D4 PARKING IMPROVEMENT 2018
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Otto Baum Company, Inc. Low bidder | $218,121 | ||
| 2 | R. A. Cullinan and Son, a div of UCM, Inc. | $268,746 | +23.2% | |
| 3 | Illinois Civil Contractors, Inc. | $279,819 | +28.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Otto Baum Compa… | #2 R. A. Cullinan … | #3 Illinois Civil … |
|---|---|---|---|---|---|---|---|---|
| 1 | X0800006 | PREPARATION OF BSE SP | 9,844 | SQ YD | $0.7500 | $1.54 | $2.49 | |
| 2 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $2,731.47 | $4,820.65 | $5,972.18 | |
| 3 | 20200100 | EARTH EXCAVATION | 384 | CU YD | $15.17 | $19.37 | $30.66 | |
| 4 | 20400800 | FURNISHED EXCAVATION | 386 | CU YD | $13.35 | $30.08 | $15.00 | |
| 5 | 25000200 | SEEDING CL 2 | 0.5 | ACRE | $5,919.06 | $5,859.00 | $6,240.60 | |
| 6 | 25000400 | NITROGEN FERT NUTR | 45 | POUND | $1.06 | $1.05 | $1.12 | |
| 7 | 25000500 | PHOSPHORUS FERT NUTR | 45 | POUND | $1.06 | $1.05 | $1.12 | |
| 8 | 25000600 | POTASSIUM FERT NUTR | 45 | POUND | $1.06 | $1.05 | $1.12 | |
| 9 | 28000500 | INLET & PIPE PROTECT | 3 | EACH | $87.80 | $171.80 | $218.08 | |
| 10 | 40200800 | AGG SURF CSE B | 4,127 | TON | $29.36 | $32.21 | $32.50 | |
| 11 | 66400305 | CH LK FENCE 6 | 1,176 | FOOT | $26.07 | $23.53 | $26.84 | |
| 12 | 66408200 | CH LK GATES 6X24 DBL | 2 | EACH | $2,635.94 | $2,074.80 | $2,236.77 | |
| 13 | 66900200 | NON SPL WASTE DISPOSL | 385 | CU YD | $53.78 | $91.04 | $89.62 | |
| 14 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $2,125.95 | $4,042.50 | $1,397.98 | |
| 15 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $3,174.56 | $4,593.75 | $2,292.69 | |
| 16 | 66901002 | ON-SITE MON REG SUB | 3 | CAL DA | $1,325.95 | $1,417.50 | $1,397.98 | |
| 17 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $3,174.56 | $1,968.75 | $2,292.69 | |
| 18 | 67100100 | MOBILIZATION | 1 | L SUM | $3,404.99 | $11,470.62 | $13,000.00 |