18Let jobs
$84,432,766Total low bids
$86,295,168Total estimates
-2.2%Low bids vs estimates
Nov 2013 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Nov 21, 2013 | 130395NHPPY-257N(020)SS | Osage Division 8 |
GRADE, DRAIN, SURFACE , AND BRIDGE US-60: FROM 2.0 MILES EAST OF SH -99, EXTEND EAST. PROJECT LENGTH = 5.821 MILES · | $43,721,903 | $36,982,702 | SHERWOOD CONSTRUCTION CO., INC. | -15.4% | 5 |
| Nov 21, 2013 | 130408NHPPY-245N(018) | Mccurtain Division 2 |
GRADE, DRAIN, SURFACE , AND BRIDGE US-70: FROM 6.2 MILES EAST OF US -259, EXTEND EAST. PROJECT LENGTH = 3.296 MILES · | $14,761,511 | $16,135,411 | THE CUMMINS CONSTRUCTION CO., INC. | +9.3% | 2 |
| Nov 21, 2013 | 130403SSP-268N(011)SS | Sequoyah Division 1 |
GRADE, DRAIN, SURFACE , AND SITE PLAN I-40: TRUCK WEIGH STATION /PORT OF ENTRY LOCATED 2.4 MILES WEST OF THE ARKANSAS STATE LINE . · | $6,571,300 | $6,445,457 | DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV | -1.9% | 2 |
| Nov 21, 2013 | 130409SSP-216N(025)SB | Comanche Division 7 |
BRIDGE AND APPROACHES I -44: MULTIPLE LOCATIONS AT TRI-LEVEL INTERCHANGE IN LAWTON . PROJECT LENGTH = 0.460 MILES · | $5,339,123 | $5,496,321 | Allen Contracting, Inc. | +2.9% | 2 |
| Nov 21, 2013 | 130407SSP-176B(195)SS | Woods Division 6 |
BRIDGE AND APPROACHES US -64: OVER RED HORSE CREEK, 5.3 MILES EAST OF SH -50. PROJECT LENGTH = 1.012 MILES · | $5,237,276 | $5,045,921 | Venture Corporation dba VCO Paving | -3.7% | 3 |
| Nov 21, 2013 | 130396STP-158C(147)CI | Ottawa Division 8 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-6): OVER NEOSHO RIVER, 2.3 MILES EAST OF THE CRAIG COUNTY LINE . PROJECT LENGTH = 0.593 MILES · | $4,437,198 | $4,796,046 | A. M. COHRON & SON, INC. | +8.1% | 4 |
| Nov 21, 2013 | 130404SSP-268N(012)SS | Sequoyah Division 1 |
FACILITY PLAN I-40: TRUCK WEIGH STATION /PORT OF ENTRY LOCATED 2.4 MILES WEST OF THE ARKANSAS STATE LINE . PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTABLE . · | — | $2,814,188 | Crossland Construction Company, Inc. | 1 | |
| Nov 21, 2013 | 130388SSP-124C(103)SS | Garfield Division 4 |
BRIDGE AND APPROACHES SH -132: OVER TURKEY CREEK , 13.3 MI NORTH OF THE KINGFISHER COUNTY LINE . PROJECT LENGTH = 0.338 MILES · | $1,894,878 | $1,970,322 | OBC, INC. | +4.0% | 3 |
| Nov 21, 2013 | 130391SSR-236B(006)SR | Kay Division 4 |
RESURFACE (ASPHALT ) US-77: FROM SH-11 WEST, EXTEND NORTH THEN EAST . PROJECT LENGTH = 5.29 MILES · | $1,089,970 | $1,249,769 | Evans & Associates Construction Co., Inc. | +14.7% | 1 |
| Nov 21, 2013 | 130384STP-NBIL(228)CI | Carter Division 7 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-190): OVER WALNUT CREEK , 0.3 MILES WEST OF SH-76. PROJECT LENGTH = 0.220 MILES · | $694,419 | $772,257 | K & R BUILDERS, INC. | +11.2% | 2 |
| Nov 21, 2013 | 130390STP-132C(152)CI | Hughes Division 3 |
BRIDGE AND APPROACHES COUNTY ROAD : OVER CANEY BOGGY CREEK , 7.3 MILES SOUTH AND 3.5 MILES WEST OF STUART . PROJECT LENGTH = 0.293 MILES · | $752,940 | $675,570 | BRIDGECO CONTRACTORS, INC. | -10.3% | 3 |
| Nov 21, 2013 | 130393STP-152D(187)CI | Noble Division 4 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-48): OVER COW CREEK, 7.0 MI WEST OF SUMNER. PROJECT LENGTH = 0.155 MILES · | $617,481 | $569,207 | BELK BRIDGE, INC. | -7.8% | 6 |
| Nov 21, 2013 | 130369STP-NBIL(062)CI | Murray Division 7 |
BRIDGE AND APPROACHES COUNTY ROAD : OVER BUCKHORN CREEK 3.9 MILES SOUTH AND 4.0 MILES EAST OF THE SOUTH US -177/SH-7 JCT. PROJECT LENGTH = 0.197 MILES · | $336,923 | $404,920 | K & R BUILDERS, INC. | +20.2% | 4 |
| Nov 21, 2013 | 130365STP-229D(002)CI | Harmon Division 5 |
BRIDGE AND APPROACHES COUNTY ROAD (NS-176): OVER AN UNNAMED CREEK , 1.1 MILES SOUTH AND 4.5 MILES EAST OF SH -9/SH-30 JCT. PROJECT LENGTH = 0.215 MILES · | $369,888 | $365,920 | KLAVER CONSTRUCTION COMPANY, INC. | -1.1% | 4 |
| Nov 21, 2013 | 130400SSR-261N(022)SR | Pittsburg Division 2 |
RESURFACE (ASPHALT ) US-69: FROM US-69B AND 2.6 MILES NORTH OF US -69B, EXTEND NORTH . PROJECT LENGTH = 0.540 MILES · | $306,273 | $340,165 | JOB CONSTRUCTION CO., INC. | +11.1% | 2 |
| Nov 21, 2013 | 130406STPY-273C(009)RW | Wagoner Division 1 |
RIGHT-OF-WAY CLEARANCE SH-16: FROM JUST NORTHWEST OF OKAY , EXTEND NORTH . PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTABLE . · | — | $151,930 | M & M WRECKING, INC. | 5 | |
| Nov 21, 2013 | 130385STP-214C(007)AG | Cleveland Division 3 |
SIDEWALK IMPROVEMENT CITY STREET (BOYD ST.): FROM CLASSEN BLVD TO BARKLEY STREET IN NORMAN. PROJECT LENGTH = 0.475 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED . BOTH BID EXPRESS AND WRITTEN BIDS WILL BE ACCEPTABLE . · | $164,085 | $122,800 | RDNJ, INC. DBA A-TECH PAVING | -25.2% | 9 |
| Nov 21, 2013 | 130386HSIP-216C(026)TR | Comanche Division 7 |
TRAFFIC SIGNAL US-277: AT THE INTERSECTION OF SH-17 IN ELGIN. · | — | $93,858 | Midstate Traffic Control, Inc. | 3 |
1–18 of 18
Source: ODOT bid tabulations for each letting on Contracts and Proposals, read from ODOT's published bid tab reports, including the engineer's estimate. Bid Potato loads new lettings as ODOT posts them and backfills the last two years. Confirm against ODOT's official tabulations.