BRIDGE AND APPROACHES COUNTY ROAD (NS-176): OVER AN UNNAMED CREEK , 1.1 MILES SOUTH AND 4.5 MILES EAST OF SH -9/SH-30 JCT. PROJECT LENGTH = 0.215 MILES
- Let date
- Thursday, November 21, 2013
- Contract
- 130365
- J/P numbers
- 28701(04)
- District
- Division 5
- County
- Harmon
- Highway
- Limits
- BRIDGE AND APPROACHES COUNTY ROAD (NS-176): OVER AN UNNAMED CREEK , 1.1 MILES SOUTH AND 4.5 MILES EAST OF SH -9/SH-30 JCT. PROJECT LENGTH = 0.215 MILES
- Project number
- STP-229D(002)CI
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $369,888 | ||
| 1 | KLAVER CONSTRUCTION COMPANY, INC. Low bidder | $365,920 | -1.1% | |
| 2 | EARTH BUILDERS, L.P. | $376,136 | +1.7% | +2.8% |
| 3 | K & R BUILDERS, INC. | $399,491 | +8.0% | +9.2% |
| 4 | Frontier Bridge, Inc. | $403,218 | +9.0% | +10.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 KLAVER CONSTRUC… | #2 EARTH BUILDERS,… | #3 K & R BUILDERS,… | #4 Frontier Bridge… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 202(H) 0185 | EARTHWORK | 1 | LSUM | $40,000.00 | $54,200.00 | $33,000.00 | $38,750.00 | $54,600.00 |
| 2 | 221(C) 2801 | TEMPORARY SILT FENCE | 500 | LF | $1.75 | $2.50 | $2.00 | $1.95 | $2.62 |
| 3 | 221(F) 0100 | TEMPORARY SILT DIKE | 300 | LF | $9.00 | $8.00 | $5.00 | $7.75 | $8.40 |
| 4 | 230(A) 2806 | SOLID SLAB SODDING | 8,500 | SY | $1.75 | $1.62 | $2.00 | $1.87 | $1.70 |
| 5 | 233(A) 2817 | VEGETATIVE MULCHING | 1.76 | AC | $450.00 | $800.00 | $2,500.00 | $550.00 | $840.00 |
| 6 | 402(E) 0225 | TRAFFIC BOUND SURFACE COURSE TYPE E | 561 | TON | $30.00 | $32.00 | $60.00 | $34.25 | $33.60 |
| 7 | 509(D) 0325 | CLASS C CONCRETE | 10 | CY | $300.00 | $350.00 | $350.00 | $290.00 | $371.66 |
| 8 | 601(B) 1353 | TYPE I-A PLAIN RIPRAP | 869 | TON | $35.00 | $45.00 | $50.00 | $46.29 | $47.25 |
| 9 | 601(C) 1355 | TYPE I-A FILTER BLANKET | 290 | TON | $30.00 | $36.00 | $40.00 | $35.29 | $37.80 |
| 10 | 613(B) 4528 | 28" X 20" CORR. GALV. STEEL PIPE ARCH | 118 | LF | $40.00 | $26.00 | $75.00 | $29.00 | $27.30 |
| 11 | 613(M) 7187 | TYPE B4 CULVERT END TREATMENT | 4 | EA | $1,100.00 | $1,500.00 | $1,000.00 | $1,375.00 | $1,000.00 |
| 12 | 202(A) 1301 | UNCLASSIFIED EXCAVATION | 1,246 | CY | $10.00 | $12.00 | $5.00 | $7.95 | $6.90 |
| 13 | 501(A) 1306 | STRUCTURAL EXCAVATION UNCLASSIFIED | 146 | CY | $12.00 | $5.00 | $10.00 | $13.25 | $28.75 |
| 14 | 509(A) 1326 | CLASS AA CONCRETE | 283.44 | CY | $500.00 | $398.00 | $400.00 | $540.00 | $420.34 |
| 15 | 511(A) 1332 | REINFORCING STEEL | 54,610 | LB | $0.9000 | $0.9000 | $1.00 | $0.9400 | $1.28 |
| 16 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $5,000.00 | $1,750.00 | $2,000.00 | $2,300.00 | $2,012.50 |
| 17 | 642(B) 0096 | CONSTRUCTION STAKING LEVEL II | 1 | LSUM | $5,000.00 | $7,500.00 | $5,000.00 | $8,900.00 | $8,250.00 |
| 18 | 220 2800 | SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM | $7,500.00 | $3,500.00 | $1,500.00 | $4,150.00 | $4,950.00 |
| 19 | 641 1399 | MOBILIZATION | 1 | LSUM | $20,000.00 | $22,437.00 | $30,000.00 | $27,500.00 | $30,000.00 |