Bid tab 68G28

Let Mar 11, 2022 · District 4 · Peoria, Tazewell Sign up free

‹ Mar 2022 results

(46-1,11)CJS

Let date
Friday, March 11, 2022
Contract
68G28 · job page
District
District 4
County
Peoria, Tazewell
Highway
Limits
Crack and Joint Sealing on US 24/IL 9 from N of Pfeiffer Rd in Bartonville to 0.16 mi SW of IL 9 (E.) and on IL 29 from Margaret Drive in Creve Coeur to N of LaSalle BLVD in Marquette Heights.

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Denler, Inc. Low bidder $214,975
2 Freehill Asphalt, Inc. $225,523 +4.9%
3 Complete Asphalt Service Co. $272,117 +26.6%
4 SKC Construction, Inc. $425,267 +97.8%

Bid tab: unit prices 7 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Denler, Inc.#2 Freehill Asphal…#3 Complete Asphal…#4 SKC Constructio…
1X4510100 CRACK ROUTING/FILLING86,857POUND $0.2100 $0.5200 $0.7500 $2.46
2X7010216 TRAF CONT & PROT SPL1L SUM $18,000.00 $35,000.00 $90,158.00 $28,000.00
367100100 MOBILIZATION1L SUM $12,500.00 $13,500.00 $16,300.00 $20,000.00
470107025 CHANGEABLE MESSAGE SN10CAL DA $225.00 $260.00 $220.00 $100.00
578009004 MOD URETH PM LINE 4122,907FOOT $1.00 $0.7000 $0.5900 $0.9900
678009006 MOD URETH PM LINE 615,680FOOT $1.50 $1.48 $0.9400 $1.49
778009008 MOD URETH PM LINE 88,779FOOT $2.00 $2.28 $1.26 $2.00