(126)SLP-1,DR
- Let date
- Friday, June 11, 2021
- Contract
- 68G13 · job page
- District
- District 4
- County
- Peoria
- Highway
- Limits
- This project is approximately 0.06 mile in length, consisting of slope repair and drainage improvements along IL Route 40, between North Mt. Hawley Road and Northmoor Road in Peoria.
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Phoenix Corporation of the Quad Cities Low bidder | $437,836 | ||
| 2 | Otto Baum Company, Inc. | $542,404 | +23.9% | |
| 3 | Stark Excavating, Inc. | $572,906 | +30.8% | |
| 4 | Fischer Excavating, Inc. | $716,826 | +63.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Phoenix Corpora… | #2 Otto Baum Compa… | #3 Stark Excavatin… | #4 Fischer Excavat… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0324028 | GROUT FOR RIPRAP | 25 | CU YD | $250.00 | $397.90 | $340.00 | $450.00 | |
| 2 | X0325299 | INLET MODIFICATION | 1 | EACH | $3,000.00 | $4,267.85 | $2,500.00 | $27,000.00 | |
| 3 | X1200191 | MH TA 8DIA T1FCL SPL | 1 | EACH | $14,500.00 | $23,199.77 | $19,000.00 | $27,000.00 | |
| 4 | X1200250 | INLET-MANHOLE MODIFICATION | 1 | EACH | $3,000.00 | $6,122.10 | $2,500.00 | $25,000.00 | |
| 5 | X1200251 | CONCRETE APRON FOR INLET | 1 | EACH | $6,200.00 | $6,547.26 | $3,550.00 | $20,000.00 | |
| 6 | X6640304 | CH LK FENCE REM & RE | 56 | FOOT | $15.00 | $68.54 | $265.00 | $150.00 | |
| 7 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $10,500.00 | $3,154.03 | $1,700.00 | $2,975.00 | |
| 8 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $4,000.00 | $5,329.22 | $3,500.00 | $8,830.00 | |
| 9 | Z0016702 | DETOUR SIGNING | 1 | L SUM | $9,400.00 | $9,679.59 | $8,500.00 | $7,750.00 | |
| 10 | Z0057900 | SAN SEW 36 | 130 | FOOT | $190.00 | $494.40 | $480.00 | $675.00 | |
| 11 | Z0057950 | SAN SEW 42 | 10 | FOOT | $250.00 | $1,517.93 | $480.00 | $2,850.00 | |
| 12 | 20100500 | TREE REMOV ACRES | 0.5 | ACRE | $22,500.00 | $55,220.36 | $55,000.00 | $44,000.00 | |
| 13 | 20200100 | EARTH EXCAVATION | 20 | CU YD | $35.00 | $91.51 | $27.00 | $100.00 | |
| 14 | 20700110 | POROUS GRAN EMBANK | 4,413 | TON | $45.50 | $40.44 | $41.00 | $40.00 | |
| 15 | 20800150 | TRENCH BACKFILL | 2 | CU YD | $115.00 | $112.15 | $60.00 | $130.00 | |
| 16 | 28000400 | PERIMETER EROS BAR | 132 | FOOT | $4.50 | $9.77 | $6.00 | $3.00 | |
| 17 | 28100225 | STONE RIPRAP CL B3 | 770 | TON | $63.00 | $66.67 | $66.00 | $80.00 | |
| 18 | 28100229 | STONE RIPRAP CL B5 | 257 | TON | $65.00 | $80.66 | $78.00 | $100.00 | |
| 19 | 42400100 | PC CONC SIDEWALK 4 | 220 | SQ FT | $16.00 | $10.55 | $63.00 | $15.00 | |
| 20 | 44000600 | SIDEWALK REM | 220 | SQ FT | $2.50 | $3.39 | $5.00 | $8.00 | |
| 21 | 50104400 | CONC HDWL REM | 1 | EACH | $500.00 | $746.05 | $1,250.00 | $7,265.00 | |
| 22 | 50105220 | PIPE CULVERT REMOV | 192 | FOOT | $20.00 | $39.90 | $12.00 | $39.00 | |
| 23 | 542D0226 | P CUL CL D 1 21 | 40 | FOOT | $65.00 | $129.89 | $88.00 | $300.00 | |
| 24 | 54210192 | PIPE ELBOW 36 | 1 | EACH | $1,700.00 | $5,673.45 | $3,500.00 | $5,700.00 | |
| 25 | 54213456 | END SECTIONS 21 | 1 | EACH | $350.00 | $1,104.98 | $480.00 | $786.00 | |
| 26 | 54262742 | METAL FL END SEC 42" | 1 | EACH | $1,100.00 | $1,768.82 | $2,350.00 | $2,300.00 | |
| 27 | 61000050 | CONC THRUST BLOCKS | 2 | EACH | $1,100.00 | $2,309.62 | $1,700.00 | $10,625.00 | |
| 28 | 63301225 | REM RE-E SPBGR TY D | 38 | FOOT | $40.00 | $110.16 | $600.00 | $175.00 | |
| 29 | 67100100 | MOBILIZATION | 1 | L SUM | $32,000.00 | $33,349.07 | $59,750.00 | $42,000.00 | |
| 30 | 70100325 | TRAF CONT-PROT 701423 | 1 | EACH | $4,000.00 | $9,135.79 | $4,950.00 | $9,950.00 | |
| 31 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $900.00 | $978.83 | $2,100.00 | $2,400.00 | |
| 32 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $50.00 | $217.52 | $2,000.00 | $1,900.00 | |
| 33 | 70107005 | PAVT MK BLKOUT TAPE 5 | 140 | FOOT | $1.75 | $2.72 | $1.50 | $5.00 | |
| 34 | 70107025 | CHANGEABLE MESSAGE SN | 14 | CAL DA | $85.00 | $135.95 | $50.00 | $140.00 | |
| 35 | 70300150 | SHRT TRM PAVT MK REM | 551 | SQ FT | $1.25 | $1.09 | $1.00 | $3.00 | |
| 36 | 70300904 | PAVT MARK TAPE T4 4 | 1,480 | FOOT | $1.40 | $1.47 | $3.00 | $2.10 | |
| 37 | 70400100 | TEMP CONC BARRIER | 550 | FOOT | $24.80 | $42.57 | $52.00 | $65.00 | |
| 38 | 70600240 | IMP ATTN TEMP NRD TL2 | 1 | EACH | $1,500.00 | $3,208.41 | $2,500.00 | $5,975.00 |