| Mar 10, 2023 | 68H00 | PeoriaDistrict 4 | I-74 in the City of Peoria. | — | Active | Endrizzi Contracting, Inc $309,583 · | ||
| Mar 10, 2023 | 68H21 | PeoriaTazewellDistrict 4 | Crack and joint sealing at various locations along 1-74 and 1-474 in Peoria and Tazewell Counties. | — | Executed | Complete Asphalt Service Co. $224,649 · |
1–100 of 165Next ›
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.