(45RB)BR
- Let date
- Friday, June 11, 2021
- Contract
- 68E48 · job page
- District
- District 4
- County
- Peoria
- Highway
- Limits
- This project is approximately 0.6 mile in length and consist of crossover construction to maintain traffic, superstructure replacement, and other minor substructure repairs on S.N. 072-0008, located 1.0 mile West of Mapleton in Peoria County.
- Classification
- Crossover construction to maintain traffic, superstructure replacement, and other minor substructure repairs o
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Otto Baum Company, Inc. Low bidder | $1,675,118 | ||
| 2 | Stark Excavating, Inc. | $1,690,572 | +0.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Otto Baum Compa… | #2 Stark Excavatin… |
|---|---|---|---|---|---|---|---|
| 1 | X4400110 | TEMP PAVT REMOVAL | 851 | SQ YD | $9.80 | $28.00 | |
| 2 | X4401198 | HMA SURF REM VAR DP | 223 | SQ YD | $14.41 | $17.25 | |
| 3 | X5030305 | CONC WEARING SURF 5 | 573 | SQ YD | $169.73 | $168.50 | |
| 4 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $4,896.69 | $1,050.00 | |
| 5 | X8410102 | TEMP LIGHTING SYSTEM | 1 | L SUM | $76,487.56 | $72,000.00 | |
| 6 | Z0001002 | GDRL AGG EROS CONT | 88 | TON | $55.37 | $91.25 | |
| 7 | Z0001900 | ASB BEARING PAD REMOV | 15 | EACH | $34.10 | $66.00 | |
| 8 | Z0012754 | STR REP CON DP = < 5 | 58.5 | SQ FT | $273.89 | $211.00 | |
| 9 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,092.10 | $4,750.00 | |
| 10 | Z0016702 | DETOUR SIGNING | 1 | L SUM | $7,286.92 | $4,000.00 | |
| 11 | Z0062456 | TEMP PAVEMENT | 851 | SQ YD | $53.96 | $76.00 | |
| 12 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | |
| 13 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | |
| 14 | 20200100 | EARTH EXCAVATION | 35 | CU YD | $77.98 | $54.00 | |
| 15 | 20300100 | CHANNEL EXCAVATION | 207 | CU YD | $28.05 | $25.00 | |
| 16 | 20400800 | FURNISHED EXCAVATION | 145 | CU YD | $69.91 | $95.00 | |
| 17 | 21400100 | GRADING & SHAP DITCH | 300 | FOOT | $9.49 | $7.00 | |
| 18 | 25000210 | SEEDING CL 2A | 0.5 | ACRE | $10,623.28 | $2,745.00 | |
| 19 | 25000400 | NITROGEN FERT NUTR | 45 | POUND | $6.37 | $2.00 | |
| 20 | 25000500 | PHOSPHORUS FERT NUTR | 45 | POUND | $6.37 | $2.00 | |
| 21 | 25000600 | POTASSIUM FERT NUTR | 45 | POUND | $6.37 | $2.00 | |
| 22 | 25100105 | MULCH METHOD 1 | 0.5 | ACRE | $2,124.64 | $2,745.00 | |
| 23 | 28000305 | TEMP DITCH CHECKS | 120 | FOOT | $9.67 | $12.00 | |
| 24 | 28100109 | STONE RIPRAP CL A5 | 630 | SQ YD | $98.49 | $98.00 | |
| 25 | 28200200 | FILTER FABRIC | 630 | SQ YD | $5.67 | $5.00 | |
| 26 | 31100300 | SUB GRAN MAT A 4 | 738 | SQ YD | $10.83 | $15.50 | |
| 27 | 40600290 | BIT MATLS TACK CT | 7,708 | POUND | $1.17 | $1.10 | |
| 28 | 40600982 | HMA SURF REM BUTT JT | 873 | SQ YD | $11.06 | $8.40 | |
| 29 | 40602978 | HMA BC IL-9.5 N50 | 74 | TON | $166.79 | $157.00 | |
| 30 | 40604060 | HMA SC IL-9.5 D N50 | 74 | TON | $171.03 | $161.00 | |
| 31 | 42000070 | PVT CON HMA BR APP SL | 131 | SQ YD | $95.61 | $107.00 | |
| 32 | 44000155 | HMA SURF REM 1 1/2 | 288 | SQ YD | $8.69 | $9.20 | |
| 33 | 44000156 | HMA SURF REM 1 3/4 | 4,485 | SQ YD | $2.54 | $2.85 | |
| 34 | 44000500 | COMB CURB GUTTER REM | 122 | FOOT | $14.29 | $18.50 | |
| 35 | 48101200 | AGGREGATE SHLDS B | 67 | TON | $54.61 | $100.00 | |
| 36 | 48203100 | HMA SHOULDERS | 587 | TON | $122.17 | $115.00 | |
| 37 | 50101500 | REM EXIST SUP-STR | 1 | EACH | $54,391.00 | $83,206.00 | |
| 38 | 50102400 | CONC REM | 5.6 | CU YD | $2,712.37 | $2,315.00 | |
| 39 | 50105220 | PIPE CULVERT REMOV | 210 | FOOT | $17.24 | $12.00 | |
