72(1,7,6-1)PP-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | G. M. Sipes Construction, Inc. Low bidder | $432,414 | ||
| 2 | Kinney Contractors, Inc. | $556,506 | +28.7% | |
| 3 | Otto Baum Company, Inc. | $610,155 | +41.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 G. M. Sipes Con… | #2 Kinney Contract… | #3 Otto Baum Compa… |
|---|---|---|---|---|---|---|---|---|
| 1 | 44200549 | CL A PATCH T1 10 | 45 | SQ YD | $275.00 | $230.00 | $331.32 | |
| 2 | 44200553 | CL A PATCH T2 10 | 401 | SQ YD | $200.00 | $175.00 | $233.08 | |
| 3 | 44200557 | CL A PATCH T3 10 | 244 | SQ YD | $200.00 | $173.00 | $218.20 | |
| 4 | 44200559 | CL A PATCH T4 10 | 1,052 | SQ YD | $175.00 | $170.00 | $205.08 | |
| 5 | 44200637 | CL A PATCH T2 17 | 6 | SQ YD | $295.00 | $260.00 | $319.17 | |
| 6 | 44200641 | CL A PATCH T3 17 | 16 | SQ YD | $295.00 | $257.00 | $307.25 | |
| 7 | 44200643 | CL A PATCH T4 17 | 27 | SQ YD | $270.00 | $255.00 | $296.30 | |
| 8 | 44213000 | PATCH REINFORCEMENT | 1,791 | SQ YD | $25.00 | $60.00 | $47.98 | |
| 9 | 44213200 | SAW CUTS | 6,848 | FOOT | $0.0100 | $4.00 | $4.13 | |
| 10 | 44213204 | TIE BARS 3/4 | 295 | EACH | $15.00 | $16.00 | $17.56 | |
| 11 | 67100100 | MOBILIZATION | 1 | L SUM | $20,000.00 | $25,000.00 | $24,281.65 | |
| 12 | 70100420 | TRAF CONT-PROT 701411 | 15 | EACH | $1.00 | $1,000.00 | $1,039.93 | |
| 13 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $20,000.00 | $55,500.00 | $47,603.22 | |
| 14 | 70103815 | TR CONT SURVEILLANCE | 6 | CAL DA | $0.0100 | $300.00 | $720.49 | |
| 15 | 70107025 | CHANGEABLE MESSAGE SN | 20 | CAL DA | $25.00 | $150.00 | $159.17 | |
| 16 | 78001110 | PAINT PVT MK LINE 4 | 500 | FOOT | $6.75 | $5.00 | $7.16 |