11Let jobs
$17,502,090Total low bids
$16,457,150Total estimates
+6.3%Low bids vs estimates
Jul 2012 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Jul 19, 2012 | 120130STP-114B(249)AG | Stp-155b(655)ag |
CLEVELAND, OKLAHOMA GRADE, DRAIN, AND SURFACE COUNTY ROAD (EASTERN AVE ): BEGIN ONE MILE EAST OF THE I-35/I-240 JCT EXTEND SOUTH . PROJECT LENGTH = 1.972 MILES · | $5,123,132 | $4,793,449 | DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV | -6.4% | 7 |
| Jul 19, 2012 | 120247NHY-022N(157) | Bryan Division 2 |
BRIDGE AND APPROACHES US -70: OVER BLUE RIVER 7.7 MILES EAST OF US -69B. PROJECT LENGTH = 0.738 MILES · | $4,690,582 | $4,555,101 | L & N BRIDGE, LLC | -2.9% | 4 |
| Jul 19, 2012 | 120196HSIPG-013N(156)TR | Hsipg-013n(157)tr |
BRYAN SAFETY IMPROVEMENT (CABLE BARRIER AND INTERSECTION MODIFICATION ) US-69: FROM JUST NORTH OF COLBERT EXTEND NORTH , AND FROM BLUE RIVER EXTEND NORTH . PROJECT LENGTH = 13.109 MILES · | $1,900,267 | $2,115,064 | Midstate Traffic Control, Inc. | +11.3% | 2 |
| Jul 19, 2012 | 120248BRFY-107B(151) | Bryan Division 2 |
BRIDGE AND APPROACHES US -69B: OVER MINERAL BAYOU CREEK 0.5 MILE SOUTH OF US-70. PROJECT LENGTH = 0.152 MILES · | $1,476,397 | $1,417,551 | L & N BRIDGE, LLC | -4.0% | 3 |
| Jul 19, 2012 | 120230HSIPIG-0244-1(009)000TR | Tulsa Division 8 |
SAFETY IMPROVEMENT (CABLE BARRIER) I-244: BEGIN AT MILE MARKER 0, EXTEND NORTH . SH-11: FROM HARVARD AVE OVERPASS , EXTEND SOUTHEAST. · | — | $1,124,671 | ACTION SAFETY SUPPLY CO., LLC | 3 | |
| Jul 19, 2012 | 120182STPG-140A(211)TR | Leflore |
SAFETY IMPROVEMENT (CONCRETE BARRIER WALL ) US-259: BEGIN 3.36 MILES SOUTH OF SH-63, EXTEND SOUTH. PROJECT LENGTH = 0.221 MILES · | $839,899 | $1,033,891 | MANHATTAN ROAD & BRIDGE COMPANY, LLC | +23.1% | 2 |
| Jul 19, 2012 | 120171SBR-255A(063)SB | Oklahoma Division 4 |
BRIDGE REPAIR I-44: OVER THE OKLAHOMA RIVER IN OKLAHOMA CITY. · | $993,596 | $785,150 | GIBSON & ASSOCIATES, INC. | -21.0% | 3 |
| Jul 19, 2012 | 120249BRF-NBIL(223)CI | Carter Division 7 |
BRIDGE AND APPROACHES COUNTY ROAD (EW-200): OVER TRIBUTARY OF WALNUT BAYOU CREEK 4.0 MILES SOUTH AND 4.6 MILES EAST OF THE US -70/SH-76 JCT. PROJECT LENGTH = 0.340 MILES · | $562,904 | $604,283 | Reece Construction Co, Inc. | +7.4% | 5 |
| Jul 19, 2012 | 120217STPG-155F(424)AG | Canadian, Cleveland, Oklahoma |
SAFETY IMPROVEMENTS (SCHOOL ZONES ) CITY STREETS : MULTIPLE LOCATIONS IN THE OKLAHOMA CITY METRO . · | $493,347 | $475,930 | Midstate Traffic Control, Inc. | -3.5% | 3 |
| Jul 19, 2012 | 120246HSIPG-205F(014)TR | Beckham, Blaine, Custer, Dewey, Jackson |
STRIPING AND PAVEMENT MARKING I -40/US-62/US-183/US-270/US-283/SH-6/SH-3/SH-33: MULTIPLE LOCATIONS IN DIVISION V. · | $377,027 | $300,000 | Direct Traffic Control, Inc. | -20.4% | 3 |
| Jul 19, 2012 | 120245HSIPG-203F(008)TR | Atoka, Bryan, Choctaw, Mccurtain, Pittsburg |
STRIPING AND PAVEMENT MARKING US -69/US-70/US-70B/US-271B: MULTIPLE LOCATIONS IN DIVISION II. · | — | $297,000 | Direct Traffic Control, Inc. | 4 |
1–11 of 11
Source: ODOT bid tabulations for each letting on Contracts and Proposals, read from ODOT's published bid tab reports, including the engineer's estimate. Bid Potato loads new lettings as ODOT posts them and backfills the last two years. Confirm against ODOT's official tabulations.