19-00384-00-SW
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Otto Baum Company, Inc. Low bidder | $109,223 | ||
| 2 | Knapp Concrete Contractors, Inc. | $128,161 | +17.3% | |
| 3 | Stark Excavating, Inc. | $138,449 | +26.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Otto Baum Compa… | #2 Knapp Concrete … | #3 Stark Excavatin… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2600012 | REM & REL SN P&P ASSY | 1 | EACH | $363.39 | $450.00 | $395.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $5,100.00 | $10,000.00 | $7,915.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $8,391.27 | $6,700.00 | $3,750.00 | |
| 4 | 20100110 | TREE REMOV 6-15 | 48 | UNIT | $60.70 | $75.00 | $70.00 | |
| 5 | 20100210 | TREE REMOV OVER 15 | 18 | UNIT | $60.70 | $75.00 | $70.00 | |
| 6 | 20200100 | EARTH EXCAVATION | 42 | CU YD | $118.66 | $80.00 | $500.00 | |
| 7 | 20400800 | FURNISHED EXCAVATION | 6 | CU YD | $116.30 | $100.00 | $41.50 | |
| 8 | 25000100 | SEEDING CL 1 | 0.4 | ACRE | $4,259.53 | $4,800.00 | $4,800.00 | |
| 9 | 25000400 | NITROGEN FERT NUTR | 35 | POUND | $3.19 | $3.30 | $2.00 | |
| 10 | 25000500 | PHOSPHORUS FERT NUTR | 35 | POUND | $3.19 | $3.30 | $2.00 | |
| 11 | 25000600 | POTASSIUM FERT NUTR | 35 | POUND | $3.19 | $3.30 | $2.00 | |
| 12 | 25100115 | MULCH METHOD 2 | 0.4 | ACRE | $2,662.20 | $2,900.00 | $4,800.00 | |
| 13 | 28000250 | TEMP EROS CONTR SEED | 40 | POUND | $3.96 | $22.00 | $2.00 | |
| 14 | 28000400 | PERIMETER EROS BAR | 1,360 | FOOT | $3.48 | $2.30 | $3.70 | |
| 15 | 35101600 | AGG BASE CSE B 4 | 865 | SQ YD | $13.57 | $8.00 | $32.75 | |
| 16 | 42400200 | PC CONC SIDEWALK 5 | 6,840 | SQ FT | $7.13 | $9.00 | $6.50 | |
| 17 | 42400800 | DETECTABLE WARNINGS | 41 | SQ FT | $25.44 | $35.00 | $24.00 | |
| 18 | 44000500 | COMB CURB GUTTER REM | 58 | FOOT | $38.26 | $18.00 | $45.00 | |
| 19 | 44000600 | SIDEWALK REM | 212 | SQ FT | $2.35 | $3.50 | $2.75 | |
| 20 | 60255500 | MAN ADJUST | 2 | EACH | $616.57 | $1,300.00 | $525.00 | |
| 21 | 60266600 | VALVE BOX ADJ | 1 | EACH | $363.39 | $850.00 | $190.00 | |
| 22 | 60605000 | COMB CC&G TB6.24 | 58 | FOOT | $71.44 | $45.00 | $104.00 | |
| 23 | 67100100 | MOBILIZATION | 1 | L SUM | $6,350.00 | $10,000.00 | $6,450.00 | |
| 24 | 78001130 | PAINT PVT MK LINE 6 | 165 | FOOT | $3.73 | $20.00 | $2.50 | |
| 25 | 78001180 | PAINT PVT MK LINE 24 | 103 | FOOT | $6.92 | $35.00 | $2.50 |