| 40 | 50200100 | STRUCTURE EXCAVATION | 16 | CU YD | $36.90 | $36.50 | |
| 41 | 50300225 | CONC STRUCT | 47.8 | CU YD | $1,264.70 | $940.00 | |
| 42 | 50300260 | BR DECK GROOVING | 853 | SQ YD | $9.77 | $9.10 | |
| 43 | 50300300 | PROTECTIVE COAT | 853 | SQ YD | $2.52 | $2.85 | |
| 44 | 50301350 | CONC SUPSTR APP SLAB | 123.1 | CU YD | $415.58 | $350.00 | |
| 45 | 50400405 | P P CONC DK BM 21 DP | 5,142 | SQ FT | $82.76 | $88.00 | |
| 46 | 50800205 | REINF BARS, EPOXY CTD | 58,740 | POUND | $1.28 | $1.50 | |
| 47 | 50901050 | STEEL RAILING TY SM | 306 | FOOT | $211.77 | $216.00 | |
| 48 | 51500100 | NAME PLATES | 1 | EACH | $638.45 | $830.00 | |
| 49 | 52000110 | PREF JT STRIP SEAL | 86 | FOOT | $206.24 | $197.00 | |
| 50 | 5421D015 | P CUL CL D 1 15 TEMP | 210 | FOOT | $31.37 | $47.50 | |
| 51 | 54261715 | STEEL FL END SEC 15" | 2 | EACH | $362.80 | $600.00 | |
| 52 | 58600101 | GRANULAR BACKFILL STR | 16 | CU YD | $116.98 | $135.00 | |
| 53 | 59000200 | EPOXY CRACK INJECTION | 35 | FOOT | $36.71 | $50.00 | |
| 54 | 63000001 | SPBGR TY A 6FT POSTS | 188 | FOOT | $31.92 | $35.00 | |
| 55 | 63100087 | TRAF BAR TERM T6A | 2 | EACH | $3,951.86 | $4,500.00 | |
| 56 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $3,495.06 | $3,100.00 | |
| 57 | 63200310 | GUARDRAIL REMOV | 474 | FOOT | $19.28 | $7.00 | |
| 58 | 63800920 | MOD GLAR SCR SYS TEMP | 1,400 | FOOT | $6.37 | $5.35 | |
| 59 | 64200116 | SHOULDER RUM STRIP 16 | 4,095 | FOOT | $1.77 | $3.10 | |
| 60 | 66900200 | NON SPL WASTE DISPOSL | 35 | CU YD | $125.87 | $148.00 | |
| 61 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,381.03 | $900.00 | |
| 62 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,390.23 | $2,300.00 | |
| 63 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,443.35 | $2,300.00 | |
| 64 | 66901006 | REG SUB MON | 3 | CAL DA | $1,274.79 | $1,100.00 | |
| 65 | 67000400 | ENGR FIELD OFFICE A | 13 | CAL MO | $1,788.65 | $1,800.00 | |
| 66 | 67100100 | MOBILIZATION | 1 | L SUM | $73,558.00 | $53,692.00 | |
| 67 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $12,747.93 | $7,560.00 | |
| 68 | 70100320 | TRAF CONT-PROT 701422 | 1 | L SUM | $7,967.46 | $7,560.00 | |
| 69 | 70100410 | TRAF CONT-PROT 701416 | 1 | EACH | $30,223.21 | $17,400.00 | |
| 70 | 70100420 | TRAF CONT-PROT 701411 | 2 | EACH | $1,327.91 | $2,400.00 | |
| 71 | 70107005 | PAVT MK BLKOUT TAPE 5 | 4,107 | FOOT | $2.39 | $1.50 | |
| 72 | 70107007 | PAVT MK BLKOUT TAPE 7 | 226 | FOOT | $5.84 | $1.60 | |
| 73 | 70107009 | PAVT MK BLKOUT TAPE 9 | 198 | FOOT | $7.97 | $1.80 | |
| 74 | 70107025 | CHANGEABLE MESSAGE SN | 88 | CAL DA | $74.36 | $50.00 | |
| 75 | 70300150 | SHRT TRM PAVT MK REM | 5,456 | SQ FT | $1.54 | $1.00 | |
| 76 | 70300904 | PAVT MARK TAPE T4 4 | 11,330 | FOOT | $1.38 | $2.50 | |
| 77 | 70400100 | TEMP CONC BARRIER | 1,400 | FOOT | $31.47 | $33.00 | |
| 78 | 70500100 | TEMP SPBGR TY A | 100 | FOOT | $65.81 | $33.00 | |
| 79 | 70500615 | TEMP TR BAR TERM T1 | 1 | EACH | $6,612.98 | $2,900.00 | |
| 80 | 70500670 | TEMP TR BAR TERM T6A | 1 | EACH | $7,574.41 | $4,300.00 | |
| 81 | 70600305 | IMP ATTN TEMP FRR TL3 | 1 | EACH | $11,685.60 | $6,600.00 | |
| 82 | 72501000 | TERMINAL MARKER - DA | 3 | EACH | $42.49 | $30.00 | |
| 83 | 78009004 | MOD URETH PM LINE 4 | 5,259 | FOOT | $0.8000 | $2.18 | |
| 84 | 78009006 | MOD URETH PM LINE 6 | 210 | FOOT | $7.86 | $3.27 | |
| 85 | 78009008 | MOD URETH PM LINE 8 | 198 | FOOT | $8.29 | $4.36 | |
| 86 | 78009012 | MOD URETH PM LINE 12 | 42 | FOOT | $81.80 | $13.10 | |
| 87 | 78200005 | GRDRAIL REF TYPE A | 12 | EACH | $9.56 | $8.00 |