72(8,9,9-1)LS-14
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Endrizzi Contracting, Inc Low bidder | $309,583 | ||
| 2 | JIMAX Landscape LLC | $313,946 | +1.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Endrizzi Contra… | #2 JIMAX Landscape… |
|---|---|---|---|---|---|---|---|
| 1 | A2000600 | T-ACER PALMATUM 5 | 5 | EACH | $750.00 | $1,050.87 | |
| 2 | C2000324 | S-ARONIA ARBUT 2' | 10 | EACH | $120.00 | $430.02 | |
| 3 | C2003600 | S-HYDRA PANI LQF CG5 | 15 | EACH | $120.00 | $191.40 | |
| 4 | K0012975 | P PL ORNAMENT T 4" P | 0.8 | UNIT | $3,750.00 | $3,134.32 | |
| 5 | K0012990 | P PL ORNAMENT T GAL P | 0.7 | UNIT | $3,950.00 | $5,527.35 | |
| 6 | K0026700 | TREE CARE | 173 | EACH | $35.00 | $163.12 | |
| 7 | K0026810 | SHRUB CARE | 4,510 | EACH | $10.75 | $21.60 | |
| 8 | K0026850 | PERENNIAL PLANT CARE | 7,952 | SQ YD | $21.00 | $10.21 | |
| 9 | K0029618 | WEED CONT BROADLF TRF | 0.1 | GALLON | $6,500.00 | $17,825.10 | |
| 10 | K0029634 | WEED CONTR PRE-EM GRN | 900 | POUND | $15.00 | $9.24 | |
| 11 | K1004539 | PLANT WATERING | 6 | UNIT | $1,000.00 | $2,604.06 | |
| 12 | X0321501 | WEED BARRIER FABRIC | 367 | SQ YD | $9.00 | $17.98 | |
| 13 | X2503110 | MOWING SPL | 69 | ACRE | $465.00 | $508.73 | |
| 14 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $4,000.00 | $13,428.00 | |
| 15 | Z0064600 | SELECTIVE CLEARING | 0.04 | ACRE | $25,000.00 | $36,668.78 | |
| 16 | 67100100 | MOBILIZATION | 1 | L SUM | $15,000.00 | $6,000.00 |