9-PP
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | G. M. Sipes Construction, Inc. Low bidder | $579,888 | ||
| 2 | Kinney Contractors, Inc. | $603,804 | +4.1% | |
| 3 | Otto Baum Company, Inc. | $699,660 | +20.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 G. M. Sipes Con… | #2 Kinney Contract… | #3 Otto Baum Compa… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0322281 | W A VID DET SYS COM | 2 | EACH | $22,175.00 | $25,000.00 | $31,260.90 | |
| 2 | X0326812 | CAT 5 ETHERNET CABLE | 274 | FOOT | $3.00 | $3.40 | $0.9600 | |
| 3 | 44200050 | WELDED WIRE REINF | 585 | SQ YD | $10.00 | $18.00 | $32.22 | |
| 4 | 44200970 | CL B PATCH T2 10 | 1,187 | SQ YD | $195.00 | $201.00 | $241.05 | |
| 5 | 44200974 | CL B PATCH T3 10 | 358 | SQ YD | $190.00 | $199.00 | $238.47 | |
| 6 | 44200976 | CL B PATCH T4 10 | 227 | SQ YD | $190.00 | $197.00 | $211.49 | |
| 7 | 44201299 | DOWEL BARS 1 1/2 | 1,980 | EACH | $35.00 | $27.00 | $25.40 | |
| 8 | 44213198 | TIE BARS 1/2 | 18 | EACH | $30.00 | $17.00 | $167.01 | |
| 9 | 44213200 | SAW CUTS | 6,715 | FOOT | $7.95 | $4.00 | $8.23 | |
| 10 | 67100100 | MOBILIZATION | 1 | L SUM | $28,000.00 | $32,000.00 | $34,690.67 | |
| 11 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $12,000.00 | $48,300.00 | $13,914.55 | |
| 12 | 70103815 | TR CONT SURVEILLANCE | 10 | CAL DA | $0.0100 | $50.00 | $1,064.53 | |
| 13 | 70107025 | CHANGEABLE MESSAGE SN | 14 | CAL DA | $25.00 | $150.00 | $127.60 | |
| 14 | 78009000 | MOD URETH PM LTR-SYM | 125 | SQ FT | $7.40 | $7.70 | $9.44 | |
| 15 | 78009004 | MOD URETH PM LINE 4 | 5,783 | FOOT | $2.47 | $2.70 | $3.15 | |
| 16 | 78009008 | MOD URETH PM LINE 8 | 1,215 | FOOT | $4.94 | $5.10 | $6.30 | |
| 17 | 78009024 | MOD URETH PM LINE 24 | 99 | FOOT | $14.80 | $15.10 | $18.88 |